Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 351 May 28, 2013. Jeff Florin Deputy Executive Director, Operations Virginia Port Authority. Agenda. NIT Gate Improvements NIT Outbound Corridor NIT OCR Portals NIT Truck Canopy
E N D
Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 351 May 28, 2013 Jeff Florin Deputy Executive Director, Operations Virginia Port Authority
Agenda • NIT Gate Improvements • NIT Outbound Corridor • NIT OCR Portals • NIT Truck Canopy • PMT Rail Upgrades • APMT Trench Drain Repairs • APMT Reefer Plugs • Craney Island Eastward Expansion
NIT Gate Improvements • Security, interchange, and transfer zone automation, personnel shifted to remote facility • Automation, appointment system and remote processing • Improves cargo velocity, safety & efficiency • Estimated combined project cost: $10 M • Includes $4.1 M software
NIT Gate Improvements Project 2 OCR Portals Project 3 Truck Canopy Completed Chassis Service/Customer Service Areas Project 1 Outbound Corridor Project 2 OCR Portals Completed Transfer Zone
NIT Outbound Corridor • Surface asphalt complete • OCR Portal construction underway • Estimated project cost : $2.2 M • Contractor: EV Williams • Project is currently 75% complete • Project completion by September 2013
NIT Truck Canopy • Infrastructure for gate automation • Estimated project cost : $300,000 • Bids received May 21st • Project completion by October 2013
PMT Rail Upgrades • Replacement and upgrade to Class I railroad standards of the East and West rail leads into PMT • On hold pending tunnel contractor work • Estimated project cost : $900,000 • Contractor: H&B Railroad • Project completion by October 2013
PMT Rail Upgrades East rail lead West rail lead
APMT Projects Reefer plug installation Trench drain repairs
APMT Trench Drain Repairs • Localized repairs of APMT storm drains • Demolition complete; vault repairs in progress • Estimated project cost : $150,000 • Contractor: Eastern Waterproofing & Restoration of VA Co, LLC • Project is 25% complete • Project completion TBD
APMT Reefer Plugs • Installation of 60 reefer plugs • Discussions with APM ongoing • Estimated project cost : $1.3 million • Bids due June 18th
Craney Island Cross Dikes Stage 2A • Stage 2A is complete • Placed1.54 MCY of sand on south and division cross dikes to +5 feet MLLW • Congressional action • WRDA amendment authorizes USACE to convey the Eastward Expansion to VPA • Next steps • Bid package for PVD installation on cross dikes will be advertised in June