ERCOT Five-Year Transmission Plan Update

ERCOT Five-Year Transmission Plan Update. Jeff Billo. 2010 5YTP Reliability Analysis. 2011-2015 Reliability Analysis Updated set of reliability projects with required in-service dates posted Generation outage scenarios not completed for 2011-2014. 2010 5YTP Economic Analysis.

inez
Download Presentation

ERCOT Five-Year Transmission Plan Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT Five-Year Transmission Plan Update Jeff Billo RPG Meeting

  2. 2010 5YTP Reliability Analysis • 2011-2015 Reliability Analysis • Updated set of reliability projects with required in-service dates posted • Generation outage scenarios not completed for 2011-2014 RPG Meeting

  3. 2010 5YTP Economic Analysis • 2015 Assumptions • Case contains all CREZ transmission facilities • Case contains all existing generation plus plants with SGIAs • Recent retirements/ mothballs removed from service • Greens Bayou 5 and SR Bertron 1 and 2 removed • Gas price assumptions posted • Fayetteville-Zenith 345 kV project added as “first” economic project • 2015 Economic Analysis • Initial set of economic projects posted • 2011-2014 Economic Analysis • Initial analysis has just begun RPG Meeting

  4. Economic Analysis Update • Early plan included projects that changed the injection of west Texas plants from load serving system to CREZ facilities • Trent/ South Trent power injecting into Sweetwater East instead of Eskota • McAdoo power injecting into Cottonwood instead of Spur • These projects have been removed from the 2010 5YTP • Pending results of ABB CREZ Reactive Study • Pending NPRR 264 • Other policy issues may need to be addressed • May be added in future plans once the above issues get resolved RPG Meeting

  5. 2010 5YTP Update • Next Steps • Finish 2011-2014 reliability analysis (generator outage analysis) • Finish 2011-2015 economic analysis • CREZ-level generation analysis • Write draft report RPG Meeting

  6. Questions? March 12, 2010 RPG Meeting