VELO-installation++ activities September 6, 2007

VELO-installation++ activities September 6, 2007. General items Detector installation plans. General. A- and C-detector halves are ready in assembly lab. All TELL1’s are installed in D3 and being tested Connectorizing of analog cables + testing finished this week

ethel
Download Presentation

VELO-installation++ activities September 6, 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. VELO-installation++ activitiesSeptember 6, 2007 • General items • Detector installation plans VELO

  2. General • A- and C-detector halves are ready in assembly lab. • All TELL1’s are installed in D3 and being tested • Connectorizing of analog cables + testing finished this week • HV-cabling + testing finished this week • LV-work is ongoing D3 A-side VELO

  3. Control and readout of a dummy module (slice test in the • pit) is making good progress. • Programming of motion-PLC at CERN first week of • October by MvB+PdG • Some external level measurements by E.J. + Raphael (end • of Sep. / early Oct.) • Magnet test during first 2 weeks of October: • - beforehand clean the area (service rack, heaters, ???) • - restricted access • - proposed VELO-activities: • * measure magnetic field at turbo’s • * check motion • * check operation of LVDT’s ?? • ECS/PVSS work to be done for FSM of motion, vacuum and • cooling by FS and APC. States need to be defined by • experts soon. VELO

  4. PT100-cabling mystery of RF-boxes needs to be solved. • Blow system is leaking. Needs fixing. • Metrology results of alignment pieces • of top frame show too large • differences betweenZeiss and Wenzel. mm Needs to be clarified !! VELO

  5. Additional fundingrequested from coming CB for production • of 42 VELO-modules by Q1 2010. • Possible reasons: • beam x VELO accident • replacement due to radiation damage • Preparation scheme of new detector halves yet unclear. • Production of 2 complete spare detector bases (= base, • hood, vacuum feedthroughs, long kaptons, evaporator, • trolley) under discussion. VELO

  6. Detector installation • A lot of external constraints: magnet test, platform A-side, • RICH1, TT, survey group, vacuum group, transport team, etc. • Preliminary planning contains >60 items. Present version: • Oct. 22-24: • * Survey the outside of the VELO by CERN-survey group • * Comparison with previous data in collaboration with NIKHEF • Monday Oct. 29: • * Open the VELO • * Level + perpendicularity measurements of the detector • supports by NIKHEF • * Make adjustments if necessary/possible • * Survey of the center, inner and top frames by CERN-group VELO

  7. Tuesday Oct. 30: • * insert A-half + check performance. If still OK then • Wednesday Oct. 31: • * insert C-half + check performance. • Thursday November 1: • * final checkout + closing • Friday November 2: • * evacuate beampipe + VELO • Monday+Tuesday November 5+6: • * motion tests + precise positioning measurements • Wednesday+Thursday November 7+8: • * venting with ultrapure Neon VELO

  8. In November and December a lot of physics manpower is needed for commissioning of the whole VELO-chain (LV, HV, CB, TELL1, TB, DSS, interlocks, cooling). When all these items work reliably for one half then start operating that detector half. VELO