An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS1 DAY • Activités EN-EL F. Duval / EN-EL on behalf of EN/EL group 1 12/06/2012

  2. EN/EL activities during LS1 Summary • Network infrastructure consolidation & upgrade 66 kV et 18 kV • UPS SILCON replacement project • Projects and maintenance work on substation 400 kV & 66 kV • Maintenance works on 18 kV, 3.3 kV and LV networks • Yearly tests • Other EN/EL consolidation & upgrade projects • Projects for other groups • R2E • Cables & fibres projects • Schedule • Workloads • Increase of manpower 2 12/06/2012 LS1 Day - François Duval EN-EL

  3. 66 et 18 kV Networks Consolidation & Upgrade • power cables replacement18 kV SPS • New substation BE91in Prévessin (Safe feeding of CCC safety network for SPS) • Repowering CCC • 66 kV Protection system consolidation (Prévessin and LHC 1-2-4-6-8) • Extension of the 66 kV substation Prevessin • New 66 kV feeder on Meyrin site + upgrade of the18 kV substation in the west area ME59 • New power link18 kV ME9 –ME59 in Meyrin and Autotransfert modification accordingly • Upgrade main18 kV substation in Prévessin du BE • Consolidation of fire protection systems for power transformers and for the 400 kV substation • Consolidation of the18 kV substations BA4 et BA5 • requirements • depending mainly on the injector schedule (2013 !) • Total budget = 20 MCHF LS1 Day - François Duval EN-EL

  4. 66 et 18 kV Networks Consolidation & Upgrade 2013 Upgrade sous station BE 2012-2013 Réseau secours Prevessin et SPS 2012-2013 Rénovation protection 66 kV 2012-2013 Nouvelles lignes 66 kV et 18 kV vers Meyrin 2012-2013 SPS consolidation LS1 Day - François Duval EN-EL 2012-2013Sous station BE91

  5. 66 et 18 kV Networks Consolidation & Upgrade 2012-2013 Nouvelles lignes 66 kV et 18 kV vers Prevessin 2012-2013 Nouvelle sous station 66 kV MEH59 2012-2014 Upgrade sous station ME59 2013-2014 Nouvelles liaison 18 KV entre ME9 –ME59 LS1 Day - François Duval EN-EL

  6. LS1 EN-EL activitiesPower distribution and Operation LS1 Day - François Duval EN-EL

  7. Replacement of SILCON UPSs • All cryo and machine : 82 UPS • Any new UPS connections • Requestsmust bedonebefore end of June2012 UPS machine : 2 UPS in RE (x16) 2 UPS in UA (x8) 2 UPS each LHC point (US, UW ou UJ) (x8) UPS cryo: 2 UPS on LHC even points (US, UW) (x4) 2 UPS on surface even points (SA, SH) (x4) 2 UPS in PM18 LS1 Day - François Duval EN-EL

  8. Replacement of SILCON UPSs • Impact on other activities: • 6 weeks per area (for 2 UPS) • Distribution downstream off during works • Possible refeeding from diesel network (subject to request justified by safety) • Transport and handling: • ~ 660 kg for an UPS and 2000 kg for battery sets (removal of old ones as well ) • Lifts on Points 3, 5 et 7 too small for UPS : Width > 800 mm • Alcoves RE : A safety issue has to be considered: Charging batteries may lead to hydrogen production. Ventilation must be dimensioned so that the risk of explosion is eliminated (EN/EL, GS/ASE, HSE) LS1 Day - François Duval EN-EL

  9. 66 & 400 kV Substations Maintenance & Projects • Maintenance • 400 kV & 66kV substations • Tests of the protection and signals on the RTE interfaces • On-site maintenance of two 400 kV circuit breakers • Factory maintenance of three 400 kV circuit breakers • Maintenance of the 400 kV & 66kV transformers • Projects • Consolidation of the66 kV protection (BE & LHC 1-2-4-6-8) • Extension of the 66 kV substation • Consolidation of the fire detection of the 400 kV substation & its transformers • Schedule contraints LS1 Day - François Duval EN-EL

