WECC 2013 TPL Assessment Coordination, PCC Task Force Review

WECC 2013 TPL Assessment Coordination, PCC Task Force Review. Not for Vote. Task Force Members. Brian Keel – SRP Jeff Mechenbier Marv Landauer Gordon Dobson – Mack Tom Green Bob Easton Chuck Matthews Melvin Rodrigues Muhkles Bhuiyan. 2013 TPL Coordination Analysis.

Download Presentation

WECC 2013 TPL Assessment Coordination, PCC Task Force Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WECC 2013 TPL Assessment Coordination, PCC Task Force Review Not for Vote

  2. Task Force Members • Brian Keel – SRP • Jeff Mechenbier • Marv Landauer • Gordon Dobson – Mack • Tom Green • Bob Easton • Chuck Matthews • Melvin Rodrigues • MuhklesBhuiyan

  3. 2013 TPL Coordination Analysis • September 8th,2011 outage • O & P7 – WECC should develop recommendations for improving coordination of TPL Assessments • WECC initiated survey and finished report based on the O & P7 and survey results. • WECC staff response to results were • Standardize assessment practices • Encourage expanded coordination of assessmsnts

  4. Major Issues from 10 recommendations of WECC Report • Report recommends sharing of assessments • Many WECC already do so • Task Force recommends the sharing, TPL-001-4 Requirement will mandate the sharing to neighboring TP and PCs • (Action) WECC staff to keep mailing list of TP and PC contacts to foster the communication • Task Force recommends to share, but understands the reluctance of some to go beyond strict letter of Requirement

  5. Major Issues from 10 recommendations of WECC Report • Each TP and PC understand their responsibilities • TPL – 001-4 Requirement 7 will mandate this

  6. Major Issues from 10 recommendations of WECC Report • Refining Data Prep Manual )DPM) for which Projects included and Projects removed • Communicated and agreed to by TSS

  7. Major Issues from 10 recommendations of WECC Report • PCC should develop process or guide for how TPL Assessments are shared. • Task Force recommends to keep ambiguous because fully developed plans may not be available for each year

  8. Conclusions: • NERC TPL-001-4 Requirements to handle some of the suggestions • Foster communication of the Assessments through Contact list maintenance • Better control of Projects in WECC Base Cases • Recommends Regional Planning participation • Action Item or Assignment - for WECC Staff to maintain the TP and PC contact list