An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update on LS1 Activities

    W.Baldini, N. Bondar, O.Maev, D. Maisuzenko, B. Schmidt LS1 Muon Meeting Apr-24th 2014
  2. Present Status LS1 activities: activities ongoing on C-side M2-5: Improving of M2 chambers DONE, M3R1-2 ongoing (18 chambers) LV investigation of M2-Q3 ongoing, for the moment nothing trivial found Conditioning of problematic chambers and reconditioning of M4R4 ongoing (Oleg) Connectivity test of M2 just started HV: Upgrade of the projects for the PNPI system done and tested (Giovanni) Mapping tested and debugged up to RDBs input Check of RDBs output (to chambers) to be done (mapping and calibration) “Malter” studies re-started on a M4R4 chamber (Dmitrii, Oleg, Nikolai) WINCC-OA migration: OPC serversnow running on Credit Card PCs, some debugging still needed (Beat, Clara, Davide). ECS:Davide is improving the threshold scan procedure
  3. Preparation of the next comm. week Next comm. week: May 5 – 9-th, we should make an effort get the system in almost run conditions. Monitoring farm now moved to SLC6, recompile the Muon monitoring tasks (Giacomo?) HV CAEN A-Side: reinstall all necessary software on the replaced machine muhva02w (online guys or ourselves?) HV PNPI C-side: still missing a routine from Clara… (Giovanni) HV GEM (Ale?) GAS control issue after the migration to WINCC