1 / 14

Conclusions of the follow-up review of LHC cryomagnet tests 16 December 2003

DRAFT. Conclusions of the follow-up review of LHC cryomagnet tests 16 December 2003. Ph. Lebrun. Background.

hinto
Download Presentation

Conclusions of the follow-up review of LHC cryomagnet tests 16 December 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DRAFT Conclusions of the follow-up review of LHC cryomagnet tests16 December 2003 Ph. Lebrun

  2. Background • In spite of remarkable progress achieved in 2003, reception tests of LHC cryomagnets remain a critical issue, with the long-sought development of series magnet production rates in industry • The criticality of this issue was foreseen in 2002, due to well identified structural and circumstantial causes; we therefore decided to follow it closely, through an array of actions, among which periodic reviews • review of reception tests of LHC cryomagnets of 23 July 2003 • this review of 16 December 2003 • Although it provided comprehensive data on test operation and results obtained in the second half of 2003, the December 2003 review proved unconclusive • insufficiently processed or inhomogeneous data • intense discussions which the agenda could not accommodate • An ad hoc meeting of the Group Leaders concerned was called on 9 January 2004, to provide decisive answers to a list of questions raised by the review Follow-up review of LHC cryomagnet tests 16 Dec 2003

  3. Aims of the review • Analyse the results obtained and the experience gained in the second half of 2003, with reference to the findings and recommendations of the July 2003 review • Identify and correct remaining difficulties • review capacity limits of test infrastructure and equipment • review contents, constraints and resource requirements of the test programs, with the aim of further streamlining • review organization of work • Agree on updated test plan for 2004 and later • Involve all concerned parties Follow-up review of LHC cryomagnet tests 16 Dec 2003

  4. Participants Follow-up review of LHC cryomagnet tests 16 Dec 2003

  5. Programme Follow-up review of LHC cryomagnet tests 16 Dec 2003

  6. Conclusions [1/5] • Significant progress achieved, with 90 magnets tested in 2003, however insufficient, as backlog of untested magnets built up to 85 by the end of the year Follow-up review of LHC cryomagnet tests 16 Dec 2003

  7. Conclusions [2/5] • Bench occupancy still a factor of ~2 above expected, with delays on all phases of sequence • connection & removal: 24 h planned, 30 h observed average + 33 h waiting time! • intervention by ICS for magnet connection/removal on weekends (A. Poncet) • pumpdown: 12 h planned, 13 h • explore possibility of shortening pumpdown (L. Tavian) • leak search: planned during pumping, + 15 h observed avg • define and enforce leak-testing procedure by ALLS (L. Tavian) • cooldown: 24 h planned, 46 h observed avg • warmup: 12 h planned, 32 h observed avg • increase cooldown/warmup flow-rate (higher Psuction, 3rd circulator) (L.Tavian) • cold tests: 36 h slot, 72 h observed avg due to • more than 2 hi-field quenches & thermal cycle • sequencing between benches • insufficient coordination between teams • review conditions of “cryo O.K.” flag (L. Tavian) • implement Test Tracking System for uniform & up-to-date information of teams involved (L. Tavian) Follow-up review of LHC cryomagnet tests 16 Dec 2003

  8. L. Walckiers Follow-up review of LHC cryomagnet tests 16 Dec 2003

  9. Conclusions [3/5] • Power tests • large incidence of hi-field quenches & thermal cycles on test programme • overall cryogenic capacity of test station sets limit to number of quenches (6 hi-field quenches + 2-3 magnet subcoolings per day) • 2 hi-field quenches are sufficient to assess electrical integrity of magnet • no strong technical case to measure retraining, hence no use of thermal cycle on series magnets • revised procedure & flow chart for power tests (Action L. Rossi) • Magnetic measurements • adequate cold/warm correlations for multipoles • importance of field integral and field angle measurements • good correlation between apertures • implement field integral & angle measurement in one aperture, consider replacement of long shaft by stretched wire for series (Action L. Walckiers) Follow-up review of LHC cryomagnet tests 16 Dec 2003

  10. MBOK MBOK MBOK Quench ? Quench ? Reduced Training Program (proposal) Shoot to 9 T n Provoke 1 Q @ 8.33 T n Verify 8.4 T Quench ? y y Shoot to 9 T n n y Q < ? 8.4 T Verify 8.4 T Quench ? y y n • Contractual Acceptance • MB should reach 9 T after 8 quenches • If more than 5 quenches to reach 9 T • Thermal cycle performed • MB should reach 8.6 T at 1st quench Follow-up review of LHC cryomagnet tests 16 Dec 2003

  11. Reduce Magnetic Measurement : Strategy Field Quality cold measurement on 50 MB : extended measurements + 150 MB : Bdl& multipole (static & dynamic) + 200 MB : W/C correlation (static) Measure b1, a1 with SSW during cold tests a1 with SSW in SMI2 : ready a1 with mole in SMA18 : 2 to 3 MB/week a1 with DIMM in Industry : mid-Febr. L. Walckiers Follow-up review of LHC cryomagnet tests 16 Dec 2003

  12. Conclusions [4/5] • Management & organization • reaffirm executive responsibilities of hierarchical line • MTM group leader • Test Operation section leader • Shift leader • reinforce leverage of Test Operation section leader on services • equipment support teams in MTM & other groups • industrial support • reaffirm consultative scientific role of test coordinators • provide adequate training to operators, shift leaders, test coordinators • improve representation in and functioning of Test Operation weekly meeting • develop & implement test assessment and follow-up tools (Actions L. Walckiers) Follow-up review of LHC cryomagnet tests 16 Dec 2003

  13. Conclusions [5/5] • Completion of the test station & future tests • Restart operation in January 2004 with 8 benches operational • Availability of remaining benches • B2 1 March 2004 • B1 15 March 2004 • A2 15 April 2004 • A1 22 April 2004 • Allocation of 2 benches to SSS series tests (D1 & D2) • 160 dipoles & 55 SSS tested by mid-2004 • 2 magnets/day from mid-2004 onwards • Catching up with the backlog • mostly composed of cross-section 2 dipoles • allocate 4 benches to tests of backlog magnets, out of which 2 configured for tests without anticryostats • only perform magnetic measurements on cross-section 3 dipoles • establish detailed test programme of backlog magnets (Action L. Rossi) Follow-up review of LHC cryomagnet tests 16 Dec 2003

  14. L. Walckiers Follow-up review of LHC cryomagnet tests 16 Dec 2003

More Related