EN/EL activities during LS1 Summary • Network infrastructure consolidation & upgrade 66 kV et 18 kV • UPS SILCON replacement project • Projects and maintenance work on substation 400 kV & 66 kV • Maintenance works on 18 kV, 3.3 kV and LV networks • Yearly tests • Other EN/EL consolidation & upgrade projects • Projects for other groups • R2E • Cables & fibres projects • Schedule • Workloads • Increase of manpower 2 12/06/2012 LS1 Day - François Duval EN-EL
66 et 18 kV Networks Consolidation & Upgrade • power cables replacement18 kV SPS • New substation BE91in Prévessin (Safe feeding of CCC safety network for SPS) • Repowering CCC • 66 kV Protection system consolidation (Prévessin and LHC 1-2-4-6-8) • Extension of the 66 kV substation Prevessin • New 66 kV feeder on Meyrin site + upgrade of the18 kV substation in the west area ME59 • New power link18 kV ME9 –ME59 in Meyrin and Autotransfert modification accordingly • Upgrade main18 kV substation in Prévessin du BE • Consolidation of fire protection systems for power transformers and for the 400 kV substation • Consolidation of the18 kV substations BA4 et BA5 • requirements • depending mainly on the injector schedule (2013 !) • Total budget = 20 MCHF LS1 Day - François Duval EN-EL
66 et 18 kV Networks Consolidation & Upgrade 2013 Upgrade sous station BE 2012-2013 Réseau secours Prevessin et SPS 2012-2013 Rénovation protection 66 kV 2012-2013 Nouvelles lignes 66 kV et 18 kV vers Meyrin 2012-2013 SPS consolidation LS1 Day - François Duval EN-EL 2012-2013Sous station BE91
66 et 18 kV Networks Consolidation & Upgrade 2012-2013 Nouvelles lignes 66 kV et 18 kV vers Prevessin 2012-2013 Nouvelle sous station 66 kV MEH59 2012-2014 Upgrade sous station ME59 2013-2014 Nouvelles liaison 18 KV entre ME9 –ME59 LS1 Day - François Duval EN-EL
LS1 EN-EL activitiesPower distribution and Operation LS1 Day - François Duval EN-EL
Replacement of SILCON UPSs • All cryo and machine : 82 UPS • Any new UPS connections • Requestsmust bedonebefore end of June2012 UPS machine : 2 UPS in RE (x16) 2 UPS in UA (x8) 2 UPS each LHC point (US, UW ou UJ) (x8) UPS cryo: 2 UPS on LHC even points (US, UW) (x4) 2 UPS on surface even points (SA, SH) (x4) 2 UPS in PM18 LS1 Day - François Duval EN-EL
Replacement of SILCON UPSs • Impact on other activities: • 6 weeks per area (for 2 UPS) • Distribution downstream off during works • Possible refeeding from diesel network (subject to request justified by safety) • Transport and handling: • ~ 660 kg for an UPS and 2000 kg for battery sets (removal of old ones as well ) • Lifts on Points 3, 5 et 7 too small for UPS : Width > 800 mm • Alcoves RE : A safety issue has to be considered: Charging batteries may lead to hydrogen production. Ventilation must be dimensioned so that the risk of explosion is eliminated (EN/EL, GS/ASE, HSE) LS1 Day - François Duval EN-EL
66 & 400 kV Substations Maintenance & Projects • Maintenance • 400 kV & 66kV substations • Tests of the protection and signals on the RTE interfaces • On-site maintenance of two 400 kV circuit breakers • Factory maintenance of three 400 kV circuit breakers • Maintenance of the 400 kV & 66kV transformers • Projects • Consolidation of the66 kV protection (BE & LHC 1-2-4-6-8) • Extension of the 66 kV substation • Consolidation of the fire detection of the 400 kV substation & its transformers • Schedule contraints LS1 Day - François Duval EN-EL
66 & 400 kV Substations Maintenance & Projects 10 07/06/2012
