1 / 11

D0 Trigger Status

D0 Trigger Status. 7 MHz input rate Data. Framework. Data Log. L1 4.2 m s. L2 100 m s. L3 48+ ms. 50 Hz. 5-10 kHz. 1000 Hz. 48 nodes. 256 terms 128 bits. 128 bits. L1 Luminosity monitor Digital Tracking CAL Muon L3/DAQ. Luminosity Monitor.

liseli
Download Presentation

D0 Trigger Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. D0 Trigger Status 7 MHz input rate Data Framework Data Log L1 4.2 ms L2 100ms L3 48+ms 50 Hz 5-10 kHz 1000 Hz 48 nodes 256 terms 128 bits 128 bits • L1 • Luminosity monitor • Digital Tracking • CAL • Muon • L3/DAQ

  2. Luminosity Monitor • Detector/readout installed • Timed-in • Providing minbias triggers using Run I electronics. • Final Electronics • TDC in production • Vertex boards 1-Jun • Expect multiple interaction triggers, luminosity database to be completed by the end of the year, delayed because lead-postdoc departed.

  3. CTT Organization showing links to the L1 TM, L2 PreProcessors and L3 AFE MIX DB/DBTC COL BC TM L3 OCT 1 CFT L1CFT Ax. /CPS Ax. L3 75 L3 OCT 2 L3 OCT 3 L2CFT · Q 1 L3 L2PS OCT 4 L2CFT · Q 2 L3 L2PS OCT 5 L2CFT Q 3 · 40 L3 L2PS OCT 6 L2CFT · Q 4 L3 · L2PS OCT 7 CPS · L3 Ax. · m OCT 8 L1 TM 5 OLR 1 L2STT SEXT 1 L3 OLR 2 L2STT SEXT 2 L3 OLR 3 L2STT SEXT 3 L3 OLR 4 L2STT SEXT 4 L3 OLR 5 L2STT SEXT 5 L3 CFT OLR 6 Stereo. L2STT SEXT 6 75 L3 L2PS N U L3 5 L2PS N V L3 CPS L2PS Stereo S U L3 10 L2PS S V L3 L2FPS N U L3 L2FPS N V L3 FPS L1FPS 16 L3 L2FPS 32 S U L3 L2FPS S V L3 LEGEND Analog Boards FSC LINK LVDS LINK the inset shows CFT LVDS LINK the number of G LINK Stereo. each type 3 TRANSITION CARDS DAUGHTER CARDS Each color Each filling corresponds to a corresponds to a Created by Manuel I. Martin different flavor different flavor May. 6, 99 L1CTP/FPS/FPD

  4. L1 CTP/FPS/FPD Digital Status • Mixer(Fermilab-CD) • Effort is delayed, shorthanded, discussing options with CD/D0-Electronics group. • 30-May: A half super-sector (2 of 20 boards.) • 25-July: Full system (estimate <1 week access) • Broadcasters/Collectors(Fermi-D0) • 65% of hardware, 70% of firmware. • 100% crates/PS/Cables • Currently installing single cards to test software & download • May shutdown, hit occupancy trigger • 11-June complete hardware installation (estimate 2-4 wks access) • 1-Aug full system integration • Difficult keeping the schedule, short a tech and programmer to help lead engineer.

  5. L1 CAL Component Status • Components • All in or nearing production expect full complement mid-June • Summers/Drivers at vendor • Receivers at Si-Det • Currently • CC populated • Timed in • Single cal tower trigger in days • Next • Readout to L2 & L3 • Quadrant capability • Completion of system • 1-2 weeks access • Reliable clock system. Has been difficult and some concern expert (Xiaonan Li) will be leaving soon.

  6. L1 MUON Status • Components • all in production, should be available for accesses. • Full set trigger system by July 1 • Centroid finders Aug 1. • Currently • A few central octants • Triggering on beam • After two week shutdown • Full central region • 1 octant in each end region • Completion of system will require • Additional 2 weeks installation access • Additional 2 weeks commissioning access

  7. Digitizing Crates (2 of 16 groups) Data pathway o o o Receiver Collector (1 of 8) o o o VBDs Fiber Path (8 total) Event Tag Generator Levels 1,2 Trigger data o o o o o o Event tag path o o o o o o Segment Bridge Processor Nodes (4 groups of 16) DAQ/L3 Originally a single multipurpose card (~300) used in most components with firmware specific to application.

  8. Moving Counting House Fixed Counting House V B D i SIB3 FCI fiber copper DCI L3I VRC (PC) copper VBDs ETI L3 filter node PCs L1 SB (PCs) V B D i’ Multiple 100 MB/s INOVA links SIB3 fiber copper ETG (PC) L3 Design In January abandoned this approach in favor of more, less complicated individual components. • VRC = VBDI + SIB3 • SB = 12 SIB2 • Node = Motherboard + 4 SIB2 • ETG = VBDI’ + SIB3

  9. L3 Status/Schedule • Currently VRC, SB, ETG emulated w/ capability of several Hz. • Assembling an intermediate 100-200 Hz system to support commissioning. Expected mid-May • Basically VRC emulation replaced w/ hardware VBDI and SIB1. • SIB1 exists and integrated • VBDI in assembly • Design work on VBDI’, SIB2 and SIB3 proceeding. • SIB2 June 1 • SIB3 July 1 • Full 1 kHz 1-Aug

  10. L3/DAQ Management • Since January have had weekly L3 Review or oversight meetings. Successful in promoting recent progress. • Today first meeting of L3 Planning Group charged with • developing a schedule for completion of hardware and software by Sept 1 • suggesting alternatives • identifying resources. • Major issues • Hardware delivery • Supportability of NT filtering. • Possibilities include • Present course • Separate DAQ & filtering farms • Hope for recommendation in one month and may request resources at that time.

  11. Summary • L1 Luminosity • Operational • >June • Completion depends on identifying manpower • Little or no access. • L1 Tracking • First steps • August • need technical assistance • 4+ weeks access. • L1 Calorimeter • CC operational • June • Help with Clock • <2 weeks access. • L1 Muon • Central operational • July • 4 week access. • L3 • Supporting Commissioning • September • Evaluating Options • No access

More Related