One Transport v4 Migration Update

One Transport v4 Migration Update. Lee Coomer Product Manager. Agenda. Scope Transport business process flow Benefits Screen design Timescales User engagement calendar. Scope. Vision Statements: Deliver an application that supports the core business processes of a Transport Team

kiley
Download Presentation

One Transport v4 Migration Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. One Transport v4 Migration Update Lee Coomer Product Manager

  2. Agenda • Scope • Transport business process flow • Benefits • Screen design • Timescales • User engagement calendar

  3. Scope • Vision Statements: • Deliver an application that supports the core business processes of a Transport Team • Deliver a migration which builds on the current version with the introduction of new concepts • Delivers an application which is easy to use and remains consistent with Admissions v4

  4. Main Scope Areas: • Mainstream, SEN and Adults • Applications • Assessments • Planning • Routes and Journeys • Contracts • Finance

  5. Process Flow Assessments Journeys Approval Finance Applications Planning Single child working Multi childworking Contractor

  6. Benefits of Transport Version 4 • Brings together the core processes of a Transport team into One • Improved planning functionality • Application process • Flexible process driven solution • Enhanced Adult and SEN functionality • Takes advantage of GIS V4 • Consistent with other recent V4 products • Improved user experience • Designed to run on existing customer infrastructure

  7. Screen Design

  8. Timescales Jan 13 – Sept 13 Aug 13 – Aug 14 Aug 14 – Nov 14 Nov 14 Defining Scope Development Testing Full Released

  9. User Engagement • SCG at major milestone point • Nov 2013 • Jan 2014 • May 2014 • Regular WebEx meetings to provide updates • User experience sessions – Summer 2014 • User Acceptance Testing – From September 2014 • Online • Hands on

  10. Preparing Transport Teams • Full Release Autumn 2014 • When to migrate? • Pilot sites? • When in the Transport process? • Migration package • Details to be confirmed • Reports • New entities may require reports to be re-written • Proposed support for SSRS

  11. Questions? Lee Coomer Product Manager Mobile: 07711 014650 Email: lee.coomer@capita.co.uk