Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 352 July 31, 2013. Jeff Florin Deputy Executive Director, Operations Virginia Port Authority. Agenda. NIT Gate Improvements CBP Screening Area OCR Portals Truck Canopy – New Lane
E N D
Capital Outlay Program & Facilities Maintenance Overview Board of Commissioners Session 352 July 31, 2013 Jeff Florin Deputy Executive Director, Operations Virginia Port Authority
Agenda • NIT Gate Improvements • CBP Screening Area • OCR Portals • Truck Canopy – New Lane • Truck Canopy – Gate Automation • PMT Rail Upgrades • APMT Trench Drain Repairs • APMT Reefer Plugs • Craney Island Eastward Expansion
NIT Gate Improvements • Security, interchange, and transfer zone automation, personnel shifted to remote facility • Automation, appointment system and remote processing • Improves cargo velocity, safety & efficiency • Estimated combined project cost: $10 M • Includes $4.1 M software
NIT Gate Improvements Project 2 Inbound OCR Portals Project 3 Truck Canopy Completed Chassis Service/Customer Service Areas Project 1 Completed Outbound Corridor Project 2 Completed Outbound OCR Portals Completed Transfer Zone
NIT Gate Improvements • CBP Screening Area and Outbound OCR Portal Building are complete • Truck canopy – new lane scale installed • Estimated project cost : $3.5 M • Contractor: EV Williams • Project is 75% complete • Project completion in September
NIT Truck Canopy – New Lane Truck scale frame being set
NIT Truck Canopy – New Lane Truck scale platform
NIT Truck Canopy Gate Automation • Infrastructure for gate automation • Estimated project cost : $300,000 • Contractor: Homeland Contracting • Pre-construction and metal fabrication underway • Project completion by October 2013
PMT Rail Upgrades • Replacement and upgrade to Class I railroad standards of the East and West rail leads into PMT • On hold pending tunnel contractor work • Estimated project cost : $900,000 • Contractor: H&B Railroad • Project completion by December 2013
PMT Rail Upgrades East rail lead West rail lead
APMT Projects Reefer plug installation Trench drain repairs
APMT Trench Drain Repairs • Localized repairs of APMT storm drains • Contractor: Eastern Waterproofing & Restoration of VA Co, LLC • Estimated project cost : $150,000 • Some demolition remaining • Project is 80% complete • Project completion mid-August
APMT Reefer Plugs • Installation of 60 reefer plugs • Discussions with APM ongoing • Estimated project cost : $915,000 • Contractor: JC Driskell
Craney Island Eastward Expansion • Cross Dike Stage 2A is complete • Placed1.54 MCY of sand on south and division cross dikes to +5 feet MLLW • Next steps • Bid package for $4 M PVD installation on cross dikes will be advertised in September 2013 • 16-acre oyster reef construction at Hoffler Creek to begin in August (Corps funded)
Craney Island Eastward Expansion Cross Dike Progress - June 25, 2013
Craney Island Eastward Expansion Cross dike as seen from the June 20thCraney Island boat tour