CSC Commissioning. Andrey Korytov. Outline. CMS schedule v31 EMU schedule EMU installation windows Shipping container Tests on arrival at CERN Quick pre-installation test Installation/commissioning sequence On-disk local commissioning Station commissioning. V31: March 2001.
E N D
CSC Commissioning • Andrey Korytov
Outline • CMS schedule v31 • EMU schedule • EMU installation windows • Shipping container • Tests on arrival at CERN • Quick pre-installation test • Installation/commissioning sequence • On-disk local commissioning • Station commissioning
V31: May 6, 2001 • Muon system installation windows v31: Austin Ball, May 6, 2001 • ENDCAP: • ========================================================================================= • start finish comments • ========================================================================================= • YE-1 23 Jul 02 14 Oct 02 free access • YE-1 22 Oct 02 23 Apr 03 share with YB- (no YB- work planned) • YE-1 23 Apr 03 15 Sep 03 shared with vac tank & coil • YE-1 12 Jan 04 18 Feb 04 free access • YE-1 12 Jul 04 03 Dec 04 crane shared with UX supply • YE-2 18 Jun 02 14 Oct 02 free access • YE-2 22 Oct 02 23 Apr 02 share with YB- (no YB- work planned) • YE-2 23 Apr 03 15 Sep 03 shared with vac tank & coil • YE-2 12 Jan 04 18 Feb 04 free access • YE-2 12 Jul 04 10 Dec 04 crane shared with UX supply • YE-3 09 Jul 02 14 Oct 02 free access • YE-3 22 Oct 02 23 Apr 02 share with YB- (no YB- work planned) • YE-3 23 Apr 03 15 Sep 03 shared with vac tank & coil • YE-3 12 Jan 04 18 Feb 04 free access • YE-3 12 Jul 04 17 Dec 04 crane shared with UX supply • ========================================================================================= • YE+1 27 Jan 03 15 Nov 03 free access • YE+1 17 Dec 03 02 Mar 03 free access • YE+1 12 Jul 04 30 Aug 04 crane shared with UX supply • YE+2 14 Oct 02 15 Nov 03 free access • YE+2 17 Dec 03 02 Mar 03 free access • YE+2 12 Jul 04 02 Sep 04 crane shared with UX supply • YE+3 28 Oct 02 15 Nov 03 free access • YE+3 17 Dec 03 02 Mar 03 free access • YE+3 12 Jul 04 15 Sep 04 crane shared with UX supply • =========================================================================================
EMU Installation/Commissioning March V31 version
Shipping Containers • stacks of 5 boxes (easily re-stackable) • chambers are assembled and tested with electronics: • once cover is taken off, one can connect and readout all electronics without extracting a chamber • HV and Gas connectors accessible without opening boxes: • test for gas leaks • test for broken wires and HV disconnections in air • test dark current at nominal HV and nominal gas mixture
CSCs will arrive to ISR Gas pipes?
