TileCal Commissioning and Performance

TileCal Commissioning and Performance. Irene Vichou University of Illinois at Urbana-Champaign on behalf of the TileCal Collaboration LHCC Comprehensive Review, 13 Nov 2006. Outline. Detector status Commissioning procedures and organization Services FE and LVPS DAQ, DCS. fibre. tiles.

gparker
Download Presentation

TileCal Commissioning and Performance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TileCal Commissioning and Performance Irene Vichou University of Illinois at Urbana-Champaign on behalf of the TileCal Collaboration LHCC Comprehensive Review, 13 Nov 2006

  2. Outline • Detector status • Commissioning procedures and organization • Services • FE and LVPS • DAQ, DCS Irene Vichou, LHCC Comprehensive Review

  3. fibre tiles A TileCal Module 64 Barrel 2x64 Ext. Barrel The TileCal detector Finger LVPS Electronics Drawer Irene Vichou, LHCC Comprehensive Review

  4. TileCal Electronics scheme Cs calibration Bulk LVPS Bulk HVPS Tile/Fibre LVPS Mixer PMT Laser calibration/LED 3 Bus Board HV Micro CANbus HVOpto Divider CIS calibration 3-in-1 7  probes L H Mother Board 5 Digitizer Analog ADC Integrator CANbus Adder Digital Optical Link Interface ROD µ Trigger Hadron Trigger Irene Vichou, LHCC Comprehensive Review Energy TTC DC Calibrations

  5. Detector installation status • All 3 TileCal cylinders were assembled. • The barrel was moved to z=0 and connected to services in November/December 2005 • The gap, crack and MBTS scintillators were installed before the summer. • The EBC and EBA are now at a distance of 3m from the Barrel. • Expected to connect services to have services connected to EBA by December. Irene Vichou, LHCC Comprehensive Review

  6. Some history since last LHCC CR • Between Nov-March • Barrel connected to services • LVPS installed and DCS progressing for LV • Exercised the commissioning testing suite. • Long time for repairs of damaged FE from LVPS behavior. • BE installation • Between March and June • Installation of modified, safe LVPS and improvements for noise. • More BE, using the RODs as a tool for commissioning. • Between July and September • Systematically testing the LVPS+FE system using the full data-taking chain, going through commissioning properly. • Had to work on optimising the LVPS installation and trimming and to cope with instabilities (at the FE/LVPS i/f level or at the FE level) • Elaborated a lot the procedures for detector commissioning • Very recently • Improving things at the level of understanding LVPS/FE long term behavior. • Throughout the whole year: • Several integration milestones achieved • Several combined technical and physics runs Irene Vichou, LHCC Comprehensive Review

  7. Organization and operations • Commissioning teams/tasks under the commissioning coordinator: • Services manufacture and QC • FE maintenance and repairs • Services connection and LVPS insertion • Diagnostics of the FE/LVPS system. • Online checks for operation • Offline validation and further analysis. • ABOVE ACTIVITIES TUNED by the run coordinator • Decisions and status discussed in: • TileCal Weekly commissioning meetings • Short bi-daily meeting for planning • Weekly meetings with TC for operations planning • Weekly meetings with ATLAS commissioning conveners for integration planning Irene Vichou, LHCC Comprehensive Review

  8. Planning and logs Irene Vichou, LHCC Comprehensive Review

  9. Services • Barrel is connected to USA15 racks since Jan-Feb 06. • No problems discovered when QC-ed after routing. • Only 1 spare used out of O(1000) cables for the Barrel • Had to buy part of the trigger cables from another company (little delay) • Central cooling was provided in April 06 (but used a temporary unit in the meantime) • EBA and EBC have local cables installed • Expect to finish routing and connections by the end of the month. Irene Vichou, LHCC Comprehensive Review

  10. FE and Power • 60 LVPS in use (50% of the Barrel) • 55 stable • 3 tripping • 2 cases of superdrawer connected problems (large voltage drops) • HV system • 3 SD that we can’t turn ON HV • In the stable modules the level of dead channels is ~1.5%. Irene Vichou, LHCC Comprehensive Review

  11. DCS and DSS • Currently the PVSS project for TileCal • Handles he LVPS control and monitoring • Displays/save the cooling loops status • Will handle the HV information in ~week. • Databases for the LV part • Configuration DB: Storing and retrieving calibration data from the Oracle archive. • Conditions DB: DCS data are stored in the Oracle archive, plan to be moving them to COOL • FSM : Plan to be working beg. of December (Tile supervisor, LV part, alarms) • DSS: TileCal LVPS and HVPS are switched off by the central DCS in case of emergency. Screenshot of LVPS status Irene Vichou, LHCC Comprehensive Review

  12. RODs and DVS DVS tests panel • All the RODs are installed • For the Barrel they are used both for commissioning diagnostics and for proper data-taking. • DVS tests • Fast tests for FE operation checks. They are configured in the OKS DB and the answers are prompt! • Have been checking routinely: • Noise in digital data • Response to CIS • Integrator noise and linearity Response of channels to CIS Irene Vichou, LHCC Comprehensive Review

