140 likes | 274 Views
AGENDA ITEM NO 13 CLUSTER BOARD Date 14 July 2011. Contents. 1. Key Financial Performance Dashboard 2. Summary Financial Position 3. Risks 4. Cost Improvement Programme Performance PCT Performance Exception Report 6. Capital Investment Programme 7. Recommendations.
E N D
AGENDA ITEM NO 13 CLUSTER BOARD Date 14 July 2011
Contents • 1. Key Financial Performance Dashboard • 2. Summary Financial Position • 3. Risks • 4. Cost Improvement Programme Performance • PCT Performance Exception Report • 6. Capital Investment Programme • 7. Recommendations
3 Risks • There are a number of financial risks that are included in the PCTs’ forecast financial position however the magnitude and certainty of these risks is variable. The table on the previous page lists the major risks and the potential best and worst cases. Currently the most likely positions are included in the forecast outturns and are mitigated by contingencies, under spends on developments and strategic initiatives. • Each PCT has assessed the risks applicable to their financial position and commissioned services. Whilst some risks are specific to particular PCTs, the risks relating to secondary care contracts, QIPP delivery and prescribing spend are common to most PCTs. • This format of presenting financial risks is new to some PCTs, and therefore the information contained within this schedule at month two should be treated with caution. However, this will continue to be developed with Organisations. 6
4 Cost Improvement Programme (CIP) Performance • NHS Bury has the highest CIP target as a percentage of revenue resource limit, at £26.9m. Of this amount, £21.7m or 81% of the schemes are rated as high risk at month two, but this is a slight improvement over the plan position. However, achievement of CIP at month two is only £1.4m , which is £2.6m behind plan, but further analysis will be undertaken over the course of the next two months to evidence the savings. • NHS Manchester set an initial CIP target of £20.2m and then added a further 50% to allow for slippage on schemes, optimism bias, and to provide a potential contingency for any deterioration in the underlying financial position. Detailed plans have been drawn up by consortia leads and other budget holders to address £23m of the revised £30m target and are currently working on proposals to achieve the balance. However significant savings are anticipated from service agreements, with over 50% of the original target covered by block contract arrangements and therefore these have been achieved. The highest risk areas are in schemes to save costs in relation to secure mental health and running costs. • NHS Stockport is reporting achievement of £6.8m of the £8.2m CIP savings at month two, and £4.6m of this relates to a 2% reduction in elective and unscheduled care contracts. If these contracts over perform later in the year, the PCT will report this as a cost pressure rather than an underachievement of CIP. • NHS Bolton are currently forecasting an under achievement against their CIP plans of £3.4m, of which £2m is related to prescribing schemes and based on holding spend to 2010-11 levels, and £1.4m is for demand management schemes. However this is expected to improve as the programme takes effect but will be closely monitored.
5 PCT Performance Exception Report • PCTs are currently forecasting achievement of the planned surpluses totalling £14,717k. This is the surplus control total agreed with the Strategic Health Authority. Therefore achieving the planned 2% recurrent headroom target. • The year to date position is a surplus achieved of £2,167k against a budgeted position of £2,604k, with the majority of the underachievement contributed by NHS Ashton Leigh and Wigan, NHS Oldham and NHS Trafford. However, as expected at this stage of the financial year, many of the sources of information used to generate forecasts are not available, most notably prescribing, collaborative commissioning and other provider activity monitoring reports. Most PCTs have incorporated month one activity from their main provider into their forecasts. • NHS Bury has a number of financial recovery schemes in place, and those related to secondary care, prescribing and continuing care in particular have had a slower impact than anticipated. NHS Bury is forecasting achievement of the target surplus on the basis that in year savings on financial recovery schemes will be made to mitigate any recurrent shortfall. To date, there have also been non recurrent savings in other areas and work will be undertaken to secure these savings recurrently. • NHS Manchester has identified forecast overspends of £6.3m, mainly within prescribing (£2m), mental health non secure contracts (£2m) and specialist/collaboratively commissioned services (£1m). There are ongoing negotiations between NHS Manchester and Manchester City Council regarding the settlement of mental health non secure over performance for 2009-10, the 2010-11 mental health pool contribution and pooling resources for 2011-12. • Currently all PCTs are assuming that the full amount of the 2% non recurrent top slice will be returned in 2011-12 and be available for planned non recurrent expenditure.
5 PCT Performance Exception Report • NHS Oldham are in the process of developing dashboards to provide evidence – based reporting on CIP achievements including financial benefits realised, and therefore whilst “banked” savings at month two are low, it is anticipated these are understated. The financial position is being closely monitored by Cluster and Locality Director of Finance. 10
6 Capital Investment Programme • Although there has been very little expenditure to date on the capital programmes, all PCTs are forecasting to remain within the net Capital Resource Limit for 2011-12. • Approximately £6.3m of capital expenditure is dependent on the disposal of assets, all to non NHS bodies, and PCTs have programmed capital schemes to commence only when disposals are certain. However, there is a risk that if disposals are delayed until later in the year, that there will be insufficient time to complete planned schemes and there may be capital resource limit under spends which cannot be carried forward to 2012-13. • IT schemes total £4.4m and work is currently being undertaken to review the nature of planned expenditure and determine whether efficiencies in procurement and/or implementation are possible across the Greater Manchester footprint. 12
7 Future Performance Management Information • In future reports information will be presented on the following areas of financial performance • Performance against main provider contracts • Delivery of running cost targets/paybill • Non recurrent 2% expenditure plans
8 Recommendations • 8.1 The Cluster Board is asked to note the contents of the report. • 8.2 The Cluster Board is asked if the information contained within or proposed is sufficient to meet the needs of Board members, given full detailed financial reports will be prepared for Locality Boards. Any comments can be sent directly to Mrs C Yarwood.