18 kV, 3.3 kV & LV Networks Maintenance • 1/3 of the equipment 18 kV et 3.3kV : 400 cubicles • LHC General Services LV switchgears • LHC Safety Network LV switchgears • Replacement of all breakers dedicated to the LHC safety network switching • LHC Diesel PLC consolidation • LHC 18 kV & 400 V switchgears in the alcoves • Planning - requirements • Slots of 5 to 6 days for each LHC points (including the AUG tests on the last day) • No underground access for 2 to 3 days (safety network not available) • No handling operations for 5 days (distribution off cranes off) • No 18 KV maintenance during 400/66 kV maintenance operations • No safety network maintenance while AUTOTRANSFERT is off • Necessary coordination with CRG & CV LS1 Day - François Duval EN-EL
Yearly Test Campaigns • Diesel and safety network • AUTOTRANSFERT • AUG • Schedule - requirements • PS / SPS magnet tests and run CTF3 until december 2012 • Warm-up LHC Cryo • To be scheduled: • end 2012 or early 2013 • end 2013 or early 2014 • end 2014 ? • No AUG tests during maintenance on 400 kV LS1 Day - François Duval EN-EL
Other EL Consolidation Projects LS1 Day - François Duval EN-EL
Projects for other groups EN/CV EL & CV meeting on 04/05/2012 New meeting to bescheduledasap LS1 Day - François Duval EN-EL
Projects for other groups TE/EPC Last meeting 7th of June 2012: Most of the requests clarified and will be defined soon. Most of the requests scheduled on 1st semester 2014 LS1 Day - François Duval EN-EL
Projects for other groups various LS1 Day - François Duval EN-EL
R2E Relocation of equipment • Locations • UJ14, 16, US15, UJ56, USC55, UL55, UL557, UJ76, TZ76, PM76, US85, UL84. • Work scheduled during all LS1. • Contractors EMTE (Points 1, 7, 8) & SPIE (Point 5). • Impact on other activities: • Difficult access to the work zone, transport not easy, limited co-activity (pts 5 (UP, UL) & 7 (TZ)) • Coordination: • Works done with MEF, MTE, EPC, CV, HE, EN-EL (consignation/déconsignation) LS1 Day - François Duval EN-EL
R2E Interruption of Service • Locations • UJ14, 16 – UJ56 (+ adjacent tunnel area) – UJ76 (+ adjacent tunnel area) – US85 (+ adjacent tunnel area) • Impact on networks and personnel safety: • UPS network (EOD) : consignation schedule compatible with WARM-UP cryo & other works? • Converter network (ERD) en UJ14-15, UJ56, UJ76 • Réseauxcanalis racks – consignation schedule compatible with WARM-UP cryo & other works? • The safety network (ESD) & general services networks (EBD – plugs & Lighting) will be operational during works but during 2 weeks, including one week without any EL safety systems: 48 VDC, AUG and safety lighting . Presently scheduled : October / November 2013 LS1 Day - François Duval EN-EL
Replacement of water cooled cable hoses: • Locations: UA/RA47, 63, 67, 83 et 87 • 12.5 months. Contractor: FLOHE, Supply: FLOHE & Contitech - 3200m. • Impact on other activities: • Access to UAs & RAs, scaffolding around converters, access to RA tunnel close to DFBs • Coordination: • Works done with CV, EPC, MEF, HE, MTE & EN-EL (consignation/décons.) • Schedule • 2 shifts will not be possible (limited FLOHE manpower) 19 07/06/2012 LS1 Day - François Duval EN-EL
New cable baskets LHC 1, 3 et 5 • following ALARA 01/2012 • Locations: R34, R36, R37 – 2 cable baskets on 550m. • 3 full months . Contractor C209, supply C209. • Other areas: RB14, 16, R542, 561: câblofil/télex installation on the ground. • Impact on other activities: • Access to the tunnel pt 3, difficult transport activities. • Coordination: • Works done with MEF et EN-HE et EN-EL (Integration) • Schedule: • Lead by RP. New cables to be installed in point 3 (TE-VSC) basket 1, 2 Cable tray 20 07/06/2012 LS1 Day - François Duval EN-EL
