Accelerator Support and Maintenance. Run 14. Maintenance this week. Initiated by PHENIX access. NOVAC leak repair ~6hrs Maintenance Day declared for RHIC. 8 hours. Many areas of RHIC opened, some remain on CA. No Booster access AGS Acces s 0800-1400hrs. Major RHIC Effort:. RMMPS
E N D
Maintenance this week • Initiated by PHENIX access. • NOVAC leak repair ~6hrs • Maintenance Day declared for RHIC. • 8 hours. • Many areas of RHIC opened, some remain on CA. • No Booster access • AGS Access 0800-1400hrs.
Major RHIC Effort: • RMMPS • Stochastic cooling equipment • 56MHz, CeCPoP. • Prep for High Energy Run. • RF Conditioning. • AC Dipole for Blue. • Vacuum, Instrumentation and Power Supply repair and maintenance.
AGS • Repair, Maintenance and inspection. • C15 polarimeter work. • Vacuum leak check. • D15 welding. • Westinghouse maintenance. • Siemens work?
Access Schedule • RHIC Experimental Access: • 0800-1700hrs. • RHIC ring Access: • 0830-1600hrs. • IR 4 Access 0830-1230hrs. • RF conditioning 1230-1700hrs.