CALO News. 9 July 2014. Pascal Perret LPC Clermont. LS1 Activities : LHCb. LHCb closure week 47 (Nov. 17 ) Operation weeks: W36 : Sep. 1-5 W42: Oct. 13 – 17 → “ rehersal of full readout and calibration”. ECAL CALIB system – fibers replacement. 6. 7. 8. W31 Neon In.
E N D
CALO News 9 July 2014 Pascal Perret LPC Clermont
LS1 Activities: LHCb • LHCb closure week 47 (Nov. 17) • Operation weeks: • W36: Sep. 1-5 • W42: Oct. 13 – 17 → “rehersal of full readout and calibration” ECAL CALIB system – fibers replacement 6 7 8 W31 Neon In Week 19 operation week #6 AUG 12/5 Dipole test w19 W33 B-field measurement Week 26 : operation week #7 9 10 11 12 RICH HPD replacement Sector test p2 Beam Pipe Installation DSO test CV maintenance 2014 Week 36 : operation week #8 Beam Pipe Installation Beam Pipe Installation Week 42 : operation week #9 LHCb CLOSURE W 47 Sector test p8 Pump down 2 CV maintenance 2014 Pascal Perret - LPC Clermont
LS1 Activities: LHCb • Most of our activities completed: • ECAL/HCAL: see Yuri’s talk • Coupling vis à billeSPD (A&C side) and ECAL A-sidereplaced • + tuning of SPD closure position on June 25 • Thanks to Bruno, Laurent B & Laurent J from LAPP! • Next: • Interlock system installation for platform doors • Tuning of closing position, etc. Pascal Perret - LPC Clermont
LS1 Activities: LHCb • M1-SPD interference (June 20 opening of M1) • No damage • Al sheetonly (fibre protection) • To check tape in place everywhere! Pascal Perret - LPC Clermont
LS1 Activities: LHCb • To do: • Addition of TELL1 • Scheduled July 21/22 • Software to be adapted accordingly • Maintenance MARATON water cooling circuit • Shouldfixed PRS3 and ECAL HV/LED power supplyproblemsboth in L3B01 Pascal Perret - LPC Clermont
Project organizations • New management & new TDR: • it was agreed at the last LHCb week that the upgrade projects of VELO, RICH, Calorimeter, Muon will be led by the current sub-detector project leaders, being the internal organization of the activities left to the decision of the sub-detector groups. • Proposal: a new appointment for calorimeter: • Upgrade coordinator: Frederic • Will take care of the upgrade, attend TB meeting in place of one deputy, etc. • 1st actions: • proper organization of the activities • set up milestones • These should concern: • the completion of the R&D activities • the various phases of production and integration • EDR, PRR, a date of "ready for installation“, etc. Pascal Perret - LPC Clermont
Next meetings • 2014 • 10/09* • 08/10 • 26/11* * prior LHCbweek • To do: • Calibration • Commissioning • Be ready to take data! Pascal Perret - LPC Clermont