  10. 66 & 400 kV Substations Maintenance & Projects 10 07/06/2012

  11. 18 kV, 3.3 kV & LV Networks Maintenance • 1/3 of the equipment 18 kV et 3.3kV : 400 cubicles • LHC General Services LV switchgears • LHC Safety Network LV switchgears • Replacement of all breakers dedicated to the LHC safety network switching • LHC Diesel PLC consolidation • LHC 18 kV & 400 V switchgears in the alcoves • Planning - requirements • Slots of 5 to 6 days for each LHC points (including the AUG tests on the last day) • No underground access for 2 to 3 days (safety network not available) • No handling operations for 5 days (distribution off  cranes off) • No 18 KV maintenance during 400/66 kV maintenance operations • No safety network maintenance while AUTOTRANSFERT is off • Necessary coordination with CRG & CV LS1 Day - François Duval EN-EL

  12. Yearly Test Campaigns • Diesel and safety network • AUTOTRANSFERT • AUG • Schedule - requirements • PS / SPS magnet tests and run CTF3 until december 2012 • Warm-up LHC Cryo • To be scheduled: • end 2012 or early 2013 • end 2013 or early 2014 • end 2014 ? • No AUG tests during maintenance on 400 kV LS1 Day - François Duval EN-EL

  13. Other EL Consolidation Projects LS1 Day - François Duval EN-EL

  14. Projects for other groups EN/CV EL & CV meeting on 04/05/2012 New meeting to bescheduledasap LS1 Day - François Duval EN-EL

  15. Projects for other groups TE/EPC Last meeting 7th of June 2012: Most of the requests clarified and will be defined soon. Most of the requests scheduled on 1st semester 2014 LS1 Day - François Duval EN-EL

  16. Projects for other groups various LS1 Day - François Duval EN-EL

  17. R2E Relocation of equipment • Locations • UJ14, 16, US15, UJ56, USC55, UL55, UL557, UJ76, TZ76, PM76, US85, UL84. • Work scheduled during all LS1. • Contractors EMTE (Points 1, 7, 8) & SPIE (Point 5). • Impact on other activities: • Difficult access to the work zone, transport not easy, limited co-activity (pts 5 (UP, UL) & 7 (TZ)) • Coordination: • Works done with MEF, MTE, EPC, CV, HE, EN-EL (consignation/déconsignation) LS1 Day - François Duval EN-EL

  18. R2E Interruption of Service • Locations • UJ14, 16 – UJ56 (+ adjacent tunnel area) – UJ76 (+ adjacent tunnel area) – US85 (+ adjacent tunnel area) • Impact on networks and personnel safety: • UPS network (EOD) : consignation schedule compatible with WARM-UP cryo & other works? • Converter network (ERD) en UJ14-15, UJ56, UJ76 • Réseauxcanalis racks – consignation schedule compatible with WARM-UP cryo & other works? • The safety network (ESD) & general services networks (EBD – plugs & Lighting) will be operational during works but during 2 weeks, including one week without any EL safety systems: 48 VDC, AUG and safety lighting . Presently scheduled : October / November 2013 LS1 Day - François Duval EN-EL

  19. Replacement of water cooled cable hoses: • Locations: UA/RA47, 63, 67, 83 et 87 • 12.5 months. Contractor: FLOHE, Supply: FLOHE & Contitech - 3200m. • Impact on other activities: • Access to UAs & RAs, scaffolding around converters, access to RA tunnel close to DFBs • Coordination: • Works done with CV, EPC, MEF, HE, MTE & EN-EL (consignation/décons.) • Schedule • 2 shifts will not be possible (limited FLOHE manpower) 19 07/06/2012 LS1 Day - François Duval EN-EL

  20. New cable baskets LHC 1, 3 et 5 • following ALARA 01/2012 • Locations: R34, R36, R37 – 2 cable baskets on 550m. • 3 full months . Contractor C209, supply C209. • Other areas: RB14, 16, R542, 561: câblofil/télex installation on the ground. • Impact on other activities: • Access to the tunnel pt 3, difficult transport activities. • Coordination: • Works done with MEF et EN-HE et EN-EL (Integration) • Schedule: • Lead by RP. New cables to be installed in point 3 (TE-VSC) basket 1, 2 Cable tray 20 07/06/2012 LS1 Day - François Duval EN-EL

