MICE Status(with a UK slant) Paul Drumm, MICE CollaborationUK-NF June 2003
Proposal Status • International Peer Review of Proposal • Jan 2003 Interrogation & homework • May 2003 Blondel, Drumm & Long • Report out ? • Strong Endorsement …. • …equates to Scientific Approval • …some advice to RAL
Management Issues • RAL Management interface to MICE • Local Technical Team Leaders • Understand Costs • Independent Review • effort requirements e.g. during installation • capital costs • common fund discussion • Constitution under discussion
Proposal Status & UK Funding • PPARC/PPRP review of UK Proposal • May 2003 – accepted science case • there is an understanding of the importance of MICE both internationally • and of the importance & strength of the UK contributions • Strenuous discussions are taking place…
UK Funding • for the remainder of 2003/4 • there is a minimal programme of work to avoid loss of rôle (intellectual leadership) and to avoid further delays to the MICE programme • pparc/pprp & cclrc have to find funds to enable this years work to take place • Referees – (Willke, Froudivaux, Brook) • to scrutinise work plans for 2003/4 • expect an answer before end of June (PPRP next week?)
2004/…. • OST budget line to be bid for in collaboration with PPARC & CCLRC in 2004/…. Gateway • Total UK Cost estimate is £21.7M • indications are that £7.5M is available through OST • £10M may be a realistic target for OST/PPARC • other sources of funding need to be accessed
This is preferred option of JPB Risks associated with Solenoid taken by PSI Cryogenic infrastructure shared with MICE RF contribution taken in kind scenarios… • £7.5M • not enough for beam line • £10.0M • gets beam line – ~no UK involvement in MICE • £12.5M • involvement suffers • £15.0M • can achieve all goals if • £21.7M
Gateway Process • Gateway 0 – Strategic Assessment: Assessment of business need; Assessment of risk; initiation of an independent review team; review of the objectives and planned delivery; review of management structure and resource plans; • Gateway 1 – Business Justification: Assessment of the business case for MICE; review of risk management plans; review delivery plans; • Gateway 2 – Procurement Strategy: confirm procurement strategy; full funding availability; appropriate resources are in place; delivery plans, financial and management controls are in place and are realistic; • Gateway 3 – Investment Decisions: confirm that the procurement strategy has been followed; review and agree procurement decisions; review risk management & change control procedures; • ….4 & 5 GW 1 Papers with Wood & Halliday to take MICE to RCUK GW 1 Review in July Success implies approval for MICE
Gateway Process • Gateway 0 – Strategic Assessment: Assessment of business need; Assessment of risk; initiation of an independent review team; review of the objectives and planned delivery; review of management structure and resource plans; • Gateway 1 – Business Justification: Assessment of the business case for MICE; review of risk management plans; review delivery plans; • Gateway 2 – Procurement Strategy: confirm procurement strategy; full funding availability; appropriate resources are in place; delivery plans, financial and management controls are in place and are realistic; • Gateway 3 – Investment Decisions: confirm that the procurement strategy has been followed; review and agree procurement decisions; review risk management & change control procedures; • ….4 & 5 GW 2 Funding plans must be shown to be secure.
& Elsewhere • US submitted its MICE proposal in 2002 • no decision as yet • MuCool contribution for R&D • Italians made request (and obtained) funds for TPG work (? for solenoid) • elsewhere require formal approval from CCLRC
Despite the lack of funds…. • so far much progress has been achieved…. • absorber, coils & safety • beam line • RF power system • tracker choice
…absorber & coils integration • Moved away from original scheme in favour of a solution which decouples the coil & absorber bringing them together for final assembly - no sparks! • first review under discussion • where - states (FNAL?) • who - WG members + non - MICE panel • when - probably (my guess) start of 2004
…Beam Line • limited options at RAL (3 quads & 2 dipoles) • beam line layout drawn up • matching – potential solution seeking resources • front end fixed (in synchrotron room) • shortly proceed to clear hall (small step forward) • smaller hole to be cut in 2004
RF Power System • Scheme Draw up in outline • Single 1MW drive per cavity • flexible • advantage of phase & amplitude control • cost effective (despite 8 systems) • possible to upgrade to deliver 4MW to one cavity • Demonstrated 1.6 MW from “old” ISIS tubes • inventory of what can be reused RAL/CERN/? • Difference Schemes are similar in cost
RAL Scheme TH 116 ex RAL Tubes 10mW >1MW 5kW Low Level Control & RF Source SS Driver ex SPS 100 kW Cavity Roy Church
RAL RF Tube Tests • Stock of ~ 12 retired tubes • trial tube operated comfortably at 1.25 MW (~300 ms pulse at 50/32 Hz) • (peaks at ~1.6 MW) 260 ms IA ~110 A Field
Tracker Choice • Referees appointed – Grégoire & Summers • Criteria published • list of measurements & performance figures • to be agreed by proponents • Time Scale defined • October collaboration meeting
Conclusion • Strong Statement from IPRP (Astbury) • Funding Discussion in progress • signs are promising • Many Technical Issues still to be addressed – good progress • MICE is a strong collaboration & with our best endeavours MICE will succeed!