Data Communications Program MEM/EWR ATCT DCL Trials Status / Overview DCIT #27 Plenary From: Matt Maki / DCL Trials Lead Date: 09.26.2013
DTAP SW Patch 5.0 Update • Included Requirements: • SID NONE (EWR ATC) • MAINT ALT NONE (EWR ATC) • Double TO (MD-11 UM79 Map Redraw) • Dual Contact/Drop Down Remarks (EWR ATC) • Discovered automation issues being corrected: • PTR #171 – Early P+30 AH processing • PTR #172 – AGDS Index Management (3000 limit) • FAT scheduled for 10/7 @ Thales CC: • Early Thales Test Book look
DTAP SW Patch 5.0 Schedule • WJHTC Install/SAT – 10/8: • Start of Data Comm lab Functional Testing • Thales and PO Ops Support • MEM/EWR Site Install Go/No-Go Trigger • MEM Install/SAT – 10/14-16: • Holiday install • Pre-SAT/SAT procedure development (Airline support) • 10/16 PM FDX will fly MD-11 UM79 DCT TO flight as part of SAT (voice read back) • Goal is DTAP RTS for 10/17 FDX AM push • EWR Install/SAT – 10/21-23: • Pre-SAT/SAT procedure development (Airline support) • 10/21 PM UPS will fly B767 flight as part of SAT (voice read back) • Goal is DTAP RTS for 10/23 evening DCL ops
Build 7 Req Update • Down selected Requirements Proposal Evaluation Underway: • Harris/Thales proposal response pending • 4 Requirements under consideration: • Flight Deck Response to AOC • Climb Via • Departure Processing • Arrival Processing • Formal Harris Task Order CSP Trials Services and DTAP license pick up Oct 1
Running 76% success • FDX Crew DCL Familiarity Increasing • 2 Performance Issues Discovered: • Early P+30 AH causes inactive SEND button • AGDS Index Management Over 3000 Causes Random DM25 UL Fails • FDX GOC Revert to PDC Ops Success Proven Upon DTAP Outage (9/20 AM Push) • Continued weekend ZME ERAM Testing: • HADDS Recons triggered • 9/28-29 48 Hr ERAM run planned (0530z - 0300z)
EWR DCL Limited Ops Update • UAL 10 Revenue DCL Ops Complete (9/3-17): • B767 ops (LSZH/ZRH, LTBA/IST, SAEZ/EZE) • UAL 757/767 Fleet Tech Mgr/Flight Standards on-site to brief each crew • Agreement with FAA AFS to complete 20-25 DCL ops before expanded UAL ops (B777 Oct +) • DLH, UPS, BAW, FDX Continuing DCL Ops: • DLH 2/day schedule (EDDM, EDDL) • UPS, BAW, FDX continued limited ops • SAS no longer actively participating (Airbus CLR7+ FMS issue) • Seeking expanded Airline Participation
Additional Misc. MEM/EWR Items • 10/1 Outreach Briefing to the Newark International Carrier Committee (NICC): • Provide Trials overview to attending International Carriers • Solicit interest in new EWR Trials participants • 9/18-19 Additional MEM Tech Ops technicians received DTAP Cert Training: • 3 techs now certified at MEM • Expands DTAP Re-Cert time options • MEM DTAP FDIO Connect Extension Out of Board Approval 9/13: • NAS CCB meeting acknowledge – 9/30
Questions ? KUSA