An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT Five-Year Transmission Plan Update Jeff Billo RPG Meeting

  2. 2009 5YTP Status • Report • Final report posted! • AC analysis • 2010 AC Case addendum report sent to TOs for comment • No voltage criteria violations • Some thermal exceedances • 2013 AC Case work ongoing RPG Meeting

  3. 2010 5YTP Reliability Analysis • 2015 Reliability Analysis • Initial n-1 reliability analysis complete • Initial generation outage analysis complete except for North/ North Central • Due to high load in North Central weather zone there is little reserve margin when large generation units are taken out of service in the region • Low wind scenarios under study RPG Meeting

  4. 2010 5YTP Reliability Analysis Tools • Powerworld SCOPF • Security Constrained Optimal Power Flow • Utilizes cost curve for each unit • Optimizes cost • Assigns penalty cost for every MVA overload • Can set to optimize for minimal change in dispatch • Performs AC contingency analysis then dispatches around problems • Must perform iteratively • Can have “see-saw” constraints • Reports “unenforceable constraints” for reliability problems that cannot be fixed with redispatch • Run times ~ 40-60 minutes for full AC SCOPF • **********Not an endorsement for Powerworld*********** RPG Meeting

  5. 2010 5YTP Reliability Analysis Tools • TARA SCRD • Transmission Adequacy and Reliability Assessment • Security Constrained Reliability Dispatch • Set to optimize for minimal change in dispatch • Assigns penalty factor for every MVA overload • Can also run SCOPF • Performs simultaneous DC contingency analysis and redispatch • Runs final AC powerflow check at end of run • May have slight overload in AC at end of run • Reports overloads in Excel spreadsheet for reliability problems that cannot be fixed with redispatch • Run times ~ 1 minute for SCRD • N-1-1 analysis • Runs contingency subset for first n-1 with full contingency set for second -1 • Performs SCRD (or SCOPF) for each of first contingency set run • Used to run generation outage analysis in 5YTP • Run times ~ 2-3 hours for ERCOT generation outage and full SCRD • **********Not an endorsement for TARA*********** RPG Meeting

  6. 2010 5YTP Low Wind Scenario Analysis • Low wind scenario(s) studied for reliability analysis • Purpose is to find local reliability problems if wind is not blowing at or near peak load • Scenario selection • Divided ERCOT into six wind generation regions • Similar to work done for SSWG wind dispatch analysis • McCamey, Central West, West Abilene, Lower Panhandle, Coast, Culberson County • Analyzed historical (2009) wind output in each region for ERCOT load above 60,000 MW • 76 hours in 2009 • ~99th percentile load • ~95-100% peak load • Assumed low/ zero curtailment • at low wind generation output RPG Meeting

  7. 2010 5YTP Low Wind Scenario Analysis • Low wind scenario(s) data observations • Regional wind output has some correlation to system load (correlation factor not calculated) • Regional wind output data above 60 GW load does not fit a normal distribution • Data set for each region divided into six quantiles • 16.67% of data points will be lower than first quantile • 83.33% of data points will be higher than first quantile • 1st quantile represents similar statistical probability to one standard deviation below mean for a normal distribution (17%) 1st Quantile 16.67% 83.33% RPG Meeting

  8. 2010 5YTP Low Wind Scenario • Results of data analysis • Will create six low wind cases for reliability analysis • Each of six regions will have wind generation in respective region set to above output % • All other wind generation in case will be left at SSWG output levels RPG Meeting

  9. 2010 5YTP Reliability Analysis • Next Steps • Wrap-up 2015 reliability analysis • Perform project back-out to validate results • Send initial project set out for comment • Begin 2011-2014 reliability analysis RPG Meeting

  10. Questions? March 12, 2010 RPG Meeting