Pembiayaan. Kegiatan A = Investigasi Lama kegiatan 10 hari Jumlah jam kerja 1 hari = 6 jam Jumlah sistem analis = 3 orang Biaya Sistem analis 1 jam = Rp.125.000. Pembiayaan. 1 org sistem analis 10 hari x 6 jam x 125.000 = Rp 7.500.000 3 org sistem analis

ferris
Download Presentation

Pembiayaan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pembiayaan Kegiatan A=Investigasi Lama kegiatan 10 hari Jumlah jam kerja 1 hari = 6 jam Jumlah sistem analis = 3 orang Biaya Sistem analis 1 jam = Rp.125.000

  2. Pembiayaan 1 org sistem analis 10 hari x 6 jam x 125.000 = Rp 7.500.000 3 org sistem analis 3 x 7.500.000 = Rp.22.500.000 Penyimpangan/resiko 10% Rp. 2.250.000 Total biaya investigasi Rp.24.750.000

  3. Tabel Biaya Tenaga kerja

  4. Pembiayaananalis 1 org analis sistem menggunakan komputer 1 hari selma 2 jam 10 hari = 20 jam 3 x 10 hari = 60 jam Biaya sewa 1 set komputer 1 jam = Rp. 20.000,- Biaya komputer investigasi 60 x 20.000 Rp. 1.200.000,- Risiko 10% Rp. 120.000,- Total Rp. 1.320.000,-

  5. Pembiayaan Programmer • 1 org Programmer menggunakankomputer 1 hariselama 10 jam • 20 hari x 10 = 200 jam • 5 x 20 hari x 10 = 1000 jam • Biayasewa 1 set komputer • 1 jam = Rp. 20.000,- • Biayakomputerpemrograman 1000 x 20.000 • Rp. 20.000.000,- • Resiko 10% Rp. 2.000.000,- • Total Rp. 22.000.000,-

  6. Tabel Biaya Sewa alat

  7. Tabel Biaya Pembelanjaan

  8. Total Biaya