TM0 components inventory and procurement schedule

TM0 components inventory and procurement schedule. In lab testing facility. Inventory layout. RF system Accelerating structure (x16) PETS structure (x8) RF distribution and loads Vacuum system BI and Vacuum systems BPM-DBQ chamber assembly Magnet system Cooling system Supporting system

gram
Download Presentation

TM0 components inventory and procurement schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TM0 componentsinventory and procurement schedule In lab testing facility A.Bartalesi

  2. Inventory layout • RF system • Accelerating structure (x16) • PETS structure (x8) • RF distribution and loads • Vacuum system • BI and Vacuum systems • BPM-DBQ chamber assembly • Magnet system • Cooling system • Supporting system • Pre-alignment system A.Bartalesi

  3. Components priority Labels: 3D done2D done Ordered Delivered A.Bartalesi

  4. Accelerating structureoverview Flange (VS) Compact load (RS) MB Unit (Assembly) Waveguides (RS) Manifold (RS) Intermodule interconnection (VS) Cooling tubes (RS) A.Bartalesi

  5. A.Bartalesi

  6. RF systemAccelerating structure (1 of 4) A.Bartalesi

  7. RF systemAccelerating structure (2 of 4) A.Bartalesi

  8. RF systemAccelerating structure (3 of 4) A.Bartalesi

  9. RF systemAccelerating structure (4 of 4) A.Bartalesi

  10. PETS structureoverview DRIVE BEAM – PETS ASSEMBLY PETS On-Off (Coupler) Cooling adapter Cooling tubes PETS Minitanks Cooling fittings adapter PETS Mock-Up Interconnection Flanges (Fixed) Interconnection Flanges (Fixed) A.Bartalesi

  11. A.Bartalesi

  12. RF systemPETS structure (1 of 3) A.Bartalesi

  13. RF systemPETS structure (2 of 3) A.Bartalesi

  14. RF systemPETS structure (3 of 3) A.Bartalesi

  15. RF distribution and loadsoverview RF networks Type 2 Type 1 Load Mock-up Load Mock-up A.Bartalesi

  16. RF systemRF distribution and loads A.Bartalesi

  17. Vacuum systemoverview Vacuum network Central vacuum tank and pumps Type 1 Type 2 A.Bartalesi

  18. A.Bartalesi

  19. WORK IN PROGRESS!! A.Bartalesi

  20. Vacuum system (1 of 2) A.Bartalesi

  21. Vacuum system (2 of 2) A.Bartalesi

  22. BI systemoverview Vacuum chamber BPM mockup Rotating flange A.Bartalesi

  23. BI System (1 of 2)(BPM-DBQ assembly) A.Bartalesi

  24. BI System (2 of 2) (BPM-DBQ assembly) A.Bartalesi

  25. Magnet systemoverview DBQ mock-up A.Bartalesi

  26. Magnet system (1 of 2) A.Bartalesi

  27. Magnet system (2 of 2) A.Bartalesi

  28. Cooling system A.Bartalesi

  29. Supporting systemoverview DB (boostec) Central vacuum tank support MB (microcontrole) A.Bartalesi

  30. A.Bartalesi

  31. Supporting system (1 of 2) A.Bartalesi

  32. Supporting system (2 of 2) A.Bartalesi

  33. Pre-alignment systemDB components only (1 of 2) A.Bartalesi

  34. Pre-alignment systemDB components only (2 of 2) A.Bartalesi

  35. Pre-alignment systemMB components only (1 of 2) A.Bartalesi

  36. Pre-alignment systemMB components only (2 of 2) A.Bartalesi

  37. Thanks for you interest -and- Thanks to all the procurement responsible people for their precious help! A.Bartalesi