Harmonisation Working Group HWG Meeting Monday, 12th December, 2011 NIAUR Offices Belfast
Minutes Minutes from HWG meeting – 2nd November 2011
ROI HSP Update Harmonisation and Service Pack Project
ROI Project Scope • Changes based on Approved Market Design Baseline (HBL). • Delivery of SAP service packs. • Implementation of Tibco Market Interface to replace existing SeeBeyond MPCC.
Current Project Status • ESBN Project Team mobilised. • ESB Design and build phases initiated • The working assumption of the Single instance of Tibco has been confirmed by SEM Committee subject to final CER approval • Project and Market Assurance approach being developed by Gemserv. • Specific ROI project deliverables will be handled through IGG forum
Market Design Update Today’s Workload Overview
DR1105 V1 - Change to MPD36 - Change of Grouped MPRN_No CoS • Change Request • The unmetered market has grown significantly since Market Opening in 2005 • RMDS-driven process review project has assessed the processes in terms of bottlenecks, weaknesses and areas for improvement • This second DR has been created to facilitate changes to MPD 36 - where there is no CoS • Previous DR from last HWG – DR1084 with CoS • At today’s Meeting • Classification as ROI-specific
DR1110 V1 - Updates to ES NI Market Message Implementation Guides and Retail Market Procedures • Change Request • Update the Enduring Solution NI Market Message Implementation Guides v2.1 and NI Retail Market Procedures v1.0 with all approved and pending changes up to and including DRs at today’s meeting • At today’s Meeting • Classification as NI-specific
DR1106 V1 – Update to NIE Revenue Protection Process • Change Request • Process Change • Where a RP Inspection Visit detects an unauthorised re-energisation of a domestic premise the RPU will replace the credit meter with a prepayment meter, preloaded with a small amount of credit and disabled from vending on the PRI system. • The RPU team will then email the registered Supplier for that premise to notify them that they must submit 017 & 030 market messages to request the re-energisation and (retrospective) replacement of the credit meter with a prepayment meter. • The email will contain an appointment ID for use on the 017(E01) & 030(K05) market messages. • RPU will complete the 017 & 030 orders and the 332 market message will be sent to the Supplier as confirmation of the meter exchange. • The 131[C1] market message that is sent on completion of the RP Inspection Visit will have • - Work Type Code = W402 - RP Inspection Visit • - Outcome Reason Code = C008 - Revenue Protection Issue • This requires the Code Value ‘W402’ on Data Item ‘Work Type Code’ to be changed to ‘Valid in NI’ in the HBL Data Code. • At today’s Meeting • Approval as DR and as MCR
DR1107 V1 - New 'Connection Card Required' code on 102P • Change Request • Introduction of a new ‘Provisional Acceptance Completion Requirement Code’ code of “CCR – Connection Card Required” for the 102P market message to notify the Supplier that a Connection Card is required before the meter works requested on the 010 (CoS) can be completed. • This 102P will return this code when • - an 010 (CoS) is submitted with Meter Works included, and • - the Meter Works involve a change to an MCC which includes heating, and • - the premise does not currently have an MCC which includes heat. • NIE need to know the additional Heating Load that is required at the premise and the Connection Card will provide this information. • The CoS meter works will not proceed until NIE have received a valid Connection Card from the Customer. • At today’s Meeting • Approval as DR and as MCR
DR1108 V1 - Update to description and usage of Delay Reason Code ‘DE01’ on 130D • Change Request • Request proposes three changes • That the description for Delay Reason code ‘DE01’ is changed from “Completion Certificate Required” to “Completion Certificate/Connection Card Required” • That ‘DE01’ will be used in NI • That ‘DE01’ will be sent on the 130D to notify Suppliers that a requested change of MCC will be delayed because a new Connection Card will be required from the customer before the work can be completed. • This situation will arise where an MCC which includes heating is being requested and the premise does not currently have an MCC which includes heat. • NIE need to know the additional Heating Load that is required at the premise and the Connection Card will provide this information.. • At today’s Meeting • Approval as DR and as MCR
DR1109 V1 - Sundry changes for Harmonised Baseline V2.2 • Change Request • Market Message Changes: Removal of the following Market Message definitions from the HBL and Harmonised Schema: 1. 501 Estimate Aggregated Supplier Non Interval Consumption 2. 504 Embedded Generation DNGG 3. 505 Aggregated Supplier Interval Consumption • Data Codes Changes: • Removal of the following Code definitions from the HBL and Harmonised Schema: • Request Status Codes as follows: C (Completed), D (Delayed), N (Not Completed) and X (Cancelled) • Reject Reason Codes as follows: SBI (New Domestic Registration), SSA (A message has not been received from SSA advising Generation Unit ID and Generator Unit MPID in advance of the registration from Supplier) • Data Definition Changes: • Estimated Usage Factor : description to be changed from "See Message Specific Information" to "Estimated Usage Factor is a statement in kWh of the • estimated consumption for a given Timeslot at a Meter Point over the next year“ • Data Item Usage / Schema Changes: • PSOExemptionFlag: this data item has changed from Required to Optional as it is not used in NI. This requires a schema change for the two Market Messages on which this data items appears: 700 and 700W. • At today’s Meeting • Approval as DR and as MCR
DR1079 V4 – Harmonised Base Line V2.2 (draft) • Change Request content • Core elements of the draft HBL V2.2 reflecting all changes since V2.1 • Change history (list of all approved and pending changes since HBL V2.1, including corrections) • Draft HBL V2.2 assumes approval of all requested approvals at HWG (today) and by HSG • (Jurisdiction-specific elements of HBL are published separately – See MCR1002 V4.0 for ROI elements at IGG today) • At today’s Meeting • Approval
Next Steps • Next HWG meeting 11th January, 2012 (Dublin) • Dates for all meetings for 2012 are on the Calendar on the RMDS website
HWG Meeting • AOB
HWG Meeting Thank You