1 / 5

MicroBooNE Working Group Meeting

MicroBooNE Working Group Meeting. April 26, 2011 1 :00 – 2:00 PM Black Hole (WH2NW). Agenda. WBS 1.4 – TPC System Progress Report [Bonnie Fleming] WBS 1.5 – Readout & DAQ Progress Report [ Hucheng Chen] WBS 1.8 – PMT System Progress Report [ Arati Prakash ]

kermit
Download Presentation

MicroBooNE Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MicroBooNE Working Group Meeting April 26, 2011 1:00– 2:00 PM Black Hole (WH2NW)

  2. Agenda • WBS 1.4 – TPC System Progress Report [Bonnie Fleming] • WBS 1.5 – Readout & DAQ Progress Report [Hucheng Chen] • WBS 1.8 – PMT System Progress Report [AratiPrakash] • Project Report [Gina Rameika] • Overall Project Status • Organization Changes • Progress on Review Recommendations • Next Meeting • Action Items 26-Apr-2011 MicroBooNE WGM

  3. Next WGMs • 10-May – Post Review Actions and WBS 1.2 - Cryogenics Systems Progress Report [Jim Kilmer] WBS 1.3 – Cryostat System Progress Report [Craig Thorn] WBS 1.6 – Experiment Infrastructure Progress Report [Dixon Bogert] WBS 1.7 – System Installation Progress Report [John Voirin] • 24-May– Post Review Follow-up and WBS 1.4 – TPC System Progress Report [Bonnie Fleming] WBS 1.5 – Readout & DAQ Progress Report [Hucheng Chen] WBS 1.8 – PMT System Progress Report [AratiPrakash] 26-Apr-2011 MicroBooNE WGM

  4. Action Items Open Items from Last WGM: • Gina – Meet with Byron Clark (Procurement Liaison) to get him up to speed on the project’s procurement needs. • Gina – at future WGM start PMG type statusing (including $) Open Items from Prior Meetings: • Cat- Generate and distribute narrative month project report. • Greg/Mike L. – address engineering needs for WBS 1.2 26-Apr-2011 MicroBooNE WGM

  5. PMG Agenda Items • Overall Project Summary Status Report (Project Manager) • Fiscal Matters (Project Manager) • Money • EVMS • Risk Management (Risk Manager/Project Manager). • Procurements (Project Manager) • Labor Resources (Project Manger) • Change Requests (Project Manager) • Progress / Status / Issues for Highlighted Subprojects (1 or 2 per meeting) • Summarize Action Items from Meeting (Project Manager / PMG Chair) 26-Apr-2011 MicroBooNE WGM

More Related