An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Muon Upgrade Simulations Status Alexei Safonov Texas A&M University

  2. Muon Upgrade Goals • Muon upgrades aim to achieve the following: • Sustain triggering at current thresholds up to |h|=2.4 • Increase offline muon identification coverage to |h|=3.5-4 • Maintain existing envelope by preventing or addressing aging effects • Goal of these studies: • Determine what kind of detectors we need and optimize parameters The “baseline” scenario since ECFA

  3. Organization and People • Muon TP editing group • Editor: Jay Hauser • Contact persons: • Consolidation of existing detectors: • DT: Cristina Bedoya DT • CSC: Armando Lanaro • RPC: Gabriella Pugliese • Simulation: Anna Colaleo, Alexei Safonov • New detectors: Archana Sharma, Marcello Abbrescia • Electronics: Paul Aspell • Integration into CMS and infrastructure, costing: TBD • Twiki: • https://twiki.cern.ch/twiki/bin/viewauth/CMS/HLLHCmuonPhase2

  4. Simulation Goals • Goals: • Quantify physics gains for each proposed element and groups of elements • Determine optimal detector parameters • Strategy: • Implement all components • Write initial algorithms and evaluate performance • Optimize parameters • Resolutions required, number of layers etc • Converge on baseline scenarios

  5. Deliverables • Trigger (focus on Level-1): • Trigger efficiency and rates for viable scenarios • For standalone Level-1 muon trigger rate versus momentum and eta • Input for itegration of standalone L1 muon with track trigger • Offline (focus on muon extension to |h|=4): • ME-0 stub reconstruction efficiency and fake rate • Provide “global muons” with ME-0 in CMSSW for physics studies • ME-0 + forward pixel extension track • Iterate over possible detector parameter scenarios using POG-style variable

  6. Software Integration Status • All components are there at the level of geometries in GEANT and digis • Work focusing on algorithm development and integration with other systems, dependent on status of other detectors: • E.g. forward pixel extension needs to be ready to do ME-0 studies

  7. Muon systems in GEANT • Many thanks to Yanna, Sven, Marcello, Cesare and Slava for a lot of hard work on implementing and validating the geometries in CMSSW

  8. Critical Tasks and Manpower: ME-0 • Deliverables: • Global Muons for physics studies • Muon efficiency, resolution and fake rate for a suitably optimized detector • CMSSW Geometry: • Close to being fully integrated • “Digi to global” chain is in progress • Simplified implementation and the overall framework: Northeastern (Nash, Trocino, Barberis) ~ 1.2 FTE, access to experts (M. Maggi, S. Krutelyov) • Some first results available, need to iterate with a realistic forward pixel extension setup • Studies critical for obtaining realistic results: • Track re-fit with muon hits included - NEU • Neutron backgrounds estimation in FLUKA – TAMU-Qatar (A. Castaneda) ~0.2 FTE • Proper segment reconstruction: a small fraction of M. Maggi (Bari) • Short-living background estimation: TBD • Optimization of segmentation and design, e.g. extra absorber between layers

  9. ME-0 Reconstruction Status • Plots use “emulated” stubs, but formats with full implementation version are similar, should be able to switch • Once done, will automatically get punch through backgrounds simulated (in GEANT) • Framework for global track+muonfit is mostly in place • More work on optimization as pixel tracking stabilized • Need to add neutron backgrounds D. Nash D. Troccino

  10. Neutron Induced Backgrounds • Able to make new geometries in FLUKA and started shielding studies • Preliminary estimates look hopeful: 100 kHz/cm2 is the worst ME-0 will see • Improvements with shielding are possible • Some questions about including hits due to to e+e- • Sensitivity measurements are ongoing (shoot electrons into GEM chambers in GEANT) – T. Maerschalk and A. Magnani • The plan is to properly convolute sensitivities and fluxes vs energy • For now use “magic numbers” for photon/neutron sensitivities from RPC A. Castaneda

