An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CSC Commissioning • Andrey Korytov

  2. Outline • CMS schedule v31 • EMU schedule • EMU installation windows • Shipping container • Tests on arrival at CERN • Quick pre-installation test • Installation/commissioning sequence • On-disk local commissioning • Station commissioning

  3. V31: March 2001

  4. V31: May 6, 2001 • Muon system installation windows v31: Austin Ball, May 6, 2001 • ENDCAP: • ========================================================================================= • start finish comments • ========================================================================================= • YE-1 23 Jul 02 14 Oct 02 free access • YE-1 22 Oct 02 23 Apr 03 share with YB- (no YB- work planned) • YE-1 23 Apr 03 15 Sep 03 shared with vac tank & coil • YE-1 12 Jan 04 18 Feb 04 free access • YE-1 12 Jul 04 03 Dec 04 crane shared with UX supply • YE-2 18 Jun 02 14 Oct 02 free access • YE-2 22 Oct 02 23 Apr 02 share with YB- (no YB- work planned) • YE-2 23 Apr 03 15 Sep 03 shared with vac tank & coil • YE-2 12 Jan 04 18 Feb 04 free access • YE-2 12 Jul 04 10 Dec 04 crane shared with UX supply • YE-3 09 Jul 02 14 Oct 02 free access • YE-3 22 Oct 02 23 Apr 02 share with YB- (no YB- work planned) • YE-3 23 Apr 03 15 Sep 03 shared with vac tank & coil • YE-3 12 Jan 04 18 Feb 04 free access • YE-3 12 Jul 04 17 Dec 04 crane shared with UX supply • ========================================================================================= • YE+1 27 Jan 03 15 Nov 03 free access • YE+1 17 Dec 03 02 Mar 03 free access • YE+1 12 Jul 04 30 Aug 04 crane shared with UX supply • YE+2 14 Oct 02 15 Nov 03 free access • YE+2 17 Dec 03 02 Mar 03 free access • YE+2 12 Jul 04 02 Sep 04 crane shared with UX supply • YE+3 28 Oct 02 15 Nov 03 free access • YE+3 17 Dec 03 02 Mar 03 free access • YE+3 12 Jul 04 15 Sep 04 crane shared with UX supply • =========================================================================================

  5. V31: May vs. March 2001

  6. FNAL--UC/UF Schedule

  7. PNPI Schedule

  8. IHEP Schedule

  9. EMU Installation/Commissioning March V31 version

  10. Shipping Containers • stacks of 5 boxes (easily re-stackable) • chambers are assembled and tested with electronics: • once cover is taken off, one can connect and readout all electronics without extracting a chamber • HV and Gas connectors accessible without opening boxes: • test for gas leaks • test for broken wires and HV disconnections in air • test dark current at nominal HV and nominal gas mixture

  11. CSCs will arrive to ISR Gas pipes?

  12. Handling on Arrival Semi-clean rooms? 1) Truck enters here 2) Unloading Stacks of 5 CSCs 3) Stacks are moved to the tunnel

  13. ISR: storage hall 4)HV and Leak Test in boxes 4*) Broken CSCs go to semi- clean room for repair • 5) Pre-installation Test: • dark current test (nominal mix) • un-stack, spread, and open • use portable mini-FAST DAQ: • LVDB mezzanine board • ALCT self-test • CFEB connectivity • CFEB noise • CFEB calibration • AFEB connectivity • AFEB noise • ALCT/CLCT Self-trigger • Glue alignment pads (?) • close and stack again • gas: Ar+CO2 Notes: Italic--we may want to skip later ME1--may require pre-installation tests conducted twice (on arrival and before installation)

