130 likes | 142 Views
MARS Taskforce. RMS Update October 19, 2011. ERCOT Board Meeting October 18, 2011. Commercial Market Operations Report http://www.ercot.com/content/meetings/board/keydocs/2011/1018/Item_04d_-_Commercial_Market_Operations_Report_-_Revised.pdf (see slide No. 9)
E N D
MARS Taskforce RMS Update October 19, 2011
ERCOT Board Meeting October 18, 2011 • Commercial Market Operations Report • http://www.ercot.com/content/meetings/board/keydocs/2011/1018/Item_04d_-_Commercial_Market_Operations_Report_-_Revised.pdf • (see slide No. 9) • Reflects that 3.7 Million ESI IDs were settled using AMS Meter data • 76.1% of the Load at ERCOT is settled with IDR data (This accounts for both AMS and IDR Meter Data)
AMS Meter Installation Status Report Oncor (approximately): • Installed: 2,122,793 as of 09.30.2011 • Deployment Plan: • 2010 – 929,000 meters • 2011 – 902,000 meters • 2012 – 902,000 meters
AMS Meter Installation Status Report CNP (approximately): • Installed: 1,725,986 as of 09.30.2011 • Deployment Plan, includes projected growth: • 2010 – 756,684 meters • 2011 – 960,327 meters • 2012 – 373,423 meters
AMS Meter Installation Status Report AEP (approximately): • Installed: 364,157 as of 09.30.2011 • Deployment Plan schedule: • 2010 – 188,212meters • 2011 – 251,571 meters • 2012 – 279,329 meters • 2013 – 278,280 meters
New Player to TEXAS AMS • Texas New Mexico Power (TNMP) started their AMS deployment on September 19, 2011: • Deployment Plan: • Approximately 240,000 AMS meters will be installed • Planned completion Q3 2016 • After 3 years of AMS deployment 70% of TNMP’s Customer Base will have an AMS meter that includes TNMP’s most populous areas.
AMS Meter Installation Status Report TNMP (approximately): • Installed: 1,160 as of 09.30.2011 • Deployment Plan schedule: • North Texas • Q4 2014 through Q3 2015 meters • Central Texas • Q3 2015 through Q1 2016 meters • West Texas • Q2 2016 through Q3 2016 meters
Market AMSInstalled Totals 4,214,096
PUCT Project 34610 Advanced Metering Implementation Team (AMIT) Documentation & Meeting Schedules can be found on: • Public Utility Commission of Texas Project 34610 AMIT Webpage: • http://www.puc.state.tx.us/industry/projects/electric/34610/34610.aspx
AMIT’s Working Group Schedule and Update • Registration, Administration & Access Working Group (RAAWG) • http://www.puc.state.tx.us/industry/projects/electric/34610/34610raawg.aspx • Operations and Maintenance Working Group (OMWG) • Every other Wednesday from 1-3 pm • http://www.puc.state.tx.us/industry/projects/electric/34610/34610omwg.aspx • Projects and Strategy Working Group (PSWG) • Every other Friday at 10:45 AM • http://www.puc.state.tx.us/industry/projects/electric/34610/34610pswg.aspx • Cyber Security Working Group (CSWG) • http://www.puc.state.tx.us/industry/projects/electric/34610/34610cswg.aspx
Advanced Metering Implementation Team (AMIT) • September 2011 • 27th meeting documents: • http://www.puc.state.tx.us/industry/projects/electric/34610/34610rel.aspx • OCTOBER 2011 (cancelled) • 24th (F2F) • Mon: 9:30 AM – 5:30 PM • AMIT Steering Committee meeting • Location: ERCOT Met Center Conference Room 206
Advanced Metering Implementation Team (AMIT) • november 2011 • 29th (F2F) • Tues: 9:30 AM – 5:30 PM • AMIT Steering Committee meeting • Location: ERCOT Met Center Conference Room 206 • December 2011 • 6th (F2F) • Tues: 9:30 AM – 5:30 PM • AMIT Steering Committee meeting • Location: PUCT Chairman Hearing Room (CHR) 7th Floor