Handling on Arrival Semi-clean rooms? 1) Truck enters here 2) Unloading Stacks of 5 CSCs 3) Stacks are moved to the tunnel
ISR: storage hall 4)HV and Leak Test in boxes 4*) Broken CSCs go to semi- clean room for repair • 5) Pre-installation Test: • dark current test (nominal mix) • un-stack, spread, and open • use portable mini-FAST DAQ: • LVDB mezzanine board • ALCT self-test • CFEB connectivity • CFEB noise • CFEB calibration • AFEB connectivity • AFEB noise • ALCT/CLCT Self-trigger • Glue alignment pads (?) • close and stack again • gas: Ar+CO2 Notes: Italic--we may want to skip later ME1--may require pre-installation tests conducted twice (on arrival and before installation)
SX5: installation/commissioning:tentative sequence under scrutiny • ME2 (example): 36+18=54 CSCs • deliver to SX5 30 chambers (6 stacks) = (5 days) • (gas leak in FY02-03 when we have time) = (6 days) • burst of installation of “back” chambers @ 4 CSC/day = 7 days XY • check for gas leak, in parallel with • burst of cabling/piping for back chambers @ 4 CSC/day = 7 days Y • commission “back” CSCs @ 4 CSC/day (portable HV and DAQ) = 7 days Y • at the same time deliver to SX5 another 30 chambers = (5 days) • burst of installation of “front” chambers @ 4 CSC/day = 7 days XY • check for gas leak, in parallel with • burst of cabling/piping for “front” chambers @ 4 CSC/day = 7 days Y • commission gas/water for the station = 1 day Y • commission “front” CSCs @ 4 CSC/day (portable HV and DAQ) = 7 days Y • alignment photogrametry = 2 days Y ------------- = 45 days • after that maintain Ar+CO2 gas flow, monitor gas leaks, test HV periodically X - need for crane, Y - need for cherry picker
Commissioning Tests to be based on FAST site DAQ MINIMAL COMMISSIONING TESTS are in BOLD 1 Assembly 2 Water leak 3 LV electronics turn-on 4 HV turn on (current and cabling) 5 ALCT self-test 6 AFEB Noise test 7 AFEB Connectivity & Alive 8 AFEB Threshold and Analog Noise 9 AFEB Time Delay 10 CFEB Noise 11 CFEB Connectivity and Alive 12 CFEB Calibration 13 Comparator Noise 14 Comparator Threshold 15 Left/Right Comparator Logic 16 Left/Right Comparator Offset 17 Neighbor Comparator Offset 18 Comparator Timing 19 Chamber gain map 20 ALCT self-trigger on cosmics (need gas+HV) 21 CLCT self-trigger on cosmics (need gas+HV) 22 High-statistics cosmics (strip analysis) 23 Performance vs HV 24 High-rate test
Commissioning Manpower • Overall Coordination: 1 FTE (senior) • DAQ Expert: 1 DAQ software expert • ISR: 1 expert, 2 techs • Receiving, quick check on arrival • Pre-installation tests • Repairs, replacement of boards • SX5: 2 experts, 2 techs • Signal cable dressing/tests (on disks) • Service cables (HV, LV, slow control), pipes, hoses… • Post-installation commissioning
Summary: 2001-2002 • 2001: • next 6 mo: start forming a core of CERN-residing physicists define all steps and procedures both at ISR and SX5 • 2002: • January: First 10 CSCs will arrive to CERN-ISR • January: Portable DAQ and Equipment at CERN-ISR Test environment (gas, outlets, Ethernet, etc.) Working place (desks, phones, cabinets, etc.) CSC test and repair tooling, clean room • Jun-Aug: Pre-installation tests of 36 ME23/2 and 18 ME2/1 • June: One more portable DAQ and Equipment at SX5 Test and work environment • August: Finish YE-2 infrastructure • Sep-Dec: Installation/commissioning of ME-2
Summary: 2003-2004 • 2003: • Jan-Feb: Pre-installation tests of 36 ME23/2 and 18 ME2/1 • Mar-Apr: Installation/commissioning of ME+2 • May-Jun: Pre-installation tests of 36 ME23/2 and 18 ME3/1 • Jul-Aug: Installation/commissioning of ME-3 • Sep-Oct: Pre-installation tests of 36 ME23/2 and 18 ME3/1 • Nov-Dec: Installation/commissioning of ME+3 • 2004: • Jan: Pre-installation tests of 18 ME4/1 • Feb: Installation/commissioning of ME+4/1 • Mar-Jun: Pre-installation tests of 74 ME1/2, 54 ME1/3, 18 ME4/1 (Magnet test at SX5) • Jul-Aug: Installation/commissioning of ME+1/2 and +1/3 • Sep: Installation/commissioning of ME-4/1 • Sep: Pre-installation tests of 18 ME1/3 • Oct-Nov: Installation/commissioning of ME-1/2 and -1/3