Special Report NuMI Target Updates

Kris Anderson 21-Mar-2011. Special Report NuMI Target Updates. Ongoing Work - Four Parallel Activities, Now Three Target Hall • NT-05 has been secured in NuMI Target Hall Morgue • Target module ready to accept new target Autopsy of NT-05 in Target Hall Workcell

kana
Download Presentation

Special Report NuMI Target Updates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kris Anderson 21-Mar-2011 Special Report NuMI Target Updates • Ongoing Work - Four Parallel Activities, Now Three • Target Hall • • NT-05 has been secured inNuMI Target Hall Morgue • • Target module ready to accept new target • Autopsy of NT-05 in Target Hall Workcell • • Done- All work on this task complete • Reclaim NT-02 as a contingency spare • •Good News: Pressure test results indicate NT-02 is still leak tight on the water and canister He volume circuit • • Bad News: Z-drive motion is likely compromised in perhaps a couple of locations • • ALARA plan in process to address slipping couplers and new bearings blocks • • May require~2 weeks of effort to reclaim z-drive motion (if possible) • NT-06 Retrofit (Activities currently on the critical path) • • Target core successfully extracted from support casing • • Old DS water turnaround successfully removed using wire EDM in WHMS • • New water turnaround design successfully fabricated, welded, X-ray inspected, • and pressure tested to 2400 psig • •Turnaround will be welded toNT-06 core and X-ray inspected Tuesday 3/22 • • All other target canister final assembly, survey, and QA expected to be complete • bySaturday 3/26

  2. Previously Identified Potential Failure Location Special Report NuMI Target Updates Downstream Water Turnaround Weldments NuMILow Energy Target General Assembly Layout

  3. Special Report NuMI Target Updates NT-06 Retrofit NT-06 Target Core in Processing Fixture

  4. Special Report NuMI Target Updates NT-06 Retrofit Original NT-06 Downstream Water Circuit Welds patched with solder

  5. Special Report NuMI Target Updates NT-06 Retrofit Original NT-06 Downstream Water Circuit Turnaround end not welded perpendicular to core centerline

  6. Special Report NuMI Target Updates NT-06 Retrofit Surgery Time Wire EDM operation to remove original water turnaround Successful cut

  7. Special Report NuMI Target Updates NT-06 Retrofit New Style Water Turnaround Successful X-ray inspection Successful pressure test to 1500 psig

  8. Special Report NuMI Target Updates NT-06 Retrofit NT-06 Cooling tube transition sleeves cleaned and ready for retrofit

  9. Special Report NuMI Target Updates NT-06 Retrofit NT-06 Retrofit ready for welding and X-ray inspection Tuesday 3/22

  10. Key Dates Special Report NuMI Target Updates Estimated Key Dates-Nominal Scenario I. NT-06 Path •NT-06 retrofit should be completion 3/26 • Efforts for NT-06 Target/Baffle Carrier final outfitting at MI-8, survey, and Q/A expected to occur 3/28 – 4/2 • Installation of NT-06 into target chase during 4/4 – 4/9 • Estimate for beam ~12:00 on Sunday 4/10 II. NT-02 Path (Contingency Target) • NT-02 is leak tight but status of z-drive reclamation is still TBD • Likely to take about 1.5 -2 weeks of effort to define and implement procedure to assess and return z-drive mechanism to operational status; Estimate z-drive recovery end of March if repairable