1 / 20

D0 Trigger Status

D0 Trigger Status. 7 MHz input rate Data. Brief discussion of each project Great progress all systems Significant delays Manpower Shortages Technical Difficulties Delivery. Framework. Data Log. L1 4.2 m s. L2 100 m s. L3 48+ ms. 50 Hz. 7 kHz.

leanna
Download Presentation

D0 Trigger Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. D0 Trigger Status 7 MHz input rate Data • Brief discussion of each project • Great progress all systems • Significant delays • Manpower Shortages • Technical Difficulties • Delivery Framework Data Log L1 4.2 ms L2 100ms L3 48+ms 50 Hz 7 kHz 1000 Hz 48 nodes 128 terms 128 terms

  2. Framework Status • Components(MSU) • Operational • Commissioning/Schedule • Support detector commissioning • Complete readout to L3 by 1/11 • Integrating with L2 • L2 trigger mask and pseudo-terms deferred? • Firmware • Need to complete pseudo-terms • Commission run-control • Personnel • Loss of senior engineer, Steve Gross • Loss of engineer, Kirsten Moore • Replacement uncertain Good progress, on time

  3. L1CAL Detector/L1/L2 Components L1 LUM LUM L2Cal CAL L1 FPS FPS L2PS CFT/ CPS Global L2 L1 CTP L2CFT L2STT SMT L2 Muon L1 Muon Muon L2FW:Combined objects (e, m, j) L1FPD FPD L1FW: towers, tracks, correlations

  4. Luminosity Monitor Status • Components(Brown) • Scintillator(48) Complete • Electronics • CAFÉ boards(175) on hand • Completing ADC(~12) board layout, ordering parts • Vertex board, FPGA 75% complete, layout commencing. • Procuring signal cables(~60) soon • Crate/PS on hand • Commissioning/Schedule • Installed Scintillator 4/00 • Cabling awaits FPS. • February 1, Electronics Installed • March 1, Luminosity Monitoring • March-April, and/or terms. • Software • Working on embedded software • Download currently underway. • Database under development Good progress, on time

  5. CTT Organization showing links to the L1 TM, L2 PreProcessors and L3 AFE MIX DB/DBTC COL BC TM L3 OCT 1 CFT L1CFT Ax. /CPS Ax. L3 75 L3 OCT 2 L3 OCT 3 L2CFT · Q 1 L3 L2PS OCT 4 L2CFT · Q 2 L3 L2PS OCT 5 L2CFT Q 3 · 40 L3 L2PS OCT 6 L2CFT · Q 4 L3 · L2PS OCT 7 CPS · L3 Ax. · m OCT 8 L1 TM 5 OLR 1 L2STT SEXT 1 L3 OLR 2 L2STT SEXT 2 L3 OLR 3 L2STT SEXT 3 L3 OLR 4 L2STT SEXT 4 L3 OLR 5 L2STT SEXT 5 L3 CFT OLR 6 Stereo. L2STT SEXT 6 75 L3 L2PS N U L3 5 L2PS N V L3 CPS L2PS Stereo S U L3 10 L2PS S V L3 L2FPS N U L3 L2FPS N V L3 FPS L1FPS 16 L3 L2FPS 32 S U L3 L2FPS S V L3 LEGEND Analog Boards FSC LINK LVDS LINK the inset shows CFT LVDS LINK the number of G LINK Stereo. each type 3 TRANSITION CARDS DAUGHTER CARDS Each color Each filling corresponds to a corresponds to a Created by Manuel I. Martin different flavor different flavor May. 6, 99 L1CTP/FPS/FPD

  6. L1 CTP/FPS/FPD Status • Components • Analog(Fermilab-D0) • AFE-8MCM (CFTax): At vendor, full order complete 1/18/00 • AFE-12MCM (FPS): • motherboard prototype this month • daughter prototype board order 1/01 • Crates/Cables on hand • Power supplies delayed until new year (partial). • Mixer(Fermilab-CD) • Super-sector (1/5th) 11/15 • Full Mixer 1/01 • Digital(Fermilab-D0) • Motherboard here • Transition module 1/11 • CTP daughter boards 11/15 • FPS daughter board order out, parts on order • Crates/Cables/PS here • Firmware • AFE & Mixer complete • DFE 50% • Collector/Broadcaster 50% • No diagnostics

