CALO Commissioning Activities. 22 June 2009. Pascal Perret LPC Clermont. A ctivities in the cavern : Last Access!. ECAL: Integrator boards re-installation and last checks: ~1 day/side: A-side: June 19-22 done C-side: July 1-2 ? HCAL : L ast checks: ~1 day/side:
E N D
CALOCommissioningActivities 22 June 2009 Pascal Perret LPC Clermont
Activities in the cavern: Last Access! • ECAL: • Integrator boards re-installation and last checks: • ~1 day/side: • A-side: June 19-22 done • C-side: July 1-2 ? • HCAL: • Last checks: • ~1 day/side: • A-side: June 26-29 2pm • C-side: June 29-30 Pascal Perret - LPC Clermont
Activities in the cavern: Last Access! • PS: • LV patch panel exchanged: June 29 (A-side)-30(C-side) • VFE electronics maintenance: • A-side: June 29-30 • C-side: July 1 • PS/SPD: • LED tuning C-side? No news from Evgueni … • Survey & alignment: July 2-3 • Detector closing & survey: July 6-10 (according to M1) • Turbines exchanged … • By groups of 3 (3 spares!): 3/day ? • … Pascal Perret - LPC Clermont
Planning • DCS shouldbeready (in action!) as soon as possible … Pascal Perret - LPC Clermont