CALO News. 9 July 2014. Pascal Perret LPC Clermont. LS1 Activities : LHCb. LHCb closure week 47 (Nov. 17 ) Operation weeks: W36 : Sep. 1-5 W42: Oct. 13 – 17 → “ rehersal of full readout and calibration”. ECAL CALIB system – fibers replacement. 6. 7. 8. W31 Neon In.

fauve
Download Presentation

CALO News

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CALO News 9 July 2014 Pascal Perret LPC Clermont

  2. LS1 Activities: LHCb • LHCb closure week 47 (Nov. 17) • Operation weeks: • W36: Sep. 1-5 • W42: Oct. 13 – 17 → “rehersal of full readout and calibration” ECAL CALIB system – fibers replacement 6 7 8 W31 Neon In Week 19 operation week #6 AUG 12/5 Dipole test w19 W33 B-field measurement Week 26 : operation week #7 9 10 11 12 RICH HPD replacement Sector test p2 Beam Pipe Installation DSO test CV maintenance 2014 Week 36 : operation week #8 Beam Pipe Installation Beam Pipe Installation Week 42 : operation week #9 LHCb CLOSURE W 47 Sector test p8 Pump down 2 CV maintenance 2014 Pascal Perret - LPC Clermont

  3. LS1 Activities: LHCb • Most of our activities completed: • ECAL/HCAL: see Yuri’s talk • Coupling vis à billeSPD (A&C side) and ECAL A-sidereplaced • + tuning of SPD closure position on June 25 • Thanks to Bruno, Laurent B & Laurent J from LAPP! • Next: • Interlock system installation for platform doors • Tuning of closing position, etc. Pascal Perret - LPC Clermont

  4. LS1 Activities: LHCb • M1-SPD interference (June 20 opening of M1) • No damage • Al sheetonly (fibre protection) • To check tape in place everywhere! Pascal Perret - LPC Clermont

  5. LS1 Activities: LHCb • To do: • Addition of TELL1 • Scheduled July 21/22 • Software to be adapted accordingly • Maintenance MARATON water cooling circuit • Shouldfixed PRS3 and ECAL HV/LED power supplyproblemsboth in L3B01 Pascal Perret - LPC Clermont

  6. Project organizations • New management & new TDR: • it was agreed at the last LHCb week that the upgrade projects of VELO, RICH, Calorimeter, Muon will be led by the current sub-detector project leaders, being the internal organization of the activities left to the decision of the sub-detector groups. • Proposal: a new appointment for calorimeter: • Upgrade coordinator: Frederic • Will take care of the upgrade, attend TB meeting in place of one deputy, etc. • 1st actions: • proper organization of the activities • set up milestones • These should concern: • the completion of the R&D activities • the various phases of production and integration • EDR, PRR, a date of "ready for installation“, etc. Pascal Perret - LPC Clermont

  7. Next meetings • 2014 • 10/09* • 08/10 • 26/11* * prior LHCbweek • To do: • Calibration • Commissioning • Be ready to take data! Pascal Perret - LPC Clermont