  7. L1 CTP/FPS/FPD Status • Commissioning/Schedule • Assembling test stands for digital/VHDL • Installing cables/crates on platform • Crates/Cables installed in MCH. • Analog • 10 AFE8 installed, operating 12/00 • Balance at FNAL by 1/18/01 • AFE12 unknown (in prototype) • Supplies as arrive • Digital • Sufficient hardware for commissioning • Balance Installed by 12/00 • Personnel • Recently lost Kin Yip (FNAL postdoc) & Juan Lizarazo (FNAL Co-op) both on VHDL • A position has been available but not yet filled & a new student arrived. • Reduced engineering (John Anderson) has delayed AFE12. • Have redirected Jamieson Olsen to assist with VHDL, Fermilab arranging technical help to assist reorganization and installation. Good progress on all fronts AFE12, VHDL concerns

  8. L1 CAL Status • Components • Analog pick-offs (320) to accommodate changed BW prototyped. 1FTE month to production • Quadrant hardware (40) circuit/firmware designed • L2/L3 Readout complete • Commissioning/Schedule • Inactive until framework complete 11/00. Within a month progress should resume • Start w/ analog pick-offs • L2 & L3 readout 11/00 • Firmware • All exists, not all tested • Personnel • Same as framework Late but well before 3/01

  9. L1 MUON Status • Components • L1MuTrigger (4 crates) Prod Beginning(UAz) • Motherboard: starting production/fabrication • Scintillator daughter board: preproduction in assembly • Wire daughter board: production board in design • Crate Manager: testing production card, balance to be assembled • Trigger Manager daughter-board: starting prod/fab now • Serial Link Transmitters complete • Serial Link Receivers production testing • MCEN (5 crates) in Preprod Testing(BU) • MCEN: preproduction testing underway • Centroid Daughter Board: preprod, testing underway • Crate manager: preprod layout. • Crates/Backplanes complete • Power Supplies on order.

  10. L1 Muon Status • Software • Download Infrastructure in place • Preproduction versions of all firmware exist. • No alarms, monitoring • Personnel • Arizona down to zero from two postdocs. Advertising for one replacement • Boston post doc hired, visa difficulties • Discussing Ken Johns buy-out. • Need help w/ assembly/test of PSupplies • Commissioning/Schedule • One trigger, one manager crate in operation and readout. • Next providing L1CTPT Manager Crate. • Two Octants triggering by 11/00 • L1 Muon full crate assembled 1/01 • MCEN full crate assembled 3/01 L1Muon before 3/01 Some concern MCEN, manpower

  11. L2 Component Status • Alpha serial processors (MSU,UM,UIC): • Production Status • 3 preproduction worked “out-of-the-box” • ADCO, same vendor that produced CDF TDCs • About 25 stuffed or nearly stuffed • Parts for another 15 in reserve • Many key components obsolete • Diagnostics @ UM • Four boards • To our knowledge none work • Diagnostics @ UIC • 10 boards • 2 incorrectly mounted components 8 have partial functionality • Rapid learning curve • Considering a range of options • Repair sufficient boards for March 1, 2001 • Build new boards with larger vias and reserve parts • Build new boards with larger vias. Recover components and build full complement. • Re-layout board and/or find new vendor • Complete redesign • Hope to decide before November 1, leaning towards full press: repair, new boards, and redesign • Complicating commissioning.

  12. L2 Components Cont. • MBT I/O Cards(U-Maryland): • 6 production cards received. 3 pass specs. 3 under test now • Firmware functionality 90% done. • Remaining 25 boards built, parts on hand • Balance by December. • FIC L1/L2 Interface(SACLAY): • Boards complete • Final firmware adjustments October 16-20. • SLIC Parallel Proc.(NIU,Columbia): • Boards complete • First results from DSP Central algorithm meet speed/efficiency requirements • CIC, SFO Muon/L2 Interface (U-Neb): • Prototypes pass battery of tests but not up to standard design practices (two layers, unconventional shielding planes, unequal traces on differential signals...) • Have solicited advice from Fermilab engineers but process delayed by illness. Restarting now. • Delivery December?

