50 likes | 190 Views
MicroBooNE Working Group Meeting. June 14, 2011 1 :00 – 2:00 PM Black Hole (WH2NW). Agenda. Project Status Report [Gina Rameika ] Cryogenics Systems Progress Report [Jim Kilmer] Site and Building Progress Report [Dixon Bogert ]
E N D
MicroBooNE Working Group Meeting June 14, 2011 1:00– 2:00 PM Black Hole (WH2NW)
Agenda • Project Status Report [Gina Rameika] • Cryogenics Systems Progress Report [Jim Kilmer] • Site and Building Progress Report [Dixon Bogert] • DAQ, Slow Control and Monitoring Progress Report [Erick Church] • Installation Progress Report [John Voirin] • Quality Integration into Projects [Tom King] • Director’s Review Preparations [Dean Hoffer] • Next Meeting/Action Items 14-Jun-2011 MicroBooNE WGM
Director’s Review Preps • Review is a CD-2/3a that includes a independent design review, cost, schedule, management (including ES&H), and monthly progressing/ analysis/ reporting cycle. • Looking at a 2.5 day review that is now reflected in the second draft of agenda • Been working with project on potential review team members. Availability will drive review date of either July 6-8 or 12-14. • DOE CD-2/3a Review scheduled for Aug 9-11. 14-Jun-2011 MicroBooNE WGM
Next WGMs 28-Jun • Project Status Report [Gina Rameika] • Cryostat Progress report [Sue Duffin] • Readout and FEE Progress Report [Hucheng Chen] • TPC Progress Report [Roxanne Guenette] • PMT System Progress Report [AratiPrakash] • Detector Design and Construction Integration [Jen Raff] • Director’s Review Preparations [Dean Hoffer] 12-July • Project Status Report [Gina Rameika] • Cryogenics Systems Progress Report [Jim Kilmer] • Site and Building Progress Report [Dixon Bogert] • DAQ, Slow Control and Monitoring Progress Report [Erick Church] • Installation Progress Report [John Voirin] • DOE Review Preparations [Dean Hoffer] 14-Jun-2011 MicroBooNE WGM
Action Items Open Items from Last WGM: • Dean – Get WGM distribution list to Gina for distribution of the project monthly reports. • Ted Lavine, Greg Bock, and Paul Philp to review and comment to Gina on the proposed L1 and L2 millstones presented during the WGM. Open Items from Prior Meetings: None 14-Jun-2011 MicroBooNE WGM