CKOV Progress 5-4-07. PMT Shields completed. Awaiting paint job - @Mississippi. PMT Enclosures parts @IIT begun (delrin material ordered). PMT selection at Trieste begun (April). LED Pulser Electronics and PMT HV Supply in hand. PMT Base v-1 @ FNAL complete.
E N D
CKOV Progress 5-4-07 • PMT Shields completed. Awaiting paint job - @Mississippi. • PMT Enclosures parts @IIT begun (delrin material ordered). • PMT selection at Trieste begun (April). • LED Pulser Electronics and PMT HV Supply in hand. • PMT Base v-1 @ FNAL complete. • CKOV Box Machining to begin @Iowa in May. • CKOV Steele Ordered IIT+Iowa (3wk delivery). • Nickel Plating company in hand. (2 wk turn around • Aerogel Order Placed by Dan. (April) • Aerogel Box dimensions checked- machining in May. • Schott Glass Window Vendor in hand. • Lexan Slumping Oven completed. • Oven Temperature Controller Completed. • Mirror slumping prototype tests completed. • Slumping of MICE prototypes to begin. • Fermilab Mirror coating schedule needs work. Eileen Hahn. • CKOV detectors ~600lb (270Kilo) ea • Fedex OxfordMississippi-OxfordUK ~$1000/500lb CKOV Progress Report, L. Cremaldi, 5-4-07
Back cover Steele frame(down) Steele sides Steele frame(up) front cover front mirrors side mirrors aerogel Schott glass window CKOV Exploded View window frame CKOV Progress Report, L. Cremaldi, 5-4-07
CKOV to Solid Works Translation- Checking • M. Reep has converted all drawings to Solid Works and has performed • dimensional checks. CKOV Progress Report, L. Cremaldi, 5-4-07
Aerogel Compartment • Delrin in hand • Matsushita will slice 6 corner panels at 45deg. • Machining to begin soon. CKOV Progress Report, L. Cremaldi, 5-4-07
Base Layout V1 - Sten Hansen - FNAL Sten has made first layout and we will begin prototype. Sockets on order. CKOV Progress Report, L. Cremaldi, 5-4-07
CKOV Progress Report, L. Cremaldi, 5-4-07 FiberGlass Oven Enclosure • Simple Fiberglass enclosure with heating elements- D. Summers design. • Lexan Slumping temperature ~ 150C • Temperature controller regulates to +-2 degC. • Preliminary testing finished and bending of MICE prototypes to begin. • Mirroring at FNAL ASAP. CKOV Progress Report, L. Cremaldi, 5-4-07
Commissioning Plan • Plan-A • - Mechanical parts to Mississippi ( June). • Practice Assembly + Light Leak Checking. • Begin shipping to RAL >July 4) • Cremaldi+Sanders to RAL July 15 - Aug 1. • Aerogel Assembly week-1 • Mechanical Assembly and Install week-2 • Plan-B • - Mechanical parts to FNAL ( June). • Practice Assembly + Light Leak Checking. • Begin shipping to RAL >July 4) • Cremaldi+Sanders to RAL July 15 - Aug 1. • Aerogel Assembly week-1 • Mechanical Assembly and Install week-2 CKOV Progress Report, L. Cremaldi, 5-4-07