Assembly and installation of TM0 Lab. F. Rossi. February 8th, 2012. MAGNETS & VACUUM TANKS. 4 DBQ (for 2 TM0) Installation on girders -> COMPLETED Alignment -> COMPLETED 2 VACUUM TANKS (for 2 TM0) Installation on girders -> COMPLETED. PETS UNITS. 2 PETS units (for 1st TM0)
E N D
Assembly and installation of TM0 Lab F. Rossi February 8th, 2012
MAGNETS & VACUUM TANKS • 4 DBQ (for 2 TM0) • Installation on girders -> COMPLETED • Alignment -> COMPLETED • 2 VACUUM TANKS (for 2 TM0) • Installation on girders -> COMPLETED
PETS UNITS • 2 PETS units (for 1st TM0) • Final brazing -> COMPLETED • Vacuum test -> COMPLETED • Fiducialisation -> COMPLETED • EBW -> COMPLETED • Vacuum test -> COMPLETED • Final dimensional control on Leitz -> COMPLETED • Installation on girders -> COMPLETED • STATUS: 100%
RF NETWORK & COMPACT LOAD • 2+2 RF networks (for 1 TM0) • Cleaning -> COMPLETED • 1st brazing -> COMPLETED • Intermediate machining -> COMPLETED • Cleaning -> COMPLETED • 2nd brazing -> COMPLETED • 3rd brazing -> IN PROGRESS • Vacuum test • STATUS: 80% • 20 Compact loads (for 1 TM0) • Final brazing -> COMPLETED • Vacuum test -> COMPLETED • STATUS: 100% • Vacuum network (for 2 TM0) • Delivery to Lab -> COMPLETED • STATUS: 100%
SUMMARY 1stTM0
SUMMARY 2nd TM0