  21. 12 Flexwell cables replacement PM45 • Locations: SR4, SL42, SD4, PM45, UJ44, UJ46, RA43, RA47 • 4 full weeks. Contractor: EMTE, supply: CERN. • Impact on other activities: • Access to PM45, RA up to 12 cell including areas behind DFBs. • Coordination: • Works to be done with BE-RF, MEF, MTE, EPC (consignation/décons.) • Schedule: • to be defined with MEF et BE-RF (tests and connectors mounting). Removal of 10km and installation of 7.4 km of Flexwellcable 7/8. 21 07/06/2012 LS1 Day - François Duval EN-EL

  22. TOTEM: modification of WCC circuits • circuits RQ 4, 5, 6, 7, 8, 9, 10 • Locations: RR53 & 57 • 5 full months on both sides • Contractor FLOHE, supply: Technical Specification to be written. • Impact on other activities: • Access to RR53 et 57, transport. Works above converters. • Coordination: • Work to be done with MEF, HE, CV, TE-EPC, TE-MPE & EN-EL (Integration, consignation/décons.) • Schedule: • to be defined with MEF. RR53 - - + DFB + + DFB - + - + DFB 22 07/06/2012 LS1 Day - François Duval EN-EL

  23. LS1 EN-EL activities • Many requests from other groups and from the experimentsto be finalised (CRG, ASE, etc.) • Experiments requests were not included in PLAN@CERN 23 07/06/2012 LS1 Day - François Duval EN-EL

  24. PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Travaux 400 kV et 66 kV – Pas d’autotransfert – S CERN <60MVA Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Consignations pour R2E ? K. Foraz - LHC Performance Workshop 2012

  25. Summary of HV, LV & Controls during LS1 Workload for High Voltage, Low Voltage & Controls Sections Projects + Maintenance + Tests EL & other groups • Requirements / Resources > 1,2 • In particular during 2ndsemester 2013) • More resources • More requests are not affordable LS1 Day - François Duval EN-EL

  26. Cables & Fibres: Requests from BE LS1 Day - François Duval EN-EL

  27. Cables & Fibres: Requests from TE VSC requests were not fully considered yet LS1 Day - François Duval EN-EL

  28. Cables & Fibres: Requests from PH LS1 Day - François Duval EN-EL

  29. Cables & Fibres: Requests from IT LS1 Day - François Duval EN-EL

  30. Cables & Fibres • The preparation work behind the cabling workload estimate LS1 Day - François Duval EN-EL

  31. Cables & Fibres The LS1 Project Leader decided • requirements/resources LS1 Day - François Duval EN-EL

  32. Cables & Fibres • Additional resources • AGH (12 project associates from Krakow) • Fellows & associates (+10 in 2011/2012) • 2 installation contracts (doubled manpower) • FSU being prepared • Specialists + project managers required (skilled and experienced people) LS1 Day - François Duval EN-EL

  33. Cables & Fibres • Help from other departments & experiments We still want new people working with EL team in order to have coherent works done • Work supervisors • Knowledge and experience of cable laying or fibre blowing technologies • Experience in work site supervision • Knowledge of site works • Project managers • Project management • People management • Schedule & Budget management • Knowledge of dedicated softwares(GESMAR, Câblothèque) LS1 Day - François Duval EN-EL

  34. Cables & Fibres • But there are limits to the increase of manpower: • Lack of experience • Increase of manpower of contractors • CERN access, hotels, logistics bottle neck, Base vie? • Schedule/coactivity LS1 Day - François Duval EN-EL

  35. EN/EL activities during LS1: Conclusion • LS1 will be a very huge shutdown also for EN/EL • On the HV & LV infrastructure side, The program will be done with some additional resources • On the cables & fibres side, the situation is critical: prioritization is done but the effort is huge for the section in charge. Additional resources have been deployed from other departments: more are needed. • We are worried about the flow of requests which are still popping up in PLAN@CERN or elsewhere LS1 Day - François Duval EN-EL