An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EnergyDelivery Holland Bottom 500/161/115kV Substation Delivering energy safely, reliably, efficiently and affordably.

  2. Energy Delivery For the past two summers, several substations in the Little Rock area showed low voltages with no significant transmission line failures in the area. The loss of one of the 500/115 kV transformers at the Mabelvale substation in 2006 resulted in low voltages in the Little Rock area during periods when power was flowing from south to north. When this happens the loss of the second transformer at the Mabelvale substation could result in widespread low voltage in the Little Rock area. Holland Bottom 500 kV Substation

  3. Energy Delivery What’s Energy Delivery doing about these problems? ?

  4. Energy Delivery Building New Facilities to Mitigate Those Issues. Holland Bottom 500 kV Substation Phase 1: Build a 500/115kV substation near Cabot northeast of Little Rock. This will provide voltage support to Little Rock and reduce some thermal contingencies. Phase 1 is on track for its current projected in service date in 2011.

  5. Energy Delivery Phase 2: Install 161 kV bus and a 600 MVA 500 kV / 161 kV autotransformer. This will provide a strong source into Conway from the East. The 161kV at Holland Bottom will also provide a long term conversion of the 115kV to North Little Rock and to Searcy Price. Phase 2 is scheduled to be in service in 2012. Holland Bottom 500 kV Substation

  6. Energy Delivery Holland Bottom 500 kV Substation

  7. Energy Delivery Holland Bottom 500 kV Substation The site for the new 500 /115 kV substation was prepared late in 2010.

  8. Energy Delivery Holland Bottom 500 kV Substation Construction crane places steel bar foundation pier.

  9. Energy Delivery Holland Bottom 500 kV Substation Structural steel frame work of gas insulated switchgear building.

  10. Energy Delivery Holland Bottom 500 kV Substation Construction crane positions roof beam of gas insulated switchgear building.

  11. Energy Delivery Holland Bottom 500 kV Substation Near completed gas insulated switchgear building. Objects in foreground are high voltage breakers.

  12. Energy Delivery Holland Bottom 500 kV Substation Completed 500 kV gas insulated switchgear building.

  13. Energy Delivery Holland Bottom 500 kV Substation Gas Insulated switchgear building .Gas insulated switchgear minimizes the footprint of a substation switchyard.

  14. Energy Delivery Holland Bottom 500 kV Substation Contractor pours floor for cable trough from Gas insulated switchgear building to autotransformer pads.

  15. Energy Delivery Holland Bottom 500 kV Substation Crews constructing fire wall foundations between 500/115kv autotransformer pads.

  16. Energy Delivery Holland Bottom 500 kV Substation Cable trough from gas insulated switchgear building to autotransformer pads.

  17. Energy Delivery Holland Bottom 500 kV Substation 80-ton capacity crane relocates scaffolding.

  18. Energy Delivery Holland Bottom 500 kV Substation Completed 35' high firewall. These stand between the substation’s 500kv autotransformers.

  19. Energy Delivery Holland Bottom 500 kV Substation Firewalls that will separate autotransformers, completed cable troughs and switchyard terminal structures

  20. Energy Delivery Holland Bottom 500 kV Substation Completed 35' high firewalls that will separate 500kv autotransformers.

  21. Energy Delivery Holland Bottom 500 kV Substation Crew drilling foundation peers for fire wall foundation between 500/161kv autotransformer pads in phase two of site.

  22. Energy Delivery Holland Bottom 500 kV Substation Substation line bay dead end structures. Components on ground behind the vertical structures are 161 kV breakers.

  23. Energy Delivery Until this project and other improvements Entergy is making are complete, during times of high demand customers can help by conserving when possible. Holland Bottom 500 kV Substation Raise thermostats to 78 degrees. Use fans instead of air conditioners if possible. Use major appliances such as dryers, ovens, dishwashers and washing machines in the early morning or late evening hours. Close blinds, drapes and curtains during the heat of the day. Turn off unnecessary lights and use fluorescent light bulbs if possible. Power off computers, TVs and other electronics when not in use.