An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of the CERN Control CentreD.Manglunki AB/OP D.Manglunki AB/OP

  2. ACKNOWLEDGEMENTS:R.Bailey, J.-L.Baldy, M.Bätz, B.Frammery,R.Saban, L.SerioM.Delrieux, R.Giachino, S.Knoops, E.Liénard, L.Randot, L.StewartM.Clark, D.Hartley, J.Wood René Ballet, A.Bland, P.Charrue, J.J.Cloye, C.Frisk, R.HopkinsS.Anghelone, M.Poehler,P.VachettaL.Burguete-Oliete, M.Colin, R.Forrest, R.Lauckner D.Manglunki AB/OP

  3. Outline • Update on OP days 4-5/3/2004 • Current plan: • 874 extension • Control desks • Layout • Staff • Schedule • Remaining issues D.Manglunki AB/OP

  4. Current building extension plan • No budget for original plan • No closing of ex-CCR and ex-PCR • Loss of > 200m2 • No visitors’gallery • Combine conference room/remote MD/videoconference • No sacrifice on operators‘ facilities D.Manglunki AB/OP

  5. Current building extension plan D.Manglunki AB/OP

  6. Current building extension plan D.Manglunki AB/OP

  7. Current building extension plan D.Manglunki AB/OP

  8. Current building extension plan D.Manglunki AB/OP

  9. Control system • Standard consoles for all desks… • …But different OS • 2006 start-up with existing 2004 applications • 4 different Access systems • SPS & EA as is • PS panels emulated • LHC new system D.Manglunki AB/OP

  10. Control Desks • 3 screens control display • 3 screens fixed display (shared by 2) • 1 administrative PC(shared by 2) • 5.0 m radius • 0.65 m deep (+0.65 m) • 0.72 m high D.Manglunki AB/OP

  11. Control Desks D.Manglunki AB/OP

  12. Control Desks: 4 firms selected for tendering CWS Lund-Halsey Erich Keller D.Manglunki AB/OP

  13. Control Desks: 4 firms selected for tendering CGM CWS Erich Keller Lund-Halsey D.Manglunki AB/OP

  14. Layouts • 1 GTD • 2 CCD • 2 CCC-WG • 1 IDOC • Workshop held on 5/11CCC-WG, IDOC, CCD, S.Baird D.Manglunki AB/OP

  15. Layout • 35 control console modules • 5 access console modules • 4 Mail/etc PC tables • 1 social area • Storage furniture Laura Stewart AT/ECR D.Manglunki AB/OP

  16. Laura Stewart AT/ECR D.Manglunki AB/OP

  17. Room ergonomics • Lighting • 7x11 direct/indirect (20%-80%) from ceiling provide background 200+ Lux • task lighting at workstation level • Acoustics • Ceiling, walls, floor & furniture acoustically treated • Acoustic screens behind consoles • RT<0.6s • Interior decoration • 3 Harmonious colour scheme • 4th chosen by IDOC D.Manglunki AB/OP

  18. Mike Clark CCD D.Manglunki AB/OP

  19. Mike Clark CCD D.Manglunki AB/OP

  20. Mike Clark CCD D.Manglunki AB/OP

  21. Mike Clark CCD D.Manglunki AB/OP

  22. Staff policy • Mandate: “Define the operating scenario of the CCC and make recommendations about the management and possible harmonization of the various categories of personnel corresponding to the different CCC usages” • WG recommendation: 1 single group as soon as possible • merging TCR + MCR teams in 2005 • Method: establish scenario for 2010+ (“LHC steady state”) then study transition D.Manglunki AB/OP

  23. Staff policy: LHC steady state (2010+) • 10 shift workers: • 6 senior operators: LHC, SPS, PS, PSB, TI, Cryo • 3 junior operators SPS, PS, TI/Cryo • 1 LHC EiC • Shift coordinator among senior operators • Experience of running accelerators • Good understanding of TI & Cryo • CP D D.Manglunki AB/OP

  24. Staff policy: PS/SPS shutdown (2005) D.Manglunki AB/OP

  25. Staff policy: LHC Hardware commissioning (2006-2007) D.Manglunki AB/OP

  26. Staff policy: LHC start-up (2007-2008) D.Manglunki AB/OP

  27. Staff policy: LHC steady state (2010+) D.Manglunki AB/OP

  28. The (very tight) Planning: 59 weeks to go • 31/12/2004: CE Studies completed, call for tenders out, preparatory works completed; start of civil engineering • 1/11/2005: building ready; installation begins, followed by commissioning • 1/2/2006: CCC commissioned, ready for OP D.Manglunki AB/OP

  29. Planning: 59 weeks to go D.Manglunki AB/OP

  30. Status of the work • Concrete slab poured • PCR empty • Servers in BA3 • IT for consoles going out • … so far so good! D.Manglunki AB/OP

  31. Remaining issues • Operators chairs • Access systems • Control system: when to converge? • Communications • Fast analog signals • Parking / Office space D.Manglunki AB/OP

  32. Conclusions • The CCC project is now well on its way • Tight schedule but respected so far D.Manglunki AB/OP