  11. Neutron Backgrounds in Digitizer • Hits from long living backgrounds added at the digitization step • Updated rates for GE-1/1 and GE-2/1 with updated geometries (long/short) are targeted for SLHC11 • SLHC10 implied a simpler geometry, but this is a small difference • ME-0 hit rates are the highest, planned to be added in SLHC11 • We may need to use custom samples in the interim to properly estimate backgrounds for ME-0 R. Hadjiiska

  12. Critical Tasks and Manpower: GE1/1 & 2/1 • Deliverables: improved trigger performance, full offline reconstruction • Reconstruction in great good shape, no outstanding issues • A strong team in place – INFN-Bari, TAMU and TAMU-Qatar, Ghent, Sofia, Egypt, Saha • Remaining studies (not on critical path): • Custom reconstruction for high pTmuons (C. Calabria, Archie Sharma, A. Colaleo, S. Krutleyov) and seeding with GEMs (R. Radogna with help of experts: S. Krutelyov, D. Trocino) • More critical remaining studies: • Completion of the local trigger algorithm implementation – S. Dildick, S. Krutelyov, A. Tatarinov, T. Huang, A. Safonov • Proper integration of new features into the full muonTrackFinder - J. Lee, K. Choi (Seoul) starting to interface with Muon TF people with help from experts (S. Dildick, S. Krutelyov, A.S.) • Integration with the L1 Track Trigger – S. Krutelyov, A. Schneider (TAMU)

  13. Trigger: Overview • Critical piece for motivation • Redundancy and bending angle improve trigger • Many technical obstacles: • New upgraded L1 TF is not easily available • Focus on making “integrated” stubs to emulate improved redundancy, trick current CSC TF into taking these stubs and evaluate the improvement

  14. Impact of Redundancy on Trigger • Implementation of a detailed algorithm is in progress • Recover CSC stubs using added redundancy of GEMs • Can even improve the high eta part not covered by GEMs • Remove soft stubs (based on bending angle) at lower eta • Urgent, but can’t happen overnight • Work in progress • RE-3/1 and 4/1 are on even more critical path: we can provide examples, but implementation is not trivial • Need people and need time to develop expertise T. Huang, A. Tatarinov, S. Dildick • Very preliminary algorithm is there, need validation and improvements. Next steps: • Replicate onto YE-2/1 • Run through full system with TF (J. Lee)

  15. Critical Tasks and Manpower: RE3/1, 4/1 • Deliverables: • Introduce RE-3/1 and 4/1 into the trigger for improved performance • Evaluate performance and detector parameters (granularity and timing) • Geometry in CMSSW and digis: P. Verwilligen, I. Osborne, M. Maggi, L. Benucci • Tasks: • Evaluation of background fluxes – S. Costantini; followed by integration for digitization (R. Hadjiska) • Proper integration of digis into the full muonTrackFinder – technical implementation has many synergies with GE-1/1 and GE-2/1 • Critical to make a physics case, but there is a lot of work and debugging that needs to happen there • Dedicated performance and detector optimization studies (timing and position resolution) – likely based on dimuon triggers and signals like rare B decays to pairs of muons, background reduction studies using improved timing (G. Grenier, S. Aly, A. Abdelalim, A. Ali) • Less critical items: • Inclusion of recHits into the global reconstruction, fitting etc.

  16. Summary • The work building the case for Muon system upgrades in Technical Proposal is under way • Structure, people, understanding of the deliverables, and a realistic plan to get them delivered is in place • Shortage of qualified manpower is a definite issue, we are taking it into consideration in planning our work • Critical issues: • Full implementation of new components in the trigger • Dependent on other systems, i.e. there is no easy way to use upgraded L1 muon trigger • Falling back onto old trackfinder and implementing local trigger, make better stubs and feed them to the • Once POG-like elements are largely in, need to fully focus on physics-specific studies