Drift Chamber Status Report

Drift Chamber Status Report. Tokyo PHENIX Meeting. Milestones Achieved. Initial delay in start of net production; 2 weeks due to late delivery of small US made precision screws. Middle October: 13 X-nets made and tested at PNPI: 8 excellent (<2 namp) 3 acceptable (<50 namp) 2 sparked:

irving
Download Presentation

Drift Chamber Status Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Drift Chamber Status Report Tokyo PHENIX Meeting

  2. Milestones Achieved • Initial delay in start of net production; 2 weeks due to late delivery of small US made precision screws. • Middle October: 13 X-nets made and tested at PNPI: • 8 excellent (<2 namp) • 3 acceptable (<50 namp) • 2 sparked: • One stray wire strand. • One poor glue application.

  3. MECH Milestones continued • End of October: • 32 UV nets made, all excellent. • Early November: • Mechanical mods to the Large prototype begun. • Shipped 10 wire modules (2 X, 4 U, 4 V). • Middle November: • Wire modules arrive intact (no tangling) • Installation complete by Thanksgiving.

  4. New Modules Installed

  5. Module Profile Old: UV cages “Tilt” into active volume New: UV cages flush with end

  6. Feedthroughs

  7. Component Overview The ASD/TMC card accepts chamber signals directly. The FEM card responds to triggers and orchestrates readout of 4 ASD/TMC cards (one “Keystone”). ASD8 = preAmp, Shaper, Discriminator (“PENN chip”) TMC = Time Memory Cell, Yasuo Arai KEK.

  8. ASD/TMC Tests • Real ASD/TMC Card • Mini FEM => Logic analyzer • ARCNet/Timing Emulation Box: • Supplies pulses • Supplies triggers • Supplies ENDat’s

  9. Noise Tests on Chamber On Chamber HV connected reads always running 3fC threshold TMC level • With the scope set to 5 second persistence, we record all disc firings. • No white noise! • Readout noise comes from Mini-FEM

  10. Interim Readout Solution

  11. All RC cards installed. Pure nitrogen tests, all cages at once. Corona at expected point. Need one more day of turns w/ 50-50. No measurable leaks. Vlad seems optimistic. MECH: Since leaving for QM97

  12. ELEC: Since Leaving for QM97 • A-side signal boards stuffed and tested. • ARCNet slave FPGA design complete. • We’ll write user code in ARCNet board called from hooks inside JF code (a standard option!). Otherwise too slow. Some code written. • g-2 blank FIFO card and most parts in hand. • Pre-prod proto shipped from LLNL. • Need to address: • Cabling • DC-DC convertor mechanical details.