LS1 plan. LS1 will start towards end November 2012 (week 48) and will last for approximately 1 ½ years (i.e. till July 2014), this corresponds to approximately 80 weeks. Baseline sequence: Add 5 TRD modules Add 6 DCal supermodules and 2 1/3 supermodules Add 1 PHOS module
E N D
LS1 plan • LS1 will start towards end November 2012 (week 48) and will last for approximately 1 ½ years (i.e. till July 2014), this corresponds to approximately 80 weeks. • Baseline sequence: • Add 5 TRD modules • Add 6 DCal supermodules and 2 1/3 supermodules • Add 1 PHOS module • On the top of this sequence, we have numerous items, like LV consolidation, UPS upgrade, extension SAA3, chilled-water upgrade, L3 ventilation, L3 cooling maintenance, PMD mechanics upgrade, CO2 and N2 systems consolidation. • MNF will not be removed. Shutdown conclusion, LS1 and LS2 planning - A.Tauro
Draft 10 years plan (27/10/11) 2012 2013 2014 2020 2015 2017 2018 2019 2021 2016 Operation period 2 (OP2) Operation period 1 (OP1) Long Shutdown 1 (LS1) • Machine : Splices consolidation… • ATLAS: - Consolidation and new forward beam pipes • ALICE: detector completion • CMS:FWD muons upgrade + Consolidation & infrastructure improvements • LHCb: consolidations Operation period 3 (OP3) Long Shutdown 2 (LS2) OP2 • Machine: Collimation & prepare for crab cavities & RF cryo system • ATLAS: new pixel detect. - detect. for ultimate luminosity. • ALICE - Inner vertex system upgrade • CMS - New Pixel. New HCAL Photodetectors. Completion of FWD muons upgrade • LHCb - full trigger upgrade, new vertex detector etc. LINAC 4 connection ? K. Foraz - LHC Performance Workshop 2012
Other activities(and their impact on services) • TPC/TRD LV cables BKF • 4m work (Mar-Jun 2013) • UPS upgrade: • Technical solution under discussion. Most probably 4-6 m unavailability of UPS (DAQ, DCS, cooling plant…) • Chilled water increase • 1-2w no water (2013) • Cooling plant tank replacement • new 2m3 tank (at least). Beginning 2013 • New outlets for redundancy of Ethernet cables
TPC gas consumption • 2012: • TPC volume: 45l/h Ne/CO2 (90/10). 50kCHF/year • TPC envelopes: 170l/h of CO2/O2 (98/2). 2kCHF/year • 2013: • TPC volume: 22.5l/h Ne/CO2 (half flow) • 2014-15: • Same as 2012
LS1 plan Remove plug, mobile shielding, open doors 4 Xmas pause 2 Remove PHOS cradle and modules 3 Modify services under SF rail 8 Swap PHOS Rails with new ones 4 DCal and PHOS services (1/2) 3 Install DCal Cradle 3 DCal and PHOS services (2/2) 1 Contingency 1 Install 3 DCal modules (C-side) 1 Install 2 1/3 DCal modules 1 Contingency 2 Concrete walls & TRD installation frame 2 TRD 4/5 (top) & counterweights 2 Suspend Miniframe 2 TRD 12/13/14 with yellow platform (bottom) 2 ‘Un-suspend’ Miniframe 2 ---------- Xmas pause 2 Install 4 PHOS modules (incl.pre-commiss.) 3 Install 3 DCAL modules (A-side) 2 Close plug, mobile shielding 4 Contingency 6 Nov.2012 Aug.2013 Removal and reinstallation of PMD; removal and reinstallation of compensator magnet; removal, reinstallation and bakeout of RB24 beampipe and ‘LV consolidation’ are in parallel. Jan.2014 LS1 schedule - A.Tauro