12 Flexwell cables replacement PM45 • Locations: SR4, SL42, SD4, PM45, UJ44, UJ46, RA43, RA47 • 4 full weeks. Contractor: EMTE, supply: CERN. • Impact on other activities: • Access to PM45, RA up to 12 cell including areas behind DFBs. • Coordination: • Works to be done with BE-RF, MEF, MTE, EPC (consignation/décons.) • Schedule: • to be defined with MEF et BE-RF (tests and connectors mounting). Removal of 10km and installation of 7.4 km of Flexwellcable 7/8. 21 07/06/2012 LS1 Day - François Duval EN-EL
TOTEM: modification of WCC circuits • circuits RQ 4, 5, 6, 7, 8, 9, 10 • Locations: RR53 & 57 • 5 full months on both sides • Contractor FLOHE, supply: Technical Specification to be written. • Impact on other activities: • Access to RR53 et 57, transport. Works above converters. • Coordination: • Work to be done with MEF, HE, CV, TE-EPC, TE-MPE & EN-EL (Integration, consignation/décons.) • Schedule: • to be defined with MEF. RR53 - - + DFB + + DFB - + - + DFB 22 07/06/2012 LS1 Day - François Duval EN-EL
LS1 EN-EL activities • Many requests from other groups and from the experimentsto be finalised (CRG, ASE, etc.) • Experiments requests were not included in PLAN@CERN 23 07/06/2012 LS1 Day - François Duval EN-EL
PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Travaux 400 kV et 66 kV – Pas d’autotransfert – S CERN <60MVA Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Consignations pour R2E ? K. Foraz - LHC Performance Workshop 2012
Summary of HV, LV & Controls during LS1 Workload for High Voltage, Low Voltage & Controls Sections Projects + Maintenance + Tests EL & other groups • Requirements / Resources > 1,2 • In particular during 2ndsemester 2013) • More resources • More requests are not affordable LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from BE LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from TE VSC requests were not fully considered yet LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from PH LS1 Day - François Duval EN-EL
Cables & Fibres: Requests from IT LS1 Day - François Duval EN-EL
Cables & Fibres • The preparation work behind the cabling workload estimate LS1 Day - François Duval EN-EL
Cables & Fibres The LS1 Project Leader decided • requirements/resources LS1 Day - François Duval EN-EL
Cables & Fibres • Additional resources • AGH (12 project associates from Krakow) • Fellows & associates (+10 in 2011/2012) • 2 installation contracts (doubled manpower) • FSU being prepared • Specialists + project managers required (skilled and experienced people) LS1 Day - François Duval EN-EL
Cables & Fibres • Help from other departments & experiments We still want new people working with EL team in order to have coherent works done • Work supervisors • Knowledge and experience of cable laying or fibre blowing technologies • Experience in work site supervision • Knowledge of site works • Project managers • Project management • People management • Schedule & Budget management • Knowledge of dedicated softwares(GESMAR, Câblothèque) LS1 Day - François Duval EN-EL
Cables & Fibres • But there are limits to the increase of manpower: • Lack of experience • Increase of manpower of contractors • CERN access, hotels, logistics bottle neck, Base vie? • Schedule/coactivity LS1 Day - François Duval EN-EL
EN/EL activities during LS1: Conclusion • LS1 will be a very huge shutdown also for EN/EL • On the HV & LV infrastructure side, The program will be done with some additional resources • On the cables & fibres side, the situation is critical: prioritization is done but the effort is huge for the section in charge. Additional resources have been deployed from other departments: more are needed. • We are worried about the flow of requests which are still popping up in PLAN@CERN or elsewhere LS1 Day - François Duval EN-EL