  13. DAQ • The Tiles DAQ s/w is in very good shape well adapted to serve data-taking but also diagnostics. • The RODs and the ROSs are used and data are taken and exported to castor every day for calibration and physics. • Using always the most recent online TDAQ release. • The integration to the ROSs is done, we are using 2 out of 4 partitions for data taking. • Usual rate is 1 kHz • 30 kHz have been reached in tests. • Databases • Detector configuration is set in OKS. OKS2COOL is used to keep a copy of this to COOL. • OF coefficients can be stored to and retrieved from COOL at Point 1. Main IGUI for run configuration Irene Vichou, LHCC Comprehensive Review

  14. Results DB Results DB • Testing suite • DVS tests (fast) for pedestals, CIS, integrators response and gain switching. • Data taking • Calibration with CIS (digitizer data) • Noise for digitizer data • LED tests • Integrators linearity and noise • Immediate answer from DVS (online) tests and results in ~24h for the TDAQ runs. Online results for a module Offline results for a module Irene Vichou, LHCC Comprehensive Review

  15. Calibration systems • CIS well exercised • Same for integrators calibration • Cs and Laser operational for calibrations after January 2007. • EM scale from testbeam is very well understood to get ready the data-taking. Irene Vichou, LHCC Comprehensive Review

  16. Source sensor card Hydraulic drive Water stations Air pressure control for source garage Cesium system • Barrel • All piping & cabling done • All local equipment installed • Extended Barrel • On detector piping done • EBC chain cabling done • Local equipment installed • EBA: fully installed, EBC: ~90% done • Hydraulic system installed in UX15 racks • Cabling/electronics and communication tests as well as pressure tests have been performed for the Barrel. • Next step: Connect system & wet test with dummy source • Goal:? Irene Vichou, LHCC Comprehensive Review

  17. Laser system Part of the laser system already installed in the USA15 racks Photodiode Box Laser head Laser Box Monitoring Fiber pump bundle Laser pump Planning to do first basic tests in the week of November 20th. Currently using LEDs instead. Irene Vichou, LHCC Comprehensive Review

  18. Performance Issues • Stability • Timing • B-field data • Cosmic muons Irene Vichou, LHCC Comprehensive Review

  19. Stability issues Integrator Gains and Pedestals • Gains are stable at a level of 10-4 -10-3 at a time scale of 6 weeks (Conservative measurement, ~450 channels) • Gains are uniform at the level of 0.5% (precision if integrator DAC fails) • Pedestals are stable at the level of • 0.5-1 per mille in several hours in quiet times CIS constants for a superdrawer (45 r/o channels) Rms/Mean < 0.5% for a period of 6 weeks. Analysis for all SDs is ongoing. Irene Vichou, LHCC Comprehensive Review

  20. Timing studies with LED • We use the LED (in the absence of the laser system): • To check the PMT responses • To equalize the timing in each module. Time differences which are used to set the delay on each digitizer Irene Vichou, LHCC Comprehensive Review

  21. Study of B-field effect 1) When Barrel Toroid field ramped to 18 kA (88% of nominal field), LED runs at the plateau and runs with no field were taken, reading out the current with the integrators (statistical precision was around 0.1%). The results showed changes <1% for ~8 superdrawers. 2) Measurement of the field in one of the TileCal fingers (LBC12). The value of ~20 Gauss was recorded, as expected. Full field reach Irene Vichou, LHCC Comprehensive Review

  22. Cosmics data ONLINE: Energy in a tower • Since summer several combined runs with the Larg have been taken. • Trigger via master-slave LTP chain • Trigger provided by the TileCal coincidence boards from UC. • 6/8 modules triggering, 16 read out. • Used the final ROD/ROS chain • Online monitoring was used for coarse or detailed quantities (e.g. pulse shapes) • HLT Athena monitoring and ATLANTIS Display was also tried online. • Offline analysis is ongoing. ONLINE! Irene Vichou, LHCC Comprehensive Review

  23. Some important integration milestones (phase II) COOLpit DAQ High speed tests, TTC synchronisation DAQ  DCS, OKS  configuration DB Configuration & condition DB for LV Trimmings in conf DB, LV FSM DCS Tile LCS Global Tile FSM HV in FSM? Trigger Intra module timing Test trigger towers, add cosmic cables Inter-module timing Monitoring GNAM for calibration run DSP, ROD mon., ATLANTIS devl. Histograms into DB Running from System Control Room, then ACR PLAN FORCombined CALO/DAQ/DCS run October December November Irene Vichou, LHCC Comprehensive Review

  24. Conclusions • During this year we gained (sometimes the hard way) a much better knowledge of our system at a large scale. • We developed procedures that help us certify efficiently our detector at commissioning • Looking forward to enrich our system and to continue integration to the ATLAS subsystems. THANK YOU! Irene Vichou, LHCC Comprehensive Review