1 / 6

ERCOT Program Management Update RMS Meeting – May 15, 2003 Steve Wallace

This update covers project progress, completed activities, and future initiatives in the ERCOT program. Includes new priorities, market coordination success, system improvements, and upcoming budget planning.

davidconte
Download Presentation

ERCOT Program Management Update RMS Meeting – May 15, 2003 Steve Wallace

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT Program Management Update RMS Meeting – May 15, 2003 Steve Wallace

  2. Project Updates Monthly Activity Project Performance • For the 50 Priority 1 Projects: • 18 are Complete • 20 are In Progress and • 12 are In Planning • New Projects Are Being Prioritized by the Market and ERCOT • The 18 Projects completed in 1st Quarter includes projects started in the last Quarter of 2002

  3. Project Updates Project Activity Highlights of Completions • TX Set V1.5 • Market coordination was key success factor (Thank You!) • Commercial Systems Disaster Recovery • Tested well below the 48 hour requirement • Trending Information: • Project Management staff added in 1st Qtr • Number of projects closed • Planning and Active projects will relate going forward • Major initiatives around market design, retail transaction performance, etc. are on the horizon • ERCOT 2004 Budget Planning starts in late June, completes in September

  4. Serve, Ensure, Protect and Operate Release 2.1 & 2.2 • Release 2.1 & 2.2 • EMS front end replacement • System map • Customized generation monitoring • Customized one line displays • EMP 2.2 upgrade • User interface enhancements related to resource plan and schedule changes • Ability to print resource plan • Market Monitoring • Additional development work with BOD approval • Simulation Engine Pilot - Plexos Technical Operations Releases Technical OperationsMarket OperationsEnterprise Operations Energy Management SystemsClearing, Settlement and Billing Portal / PUCT Market Interface Market Management Systems Market Relationship Management Transaction Management Transaction Processing Cyber Security Facilities Architecture and Maintenance 2nd Qtr 3rd Qtr 4th Qtr 2nd Qtr ‘04 4th Qtr ‘04 Release 2.0 Release 3.0 Release 3.1 Draft Release 4.0 • Release 3.0 & 3.1 • Mitigate constraint oscillation • Security constrained optimal power flow • Dynamic ratings • Load rollover during line outage • Multi-hour, multi-day outage evaluation studies • Special protection schemes in contingency analysis • VSAT/TSAT Interface upgrades • Enhance PTI export • Simultaneous A/S procurement (PRR342) • Balancing energy – ramp rates (PRR349) • Enhancements to BES and RPRS markets • RPRS market re-design (SCUC) • Association of BE bids with RPRS awards (PIP137PRR211) • Resource ramp rate constraints • Allow resource plan updates after adjustment period (PRR359) • Automate calculation and posting of CSC Limits • Handling of resources in Test Mode (PRR332) • Enhanced Market Monitoring • Day Ahead/Forward Market/Matching/Scheduling Engine • POS/MOS Design for new market model, Pilot? • Release 4.0+ • Texas Nodal, replace MOS • POS rollback or POS Replace to support Texas Nodal • Automate A/S qualification testing • Changes to A/S performance monitoring and frequency control algorithms • Remove BE and energy schedule dependencies on resource plan • Regulation service from loads (PRR307) • Fleet deployment of OOME? • Automated Market Power Mitigation Pilot • Real Time Market Indicies and Monitoring Release 2.0 • Direct weather data path to EMMS • Integrate OSI PI systems • Commission alarm system • Smoothing algorithm (PRR350) • Outage sensitivity factor • Outage scheduler customization • BULs and Blocked deployment (PIP112/PIP210) • Oracle 9i upgrade • QSEMOS web enhancements • Balancing energy deployment timing improvement • Market operator interface – printing requirements

  5. Serve, Ensure, Protect and Operate Market Operations Releases Technical OperationsMarket Operations Enterprise Operations Energy Management Systems Clearing, Settlement and BillingPortal & PUCT Market Interface Market Management SystemsMarket Relationship ManagementTransaction Management Transaction Processing Risk, Cyber Security, Facilities Architecture and Maintenance 2nd Qtr 3rd Qtr 4th Qtr 2nd Qtr ‘04 4th Qtr ‘04 Release 2.0 Release 2.1 & 2.2 Draft 3.1 Release 3.0 Draft Release 4.0 • Release 3.1 • MIMO/Stacking, TCH, Registration engines replacement/upgrade and Competitive Metering tied to major release timing • Texas Set Version 1.6 • Commercial Systems Performance Enhancements • -Forward Markets and • Forward Market Clearing Engine? • -Standardize Retail XML Transactions • -Texas Nodal Protocols, CBA and Rollout Plan • -Initial Enterprise and Risk Dashboard Capabilities • -PUCT & Market EDW • Release 4.0+ • -Texas Nodal Market System (clearing, scheduling, trading, balancing, billing and settlement tied to retail systems, slated for Mar 06) • -Texas Set Version 1.7 • -Full PUCT/MOD/RISK Market Analysis Portal and Reporting • Release 2.1 & 2.2 • -Competitive Metering for Large Non Res. Customers Pilot • -Proxy Day Determination Extensions • -EPS Meter Data Transmittal Via Extract • -Meter Data Loading Improvements • -Increased Number of Sub QSE’s • -Commercial Applications Development Environment • -RMC Redundancy • -TCR Redundancy • -OVWTA Combined Network Improvements • -Lawson & HR Upgrades • -Market Monitoring Pilot • -Increased Zones Study Request Release 3.0 -Load Profiling Enhancements -Build Load Research Sampling Capability -TCR Settlements Synchronization -MIMO/Stacking, TCH, Registration Replacement and Competitive Metering Design -Supplemental Load Profiling Improvements -Enhance ESI ID Lookup Capabilities Pilot -Invoice Generation Performance Enhancements -Hardening EDI TX Pipeline -EDI Pipeline Performance -DA/DW Redundancy -Rental/Build Facility Systems -Texas Nodal Design & Studies - Server Consolidation • Release 2.0 • -BUL and Blocked Deployment of LAR • -SCR 727 Extracts • -Combined Cycle Units • -Balancing Energy Mismatch Schedule • -GISB 1.4 Transport • -Texas Set Version 1.5 • -TX Set 1.5 ETS Changes • -EDI Pipeline Improvements • -Move In / Move Out Short Term Changes • -Retail Market Performance Measures • -Commercial Applications Disaster Recovery • -Upgrade Tape Backup System • -Austin Computer Room Expansion

  6. Ability to Assess our Project Portfolio

More Related