1 / 19

LBNE Working Group Meeting

LBNE Working Group Meeting. December 20, 2011 3:00– 5:00 PM Snake Pit. Agenda. Purpose of Working Group Meetings [Dean Hoffer] Project Report [Jim Strait/Elaine McCluskey] Overview of the Project Scope

freya
Download Presentation

LBNE Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBNE Working Group Meeting December 20, 2011 3:00– 5:00 PM Snake Pit

  2. Agenda • Purpose of Working Group Meetings [Dean Hoffer] • Project Report [Jim Strait/Elaine McCluskey] • Overview of the Project Scope • Project Status (including design, schedule, estimates, risks and PM documents preparations for CD-1) • Funding Limitations • Staff Re-allocation Post-Decision • Overview of requirements for CD-1 [Dean Hoffer] • Preparations for Director's Independent Conceptual Design and CD-1 Readiness Review [Dean Hoffer] • Discuss Next Meeting [Dean Hoffer/All] 20-Dec-2011 LBNE WGM

  3. Fermilab’s Project Management System Lifecycle 20-Dec-2011 LBNE WGM

  4. Purpose of Working Group Meetings • Mentor Project Teams in Project Management Processes and DOE Requirements • Guide projects through CD-0,1, 2 and 3 process • Ensure projects are ready for Director’s and DOE Reviews • Facilitate open communication to address problems • Meetings include project office personnel, Control Account Managers, Directorate that oversee the project, the DOE Federal Project Director, DOE OHEP Program Manager, OPMO, ES&H, Procurement and other support personnel • For LBNE, BNL and LANL Management included 20-Dec-2011 LBNE WGM

  5. Typical DOE Acquisition Management System for Line Item Projects • Figure 1 from DOE O 413.3A Pre-conceptual Planning Conceptual Design Preliminary Design Final Design Construction 20-Dec-2011 LBNE WGM

  6. Summary of Major Requirements Table 20-Dec-2011 LBNE WGM

  7. Critical Decision S-4 Under Secretary of Science (Brinkman, acting) SC-1 Director, Office of Science (Brinkman) 20-Dec-2011 LBNE WGM

  8. Review Requirements for $750M or More ICE – Independent Cost Estimate ICR – Independent Cost Review SC-28 Office of Project Assessment (Lehman) 20-Dec-2011 LBNE WGM

  9. Matrix Link • OPA Project Decision Matrix http://science.energy.gov/~/media/opa/pdf/processes-and-procedures/Project_decision_matrix_11_2010_m.pdf 20-Dec-2011 LBNE WGM

  10. OPMO Website and Procedures • OPMO Main Webpage: http://www.fnal.gov/directorate/OPMO/OPMOhome.htm • OPMO Procedures: http://www.fnal.gov/directorate/OPMO/PolProc/home.htm • FRA Earned Value Management System Description • 12.PM-001 Project WBS, OBS, RAM • 12.PM-002 Control Accounts, Work Packages, Planning Packages • 12.PM-003 Work Authorization • 12.PM-004 Project Scheduling • 12.PM-005 Cost Estimating • 12.PM-006 Monthly Status and Reporting • 12.PM-007 Change Control • 12.PM-008 EVMS Surveillance & Maintenance 20-Dec-2011 LBNE WGM

  11. Project Report [Jim Strait/Elaine McCluskey] • Overview of the Project Scope • Project Status (including design, schedule, estimates, risks and PM documents preparations for CD-1) • Funding Limitations • Staff Re-allocation Post-Decision 20-Dec-2011 LBNE WGM

  12. CD-1 Requirements 20-Dec-2011 LBNE WGM

  13. CD-1 Requirement Matrix 20-Dec-2011 LBNE WGM

  14. Critical Path to get through CD-1 • Complete Conceptual Design and documenting it in the Conceptual Design Report (CDR) • Developing a Resource Loaded Schedule (RSL) and Cost Estimate (includes BOEs and risk driven cost and schedule contingency) • Developing Required Project Management Documents (i.e. PEP, PMP, CDR, Acquisition strategy, Preliminary Hazard Analysis, Configuration Management Plan, Value Management Plan, Risk Management Plan, etc.) 20-Dec-2011 LBNE WGM

  15. CD-1 Documents • Preliminary Project Execution Plan (PEP) • Acquisition Strategy • Preliminary Project Management Plan (PMP) • Conceptual Design Report (CDR) • Baseline Range and Resource Loaded Schedule • Configuration Management Plan • Preliminary Hazard Analysis Report • Assumptions Document • Preliminary Risk Management Plan and Risk Assessment • QA Program • Value Management Documentation 20-Dec-2011 LBNE WGM

  16. Director’s Review • There are two parts • Independent Design Review • Technical evaluation of the Conceptual Design Report (CDR) • CD-1 Readiness (“Approve Alternative Selection and Cost Range”) • Evaluate Cost, Schedule, Risk Management, Quality Assurance, ES&H, and Project Management Organization/Process 20-Dec-2011 LBNE WGM

  17. Preparations for CD-1 Director’s Review • Scope - Focus on Conceptual Design and readiness to Approve Alternative Selection and Cost Range (schedule/ cost estimate/ labor resources) • Duration estimated at approximately 4+ Days (will be determined by agenda) • Charge – Dean to draft • Agenda – Jim/Elaine to draft • Target Date of Review Week of March 5 • Need to get confirmation of Director/Deputy Director availability to schedule 20-Dec-2011 LBNE WGM

  18. Review Logistics Preparations • Establish Review Committee Team • Will use some of the independent reviewers used on LBNE internal reviews for Director’s Review Team • Create Review Website (OPMO’s and LBNE’s) • LBNE’s Review Documents to be posted 2 week’s prior to start of review. This includes drafts of presentations. • Reserve Meeting Rooms • Initially reserved when review date determined • Firm reservations after draft agenda 20-Dec-2011 LBNE WGM

  19. Next Meeting • If weekly, December 27 from 3:00 – 5:00 PM (CT) • Potential Agenda Items • Review Draft Charge • Review Draft Agenda 20-Dec-2011 LBNE WGM

More Related