1 / 20

ODI Project Status

ODI Project Status. 30 Sep 2008. ODI Tasks. Corrector Optics ADCs Lens 1 Lens 2 AR Coatings OTA Detector Fabrication Lot 3 Lot 4 OTA Packaging and Testing. ODI Tasks (2 of 4). Filters ISP Forward Corrector ADC Assembly Filter Mechanism Shrouds Bonn Shutter. ODI Tasks (3 of 4).

frayne
Download Presentation

ODI Project Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ODI Project Status 30 Sep 2008

  2. ODI Tasks • Corrector Optics • ADCs • Lens 1 • Lens 2 • AR Coatings • OTA Detector Fabrication • Lot 3 • Lot 4 • OTA Packaging and Testing

  3. ODI Tasks (2 of 4) • Filters • ISP • Forward Corrector • ADC Assembly • Filter Mechanism • Shrouds • Bonn Shutter

  4. ODI Tasks (3 of 4) • Dewar Assembly • Dewar Window Assembly • Dewar Vessel and Backplate • Focal Plane Assembly • Thermal Management System • Vacuum System • Electronics Controller Packaging • Cable Wrap Assembly

  5. ODI Tasks (4 of 4) • Instrument Controllers • ADC • Filter Mechanism • Thermal Management System • Vacuum System Monitor • OTA Controller • ODI Software • Integration & Test • Commissioning Support

  6. Optics • Optics Contract with SESO • WIYN provided PBL6Y for two prisms • SESO provides • Fused Silica for two prisms • Polishing of four ADC prisms • Lens 1 Aspheric Lens • Lens 2 Dewar Window - Concave/Convex spherical/spherical lens • AR Coatings Contract with Infinite Optics • Delivery two months from receipt of optics

  7. Optics (2 of 2) • Status • ADCs scheduled for delivery in Oct 08 • Lens 1 scheduled for delivery in Dec 08 • Lens 2 scheduled for delivery in Dec 08 • Test of SESO test optics by CGH end of Sep 08

  8. OTA Production • Contract with Semiconductor Technology Associates (STA) fabrication by Dalsa • Lot 3 OTAs • Incorporated design changes from Lot 2 • 12 wafers/ 48 OTAs • Packaged thick test devices • 4 OTAs unthinned OTAs for QUOTA • Lot 4 OTAs • Changed to higher resistivity material • Completed 35 of 48 wafers with 52 good devices • Successfully tested at University of Hawaii • STA/Dalsa to produce 12 more wafers at no additional cost

  9. OTA Packaging • Contract with U of AZ, ITL to package, characterize, and mount OTAs on Focal Plate • Packaging delays due to ceramic contractor • Production equipment and employees in place • Test facility in place • First packaged devices in Nov 08 • Delivery of populated focal plate Oct 09 on Critical Path

  10. Filters • Planned six filters • g,r,i,z filter set • H-alpha • U band • RFP currently at vendors • Need one filter by Jul 09 for on-telescope optics test

  11. ISP (HEMI) • Forward Corrector remaining tasks • Final machining for Lens 1 Mount • Blackening • ADC Mechanism remaining tasks • Final Bores for Filter Swing Arm axles • Mount motor drive assemblies • Optics cells final machining

  12. ISP (HEMI) (2 of 3) • Filter Mechanism • Swing Arms completed • 1 of 3 motor drive and swing arm assemblies completed • Fabrication of Filter Holders started • Axles completed • Shrouds • Fabricated • Awaiting final assembly

  13. ISP (HEMI) (3 of 3) • Bonn Shutter • Contract with University of Bonn • Delivery scheduled for Feb 2009

  14. Dewar Assembly • Gary will cover in detail

  15. Instrument Controllers • ADC Controllers • Fabricated awaiting integration with ADCs • Filter Arm Controllers • Fabricated awaiting integration with Filter drives • Thermal Management Controller • Temperature sensor multiplexer built • Design of temperature controller started • Vacuum System monitor

  16. OTA Controller • Contract with IfA @ University of Hawaii for Stargrasp controllers • Delivery of 64-channel prototype scheduled for Oct 08 • Delivery of 256-channel controller in Feb 09 • Delivery of additional 256-channel controller in May 09

  17. ODI Software • Delayed by change from MONSOON OTA controller to StarGrasp Controller • Software architecture completed, some prototypes completed, but being revisited to see what we can reuse from other projects • Design review planned for 19-20 Nov 08

  18. Integration and Test • ODI Strategy: Integrate and test as components become available • Three phase ISP integration • Without optics – now thru March 09 • With optics – March 09 thru July 09 • Telescope test of optics – Aug 09 • Three phase Dewar integration • Thermal tests without detectors – Apr thru Aug 09 • Vacuum tests with Dewar window, without populated focal plane – Sep 09 • Tests with populated focal plane – Oct 09 thru Feb 09

  19. Commissioning Support • Provide engineering support during ODI Commissioning

  20. Dewar Expenses vs. ETC Budget * Based on Estimate to Complete May 08