  13. L2 Status Cont. • Software • C++ Framework exists • Preprocessor algorithms well developed, global needs attention. • Commissioning/Testing: • MCH and test stand racks and crates 85% done. Cabling 65% done • Commissioning sequence under discussion. • Essentially on hold until alpha, CIC, SFO issues resolved. • Once alpha’s MBTs are on hand the L2CAL, L2CTT, L2PS can be assembled <1 month. • Personnel • Recently lost one key postdoc from UIC and one from Maryland, will lose another UIC postdoc at the end of the year • One UIC postdoc has been replaced and new ones added from MSU and Columbia • Lack of on-site coordinator has slowed progress. Discussing Nikos Varelas buy-out. • Lack of project engineer has slowed progress. However, Rich Kwarciany (CD Electronics System Engineer) has been a great help as an on-call consultant. Fermilab looking into this. MBT, SLIC, FIC ready before 3/01 Alpha, CIC/SFO, manpower concerns

  14. STT • Motherboard & communication daughter board • First prototypes in hand or being built • November • Fiber Road & Track Fit daughter boards • Parts in hand • prototypes coming (Feb/ Dec) • VHDL and simulation in progress • STC(hit filter, cluster finder) • VHDL design/coding in progress • Not easy to fit into real estate • May change Altera to Xilinx? • Or fancier Altera? • VME CPU: purchase in progress • Schedule • Schedule in mid-update • Attempt integration in Feb 2001 with first prototypes, not 2nd • Scheduled Complete Feb 2002

  15. Digitizing Crates (2 of 16 groups) Data pathway o o o Receiver Collector (1 of 8) o o o VBDs Fiber Path (8 total) Event Tag Generator Levels 1,2 Trigger data o o o o o o Event tag path o o o o o o Segment Bridge Processor Nodes (4 groups of 16) DAQ/L3 • Evolved to a single multipurpose card used in VRC, SB, processor nodes (~100) • VHDL code specific to VRC, SB, Node complete • ETG is one of a kind.

  16. L3/DAQ Status • Components(Brown) • Layout done for 6 wks, parts procurement difficult. • 25 board order placed with vendor • Layout @ board houses. Bids received. Production complete < 2 weeks. • Procuring parts now w/ Fermilab assistance • 5 days to stuff & check • Software(Brown,Washington) • Framework up and running • Nodes also operational • Commissioning/Installation • Maintaining emulators for commissioning, no schedule delay for other systems. • Cable plant is minimal - reuses infrastructure, MCH 50% done, remainder under discussion. • Schedule (full chain by Jan 1) • After receipt of board 1-2 week at Brown, then install 4 VRCs @ DAB • 2 wks install 1 SB, fiber between VRC-SB • 2 wks install multiple node adapters, fiber between SB-node. • ETG January Software in good shape Watching delivery closely

  17. Filtering/Database • Components(Various Institutions) • Operational version of ScriptRunner • Unpacking code for cal, smt and muon • electron, muon, jet, missing et, and tau tools • Database and interface in design. • Installation/Commissioning • Participating in online tests of PDTs, CFT. • Participating in 10% SiDet Test • Milestone: readout/filtering muon system! • Personnel • Impending departure of Charles Leggett (LBL) infra-structure (unpack,tool template,offline verification) • Carmem Silva (LAFEX) database, currently only 1FTE on database • Insufficient support for NT release & porting. • Too few tool authors! • Schedule • 11/00 standard running including ScriptRunner in Mark & Pass mode • 1/01 monitor displays available • 3/01 operational versions of all physics tools ported and available Filtering operable, needs personpower

  18. Reportable Milestones Priorities: (1) FWK, L1mu, L1CAL, L3 (2) L2Global, L2CAL (3) L1&L2 CTPT, FPS

  19. Personnel Increases? • To free engineers for VHDL preparation a senior technician to assist CTPT construction. Could also help with L1Muon, L2 installation. Fermilab investigating. • An engineer to assist L2 debugging & integration. This could be considered an escalation of the already valuable on-call arrangement. Fermilab investigating • Trying to arrange full-time contributions from • Ken Johns L1Muon • Nikos Varelas L2 • Looking fortwo programmers for • L3 infrastructure/release (Fermilab/LBL?) • Database (Collaboration?) • Other needs: • Examines • L2 tools & verification • L3 tools & verification!

  20. Closing Comments • Trigger making excellent progress in all areas. (Didn’t mention TrigSim but will be a release Nov 1.) • Responding to delays by adding people to construction and commissioning efforts. • Will make L2alpha decision soon & trying to accelerate L3 component delivery. • First priority FMWK, L1CAL, L1Muon, L3. Then will add systems as components come available. • Now’s the time to help: tools, filtering, database, commissioning.

More Related