This project involves measuring and supporting various magnets in accelerators, including the Linac, Booster, Main Injector, P-Bar Source, and Tevatron. Measurements will be conducted on different magnet types and strengths, and any necessary repairs or refurbishments will be made. This project also includes the development of new magnets for future projects like LBNE, Project X, Mu2e, and G-2. Additionally, there is a need to upgrade the DAQ measurement system for increased efficiency and reliability.
E N D
FY10 and beyond Accelerator Support Magnet Measurements 14 Jan 2010 G.Velev
By machine • Linac • Booster • Main Injector • P-Bar Source • Tevatron
Linac • 2-3 solenoids for Linac RFQ - R&D, need By Sep.-Oct 2010. • Possible measurements • Sep 09 • Hall probe scanning
Booster - BMA • Some study of the magnet anomalies seen in 31,47 and 62 • low priority • need to check a couple of good magnets
Booster VBC • Measuring the integral field and harmonics - March 2010
Main Injector: IQx Quadrupoles • About a dozen are recovered from PW5 • Re-conditioning • Re-measuring • Refurbish 1-2 IQG->IQB • Optimistically 1-2 IQx may be measured/checked
Main Injector: ILA Lambertsons • Two spare magnets – ready for measurement • Wait for Stand A • SSW • Spring-Summer
P-Bar: SDFB->SDFW • Magnet was just started • Strength and harmonics in April-May
Tevatron measurements • Unlikely
NOvA • Kickers • ADCW – 3 magbets • Lambertsons –3 MLAW magnets (wide) • Permanent magnets • PDD – 5 magnets • PDDW - 2 magnets (weak) • RQ quadrupoles – trimming and 10 new magnets
NOA/ANU: Kickers • We are producing 7 new kickers for NOvA • We have all major measurement apparatus • For now - Luciano’s group • Magnetic measurements???
NOA/ANU: ADCW reworked dipoles • Production measurements – Jan-Sep • Integrated strength • Field shape • AC measurement at 15 Hz – next week • 3 Magnets
MLAW • Three magnets • SSW • Rotating coil ?? • Summer-Fall 2010
Nova - Permanent dipoles • PDD and PDDW (weak) • 5 PDD + 2 PDDW • Integral strength • Harmonics • Fall 2010 –Winter 2011
Nova - Permanent dipoles PDS • 2 PDS (strong) • Integral strength • Harmonics • May need tuning • Summer 2010
Nova - Permanent magnet R&D • Quadrupole trimming capability • Integral Strength • Thermal compensation • Build 10 RQM – 2011 • Integral • Harmonics • Summer 2011 or later
Helical Solenoid 2 • Second model • Warm measurements –Feb10 • Hall probe scan • Cold 2010
μ→e : AC dipole • rep rate ~ 0.3 MHz (Fermilab) ~0.03 T-m peak • rep rate ~ 5.1 MHz (Fermilab) ~0.008 T-m peak • Integrated field • Prototype 2010 • Measurements
μ→e : Solenoid model • Just started - Apr 2010 ready • Measurements – not specified
TQTC100 • Magnet is on the stand • DC integral strength • Harmonics • Unique one
Mapping MINERvA dipoles • Two small spectroscopic magnets • January 2010 • Hall probe map
Everything repaired and fixed • Any magnet which comes for a repair • Occasional tasks
New Projects • LBNE (DUSEL) – ~150 MI type dipoles, quads and correctors for the beam line • Project X - ~ 110 dipoles, quads (correctors are not included) for 2-8 GeV Booster • Mu2e – the beam (snake type ) solenoid, I am not sure about the detector magnet, 3-4 AC dipoles • G-2 - no any significant request for magnets
DAQ Upgrade for satandA,B &C • For next 4-6 years we may need to measure ~ 200-300 magnets or if we decided fraction of them • Stands A,B and C need upgrade of the DAQ measurement system to increase the efficiency and reliability of the measurement process - T&I and MS joint R&D effort is needed