This report details the progress in constructing conventional facilities, with efforts to minimize the impact of Continuing Resolution. Key methodologies include reviewing work breakdown structure, adjusting cost assumptions, and managing risks. Critical milestones and risk management strategies are also outlined.

krystalm
Download Presentation

Conventional Facilities

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conventional Facilities CONSTRUCTION PROGRESS AND ESTIMATE TO COMPLETE METHODOLOGY

  2. Conventional Facilities • Project Office efforts to minimize impact of Continuing Resolution on Conventional Facilities • Continued full funding of construction contracts • Increased staff to support construction schedule • Maintained construction schedule for Early and Beneficial Occupancy of conventional facilities

  3. Conventional Facilities • Impacts of Continuing Resolution • Scope • Build-out of Far Experimental Hall hutches shifted to later years • Build-out of existing Lab Office space shifted to later years • Staff • CF Support for build-out and Technical Systems installation shifted to later years

  4. ETC Methodology • Reviewed Work Breakdown Structure • Re-evaluated Resource Loaded Schedule • Adjust Key Cost and Schedule Assumptions • Validate Funding Profile • Review Critical Path • Update Risk Management • Develop Cost-to-go (Estimate to Complete)

  5. Contingency Analysis • Work Remaining (from July 07 ETC) = $73M • Total estimated contingency = $6.5M (9%) • Estimated contingency for FY08 only = $3.7M

  6. BTH – NEH Co-Avail (20DEC07) XRT- FEH Co-Avail (21MAR08) Critical Milestones Beneficial Occupancy Dates support CD-4 (July 2010)

  7. Critical Path • Reasonably defined thru CD4 • CF Milestones support overall project Level 1 and Level 2 Milestones • Critical Path through Central Utility Plant for start-up at NEH • Critical Path through Far Experimental Hall for CD-4 • Reflects an integrated schedule • The integrated schedule includes Co-Avail and Beneficial Occupancy dates for starting technical system installation • Are durations reasonable • CF Baseline Schedule includes durations by the Trade contractors and approved by LCLS • Consistent with Funding profile, start-up test plan, acquisition strategy, available resources • Project strategy to complete conventional construction forces the funding profile to be consistent with construction demand • Assess float • All critical activities are zero float (latest schedule recovery plan)

  8. CF Completed Level 3 Milestones

  9. Schedule – Level 3 Milestones

  10. Risk Management • Protect in-place Utilities • $100K (Mitigate) • Protection for unknown existing utilities • Contractor Claim • $2.4M (Mitigate) • In negotiations – appears likely to settle for less than claimed amount • Affholder default due to liquidation • $250K (Accept) • Performance Bond used to complete work • Far Experimental Hall Hutches • $1.0M (Mitigate) • Design of hutches proceeds during FY09 • Construction Stand-down • $2.75M (Mitigate) • Laboratory-wide stand down due to safety

  11. Conventional Facilities • Summary • Minimal Impacts from Continuing Resolution • Delayed build-out of Far Experimental Hall • Increased Project Staff costs • Overall Estimate to Complete increase = $3.9M • Early and Beneficial Occupancy preserved. Outlook for meeting CD-4 is good. • Risks going forward are minimal