1 / 18

TRANSMISSION INVESTMENT ( or - Living on the Reliability knife-edge)

TRANSMISSION INVESTMENT ( or - Living on the Reliability knife-edge). Gordon Jardine. 2 April 2004. It’s about RELIABILITY.

elks
Download Presentation

TRANSMISSION INVESTMENT ( or - Living on the Reliability knife-edge)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TRANSMISSION INVESTMENT (or - Living on the Reliability knife-edge) Gordon Jardine 2 April 2004

  2. It’s about RELIABILITY “the (UK) regulator’s concern to reduce costs to consumers should now be tempered by a greater emphasis on ensuring that electricity network owners have the financial resources to secure a viable, long term electricity supply” UK House of Commons Committee 2004

  3. And so says a major user “I would like to acknowledge and congratulate Powerlink for your commitment to ensuring more reliable and quality electricity supply throughout South-East Queensland” “If the Refinery experiences power failure, even for a short period, we experience an unplanned shutdown which can affect the plant for a considerable period of time” “investment in energy infrastructure … has helped ensure reliable electricity supply to business customers including Caltex” Caltex Refinery Manager - 5 March 2004

  4. Overview • How the existing capex framework delivers very good outcomes for customers • How the proposed framework - as written - creates a serious threat to reliability • Is it possible to create a light-handed, capped framework which delivers better outcomes than the present framework?

  5. Some background • PQ capex allowance $1040M = replacement life of 45 years and load growth 3.5% p.a. • BUT…..load growth so far is 6.6% p.a., and now forecast at 6% for next 3 years • Material difference - now MUST accelerate network development (and capex spend) in the face of accelerated load growth in order to maintain reliability • To deliver mandated reliability, actual capex spend MUST exceed original allowance

  6. Good outcome for customers • Reliability can be maintained … “Just in time” • TUOS price path in Qld is flat in real terms • Get no customer complaints about TUOS (only 8% of total delivered cost) • DO get customer concerns about reliability, and requests about assuring future reliability (major customers to government)

  7. Ex-post review by ACCC • PQ confident it can justify extra capex spend … load growth : around 6% p.a.vs allowance based on 3.5% p.a. • Peak demand for 2003/04 summer: - 10% POE forecast was 7380MW (at time of reset) - actual 7934MW • Well documented Regulatory tests: - 9 major ($23M to $71M); plus 9 small, so far • Regulatory tests included capex cost sensitivity; no majorblow-outs

  8. Ex-post review by ACCC • Regulatory tests supported by retailer/distributor which pays the TUOS from its capped retail price - very compelling • Grid is very heavily loaded and high load growth - thus negligible optimisation risk • Review should not be traumatic for ACCC or PQ

  9. “Just in time” Reliability • 2 major augmentations in SEQ commissioned on13 December 2003 • First new record demand on 23 December 2003 • New network elements were needed to ensure reliability of supply - only 10 days to spare! • In a high load growth environment, no time for “regulatory roadblocks” • Or for dispute provisions which allow “nimbies” and vexatious parties to delay

  10. Litmus test for new framework • Benchmark - outcomes vs. existing framework • Can reliability be maintained if load growth accelerates? • For accelerated load growth: Action needed - immediately accelerate network development (capex spend) Offered - STOP (“off ramp”) for a regulatory review • New framework FAILS the reliability litmus test !

  11. “Regulatory Roadblocks” • ACCC document contains various proposals for the regulator to “pull over” sets of projects during the period - eg large, uncertain, new load growth, etc….. • These roadblocks don’t add value, but do cause delays and reliability risk • They convert “just in time” to “way too late”

  12. Apparent policy shift ? • FROM: “ensure reliability, with some risk to TUOS price” • TO: “ price is sacrosanct, reliability is sacrificeable” • NOTE: Reliability is NOT discretionary

  13. This is NOT the UK UKQld Load growth p.a. 1.8% ~6.0% Grid standard N - 2 N - 1 or less Grid topology Meshed Long, thin

  14. Capital Expenditure Profile 350 300 Regulated capex allowance 250 200 150 100 50 Regulatory Period 98/99 99/00 00/01 01/02 02/03 03/04 04/05 05/06 06/07 07/08 08/09 09/10 Year AREA OF HIGH RISK EXPOSURE

  15. Is there a better way ? • Possible to design a light-handed, capped capex framework which: - enables reliability to be maintained- minimises the risk of regulator-induced reliability failures- avoids windfall gains • Requires a “paradigm shift” in thinking, away from UK/low load growth experience with its presumptions of predictability and stability

  16. A formularised capex cap for reliability capex • Cap for reliability/load growth capex = f (actual load growth in regulatory period) • Thus, cap automatically adjusts each year in response to load growth • No delays to development if load accelerates - no need for “regulatory roadblocks” or “off ramps” • No need for regulator to estimate capex/load growth - a low estimate could threaten reliability

  17. A formularised capex cap for reliability capex • Eliminates windfall gains due to load forecasting error (over-estimate) • Retain Regulatory test (in simplified form) • Could use hybrid approach - list of projects for year 1 (where there is a high degree of certainty); then formula for years 2 through 5 • End-of-life replacement capex ( predictable, but variable period-to-period) can be readily added in.

  18. Other matters • Non-reliability augmentations e.g interconnectors / intra-connectors : exclude from cap, handle on an individual project basis as they arise, using full-blown Regulatory test , with ACCC as final arbiter • Disputes - no “nimby” disputes on any projects - and, for reliability projects, only those paying material extra TUOS can dispute

More Related