1 / 6

Status of Project Reporting

Understand the reporting process for NPA-funded projects including deadlines, project periods, and submission criteria to ensure compliance and successful reporting. Plan ahead for timely submissions to meet program requirements and maintain transparency in project finances.

hvega
Download Presentation

Status of Project Reporting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status of Project Reporting Rachel Burn, Joint Secretariat. September 29th Akureyri.

  2. Reporting • 20 Projects are now in the process of reporting.

  3. 3rd Call • In February 2016 the Monitoring Committee approved: • 1. SECURE • 2.WATERPRO • 3. ASCENT • 4. E-LIGHTHOUSE • 5. BUSK

  4. eMS and Reporting • Main Projects run for a period of 36 months which includes the submission of the final reporting of the project. • Main projects are expected to submit a project report on a 6-monthly basis. • The reporting periods are decided on the basis of the project implementation start date, which means that the reporting periods differ from project to project • After the end of the reporting period, projects have 3 months to submit their complete project report, which includes the certification of costs by FLC. • Project reporting periods are visible in GOL and in eMS

  5. eMS and Reporting • Reporting deadline A complete Project Report procedure is set to a maximum of three months after the end of the reporting period. • It is up to the Lead Partner to set internal deadlines for project partners in order to meet the 3-month deadline. • Please note that First Level Controllers are entitled to 2 months for their certification of the costs. • For the 1st and 2nd reporting periods the programme has applies flexibility*

  6. Thank you for listening • Rachel Burn • rachel.burn@interreg-npa.eu

More Related