E N D
1. Fossil & Hydro Leadership Meeting
2. Brayton Point StationClosed Cycle Cooling Natural Draft Cooling Towers
4. Cooling Tower – Artist Rendering
5. Cooling Tower – Arrangement Overlay
6. Natural Draft Cooling Tower 3D Model Integration
7. Closed Loop Cooling – Project Status
Brayton’s use of once through cooling water has been a regulatory issue since 1970’s
Decline of flounder in the bay in the late 1980’s sharpen DEP/EPA focus on Brayton
October 2003 EPA issue Brayton a NDPES permit that only could be met with closed cycle cooling
Permitting commenced January 2008 – Final permits received May 13, 2009
Current EPA order schedule requires in-service by winter 2011 – spring 2012
> 95% reduction in cooling water flow and thermal discharge
First natural draft cooling towers built in the United States in ~20 years
8. Closed Loop Cooling – Project Status Kiewit Construction Co. – awarded EPC in August of 2008
Engineering approximately 76% complete
Cooling tower foundation commence on May 14, 2009
Tower piles completed on September 3, 2009; 10 weeks early
1,592 total piles to driven for cooling towers
Tower supports are 20” square concrete PSCP
Project Facts
1.5 miles of circ water tunnels
75,000 cubic yds of concrete
10,000 tons of reinforcing steel
6,500 feet of conduit
9. Natural Draft Cooling Tower Fundamentals
10. Natural Draft Cooling Tower Fundamentals
11. Cooling Tower Details
Shell
497’ tall
365’ diameter at the base
222’ diameter at the outlet
Each tower will be surrounded by a noise reduction wall
2010 Activities
Major focus in 2010 will be the erection of the cooling tower
12. DOKA Climbing Forms
13. DOKA Climbing Forms
14. DOKA Climbing Forms
15. Closed Loop Cooling – Positive Financial Impacts
Total project cost to Dominion - $620,000,000
Infusion of multi-millions of dollars into the local economy
Material suppliers
Sub-contractors
Lodging and restaurants
Employment of 250 + local union trades
Continued viability of Brayton Point Station as a large local employees for years that follow
16. Cooling Tower Project Challenges Aggressive Compliance Schedule
Retrofit of Closed Loop Cooling while Maintaining Station Operations
Lack of Recent Natural Draft Experience in the U.S. Construction Market
Large (60” - 108”) Bore Piping Installed through the “Heart” of the existing Station undergrounds
Material Lead Times – 60-70 weeks for pumps
Magnitude of Construction Impacts on Station Access and Existing Operations
Weather Constraints on Tower Erection
17. Closed Loop Cooling – View Looking North
18. Closed Loop Cooling – View Looking North