Status of the CERN Control Centre D. Manglunki AB/OP.
E N D
Status of the CERN Control CentreD.Manglunki AB/OP D.Manglunki AB/OP
ACKNOWLEDGEMENTS:R.Bailey, J.-L.Baldy, M.Bätz, B.Frammery,R.Saban, L.SerioM.Delrieux, R.Giachino, S.Knoops, E.Liénard, L.Randot, L.StewartM.Clark, D.Hartley, J.Wood René Ballet, A.Bland, P.Charrue, J.J.Cloye, C.Frisk, R.HopkinsS.Anghelone, M.Poehler,P.VachettaL.Burguete-Oliete, M.Colin, R.Forrest, R.Lauckner D.Manglunki AB/OP
Outline • Update on OP days 4-5/3/2004 • Current plan: • 874 extension • Control desks • Layout • Staff • Schedule • Remaining issues D.Manglunki AB/OP
Current building extension plan • No budget for original plan • No closing of ex-CCR and ex-PCR • Loss of > 200m2 • No visitors’gallery • Combine conference room/remote MD/videoconference • No sacrifice on operators‘ facilities D.Manglunki AB/OP
Current building extension plan D.Manglunki AB/OP
Current building extension plan D.Manglunki AB/OP
Current building extension plan D.Manglunki AB/OP
Current building extension plan D.Manglunki AB/OP
Control system • Standard consoles for all desks… • …But different OS • 2006 start-up with existing 2004 applications • 4 different Access systems • SPS & EA as is • PS panels emulated • LHC new system D.Manglunki AB/OP
Control Desks • 3 screens control display • 3 screens fixed display (shared by 2) • 1 administrative PC(shared by 2) • 5.0 m radius • 0.65 m deep (+0.65 m) • 0.72 m high D.Manglunki AB/OP
Control Desks D.Manglunki AB/OP
Control Desks: 4 firms selected for tendering CWS Lund-Halsey Erich Keller D.Manglunki AB/OP
Control Desks: 4 firms selected for tendering CGM CWS Erich Keller Lund-Halsey D.Manglunki AB/OP
Layouts • 1 GTD • 2 CCD • 2 CCC-WG • 1 IDOC • Workshop held on 5/11CCC-WG, IDOC, CCD, S.Baird D.Manglunki AB/OP
Layout • 35 control console modules • 5 access console modules • 4 Mail/etc PC tables • 1 social area • Storage furniture Laura Stewart AT/ECR D.Manglunki AB/OP
Laura Stewart AT/ECR D.Manglunki AB/OP
Room ergonomics • Lighting • 7x11 direct/indirect (20%-80%) from ceiling provide background 200+ Lux • task lighting at workstation level • Acoustics • Ceiling, walls, floor & furniture acoustically treated • Acoustic screens behind consoles • RT<0.6s • Interior decoration • 3 Harmonious colour scheme • 4th chosen by IDOC D.Manglunki AB/OP
Mike Clark CCD D.Manglunki AB/OP
Mike Clark CCD D.Manglunki AB/OP
Mike Clark CCD D.Manglunki AB/OP
Mike Clark CCD D.Manglunki AB/OP
Staff policy • Mandate: “Define the operating scenario of the CCC and make recommendations about the management and possible harmonization of the various categories of personnel corresponding to the different CCC usages” • WG recommendation: 1 single group as soon as possible • merging TCR + MCR teams in 2005 • Method: establish scenario for 2010+ (“LHC steady state”) then study transition D.Manglunki AB/OP
Staff policy: LHC steady state (2010+) • 10 shift workers: • 6 senior operators: LHC, SPS, PS, PSB, TI, Cryo • 3 junior operators SPS, PS, TI/Cryo • 1 LHC EiC • Shift coordinator among senior operators • Experience of running accelerators • Good understanding of TI & Cryo • CP D D.Manglunki AB/OP
Staff policy: PS/SPS shutdown (2005) D.Manglunki AB/OP
Staff policy: LHC Hardware commissioning (2006-2007) D.Manglunki AB/OP
Staff policy: LHC start-up (2007-2008) D.Manglunki AB/OP
Staff policy: LHC steady state (2010+) D.Manglunki AB/OP
The (very tight) Planning: 59 weeks to go • 31/12/2004: CE Studies completed, call for tenders out, preparatory works completed; start of civil engineering • 1/11/2005: building ready; installation begins, followed by commissioning • 1/2/2006: CCC commissioned, ready for OP D.Manglunki AB/OP
Planning: 59 weeks to go D.Manglunki AB/OP
Status of the work • Concrete slab poured • PCR empty • Servers in BA3 • IT for consoles going out • … so far so good! D.Manglunki AB/OP
Remaining issues • Operators chairs • Access systems • Control system: when to converge? • Communications • Fast analog signals • Parking / Office space D.Manglunki AB/OP
Conclusions • The CCC project is now well on its way • Tight schedule but respected so far D.Manglunki AB/OP