  14. SX5: installation/commissioning:tentative sequence under scrutiny • ME2 (example): 36+18=54 CSCs • deliver to SX5 30 chambers (6 stacks) = (5 days) • (gas leak in FY02-03 when we have time) = (6 days) • burst of installation of “back” chambers @ 4 CSC/day = 7 days XY • check for gas leak, in parallel with • burst of cabling/piping for back chambers @ 4 CSC/day = 7 days Y • commission “back” CSCs @ 4 CSC/day (portable HV and DAQ) = 7 days Y • at the same time deliver to SX5 another 30 chambers = (5 days) • burst of installation of “front” chambers @ 4 CSC/day = 7 days XY • check for gas leak, in parallel with • burst of cabling/piping for “front” chambers @ 4 CSC/day = 7 days Y • commission gas/water for the station = 1 day Y • commission “front” CSCs @ 4 CSC/day (portable HV and DAQ) = 7 days Y • alignment photogrametry = 2 days Y ------------- = 45 days • after that maintain Ar+CO2 gas flow, monitor gas leaks, test HV periodically X - need for crane, Y - need for cherry picker

  15. Commissioning Tests to be based on FAST site DAQ MINIMAL COMMISSIONING TESTS are in BOLD 1 Assembly 2 Water leak 3 LV electronics turn-on 4 HV turn on (current and cabling) 5 ALCT self-test 6 AFEB Noise test 7 AFEB Connectivity & Alive 8 AFEB Threshold and Analog Noise 9 AFEB Time Delay 10 CFEB Noise 11 CFEB Connectivity and Alive 12 CFEB Calibration 13 Comparator Noise 14 Comparator Threshold 15 Left/Right Comparator Logic 16 Left/Right Comparator Offset 17 Neighbor Comparator Offset 18 Comparator Timing 19 Chamber gain map 20 ALCT self-trigger on cosmics (need gas+HV) 21 CLCT self-trigger on cosmics (need gas+HV) 22 High-statistics cosmics (strip analysis) 23 Performance vs HV 24 High-rate test

  16. Commissioning Manpower • Overall Coordination: 1 FTE (senior) • DAQ Expert: 1 DAQ software expert • ISR: 1 expert, 2 techs • Receiving, quick check on arrival • Pre-installation tests • Repairs, replacement of boards • SX5: 2 experts, 2 techs • Signal cable dressing/tests (on disks) • Service cables (HV, LV, slow control), pipes, hoses… • Post-installation commissioning

  17. Summary: 2001-2002 • 2001: • next 6 mo: start forming a core of CERN-residing physicists define all steps and procedures both at ISR and SX5 • 2002: • January: First 10 CSCs will arrive to CERN-ISR • January: Portable DAQ and Equipment at CERN-ISR Test environment (gas, outlets, Ethernet, etc.) Working place (desks, phones, cabinets, etc.) CSC test and repair tooling, clean room • Jun-Aug: Pre-installation tests of 36 ME23/2 and 18 ME2/1 • June: One more portable DAQ and Equipment at SX5 Test and work environment • August: Finish YE-2 infrastructure • Sep-Dec: Installation/commissioning of ME-2

  18. Summary: 2003-2004 • 2003: • Jan-Feb: Pre-installation tests of 36 ME23/2 and 18 ME2/1 • Mar-Apr: Installation/commissioning of ME+2 • May-Jun: Pre-installation tests of 36 ME23/2 and 18 ME3/1 • Jul-Aug: Installation/commissioning of ME-3 • Sep-Oct: Pre-installation tests of 36 ME23/2 and 18 ME3/1 • Nov-Dec: Installation/commissioning of ME+3 • 2004: • Jan: Pre-installation tests of 18 ME4/1 • Feb: Installation/commissioning of ME+4/1 • Mar-Jun: Pre-installation tests of 74 ME1/2, 54 ME1/3, 18 ME4/1 (Magnet test at SX5) • Jul-Aug: Installation/commissioning of ME+1/2 and +1/3 • Sep: Installation/commissioning of ME-4/1 • Sep: Pre-installation tests of 18 ME1/3 • Oct-Nov: Installation/commissioning of ME-1/2 and -1/3