Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 348 November 27, 2012. Jeff Florin Deputy Executive Director, Operations Virginia Port Authority. Agenda. NIT Gate Improvements NIT CBP Interchange NIT Customer Service Area Improvements
E N D
Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 348 November 27, 2012 Jeff Florin Deputy Executive Director, Operations Virginia Port Authority
Agenda • NIT Gate Improvements • NIT CBP Interchange • NIT Customer Service Area Improvements • NIT Shuttle Road Repair • Commonwealth Railway Road Crossing Restoration • Craney Island Cross Dikes Stage 2A • Paradise Creek Mitigation
NIT Gate Improvements • Security, interchange, and transfer zone automation, personnel shifted to remote facility • Automation, appointment system and remote processing • Improves cargo velocity, safety & efficiency • Estimated combined project cost: $10 M • Includes $4.1 M software
NIT Gate Improvements Project 3 OCR Portals Project 2 Chassis Service/Customer Service Areas Project 1 Interchange & CBP Improvements Project 3 OCR Portals Completed Transfer Zone
NIT CBP Interchange Improvements • Project clear of all utility conflicts; continuing roadway north of the truck canopy and starting RPM foundations • Estimated project cost : $2.2 M • Contractor: EV Williams • Project is currently 50% complete • Project completion by March 30, 2012
NIT Customer Service Area Improvements • Area clearing in process to begin customer service area renovations • Estimated project cost : $1.25 M • Contractor: Ridley Construction Group • Project is currently 75% complete • Project completion by February 9, 2013
NIT Customer Service Area Improvements Customer Service canopy
NIT Shuttle Road Repairs Pier 2 waterside rail crossing Shuttle road progress
Commonwealth RailwayRoad Crossing Restoration Removing road and rail at Taylor Rd crossing Former crossing at Peppercorn Drive
Craney Island Cross Dikes Stage 2A • USACE will begin Stage 2A December 17th • Placing foundation lifts of sand • Land will be visible this time next year • Contractor: Manson Construction Company • Project cost: $26.8 M in federal appropriations • No new VPA money will be appropriated • Low bid came in at $21.5 M • Project completion by April 2013
Craney Island Cross Dikes Stage 2A CIDMMA South Cross Dike +10 ft Division Cross Dike +10 ft
Paradise Creek Mitigation • Earthwork with beneficial reuse of excavated materials; planted 11 acres of tidal wetlands • Minor reseeding anticipated next year along with ongoing phragmitescontrol • Contractor: C.T. Purcell, Inc. • Estimated project cost: $4.6 M • Project is complete
Paradise Creek Mitigation Approximate limits of excavation and wetlands creation Wetlands Wetlands channel Paradise Creek
Paradise Creek Mitigation Wetlands planting