Agenda • Patch 4 Testing Status / MEM-EWR Installs • MEM / EWR Operational Trials Status/Results • Patch 5 / Build 7 Status • MEM Test NCP Extension: JW925-FDIO-1001 / T34501
Current DTAP Patch 4 Outlook • 6/4: Factory Acceptance Testing Completed @ Thales • 6/5: Patch 4 Installed at the WJHTC • 6/6-14: Patch 4 Testing at the WJHTC • 6/17: EWR Install • 6/18-20: EWR Pre-SAT Testing • 6/24: MEM Install (Includes UPS upgrade) • 6/25-27: MEM Pre-SAT Testing along with proposed 6/27 MGT demo - 24x7 Checkpoint
MEM Trials Current Status • Continued FDX Limited Ops (As of 6/13): • 35 to 50 DCL ops ‘shakeout’ period (20 MD-11, 15 B777 ops minimums) • 36 successful CAF DCL issued since April 17 start (28 MD-11, 8 B777) • 34 CAF, 2 UM80 Initial DCLs Issued • 5 UM79 , 3 UM80 Revisions issued • Additional ops up to 6/23 planned • MD-11 UM79 Revisions stopped after May 3 Op due to FDX FD observed en-route FMS Map ‘To Point’ Magenta Line re-draw (back to original route): • Boeing/Honeywell identified and can reproduce issue • Procedural Work around being presented to Flight Deck Working Group at Boeing/Long Beach • EWR/UPS MD-11 to try to duplicate issue • MEM 24x7 Trials Ops ‘Go’ Date pending FDX work around acceptance
EWR Trials Current Status • Continued Limited Ops (As of 6/13): • 6 successful CAF DCL issued since May 16 start (3 MD-11, 2 B777, 1 A340) • 6 CAF DCLs Issued • 2 UM79 , 1 UM80 Revisions issued • Additional ops up to 6/14 planned • Limited Trials Ops can resume 6/21 • Additional ATC DTAP support expected after 6/21 or Refresher Training • Domestic and International Participation: • UPS • BAW • SAS • FDX (pending first Revenue operation) • DLH, DLH Cargo, Swiss Air (pending initial testing)
DTAP Patch 5 and Build 7 Status • DTAP Patch 5 Requirements / Delivery Status: • EWR ATC Requirements (4 Total) • Thales cost/schedule proposal currently undergoing Gov evaluation • Dual Contact / Drop Down Remarks proposal for a summer delivery • Remaining Requirements delivery proposal moved to late Fall • Combine remaining reqs with pending Build 7 proposal/estimate • Thales to Scope Build 7 Requirements for Scope, Schedule Cost: • FAA options to select specific functionality based on schedule/cost consideration • Build Contract Acceptance and Delivery to FAA currently TBD
MEM/EWR Test NCP Status MEM Test NCPs: JW925-HNL-1004 / T34840ZME HADDS Connection (EXTENSION) NAS CCB Approved – 5/2/2013JW925-FDIO-1001 / T34501MEM DTAP FDIO/PCRCU Echo Port ConnectionNCP Issuance Date - 8/25/2012 EWR Test NCPs: JW925-HNL-1003 / T34752ZNY HADDS Connection NAS CCB Approved – 5/2/2013JW925-FDIO-1002 / T34753EWR DTAP FDIO/PCRCU Echo Port Connection NAS CCB Approved – 5/2/2013JW925-ATCT-1002 / T34759EWR DTAP Equipment Space ESA Approved – 3/4/2013