1 / 6

Project Administration

Detailed procedures for consultant selection, contract approval, engineering plan preparation, design standards, and construction processes on federally or State-funded projects. Includes key approvals, specifications, and compliance requirements for successful project execution.

oscarf
Download Presentation

Project Administration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Administration Mark Patterson, P.E.

  2. CONSULTANT SELECTION PROCEDURES - (2 MONTHS) • LG required to submit consultant selection procedures for all projects where federal or State funds will be used to reimburse consultants • General requirements Advertise in paper of highest regional circulation Qualifications-based selection Approved DBE/HUB goals No geographic preference • TxDOT will send LG example selection procedures • LG submits formal selection procedure to TxDOT for approval • TxDOT approves and authorizes LG to advertise • LG advertises / makes selection based on performance / qualifications • LG submits consultant selection information / TxDOT approves

  3. CONSULTANT CONTRACT - (2 TO 3 MONTHS) • TxDOT must approval contract between LG and consultant prior to execution • Approval of scope, contract format, and fee is required for all contracts where federal or State funds will be used • Approval of scope only is required for contracts that are not using federal funds • TxDOT sends LG sample standard contract • Contract must be either lump sum or cost plus, fixed fee • LG and consultant negotiate a contract and submit to TxDOT for review • TxDOT reviews /approves draft contract (meet if necessary) • LG and consultant finalize negotiations and send contract to TxDOT • District submits to TxDOT Audit office for review • If Audit approves, TxDOT submits final approval • LG executes contracts and schedules kick off meeting • LG sends TxDOT fully executed consultant contract • All supplemental agreements to consultant contract require prior approval

  4. ENGINEERING PLAN PREPARATION • Project design kick-off meeting is held • TxDOT assigns project manager • Plan review at 30, 60, 90, and 100 percent completion • TxDOT requires five month review of final plans • Plans will utilize TxDOT specifications and plan format for TxDOT lettings • Local specifications and plan format can be used for local lettings • Local lettings require TxDOT prior approval and adherence to local let guidelines

  5. DESIGN STANDARDS AND SPECIFICATIONS • Design must match design criteria in TxDOT’sOperations and Procedures Manual Chapter IV and AASHTO Guidelines • Deviation from design criteria requires exception / waiver approved by TxDOT • Pedestrian facilities must meet ADA standards • Bicycle facilities must meet AASHTO Bicycle Guidelines

  6. CONSTRUCTION • Projects may be let and managed by TxDOT or LG • Local let projects are reimbursed on a monthly basis depending upon the percentage contract completion • State lets: LG’s 20 percent match is due 60 days prior to letting • Field changes must be approved by TxDOT • TxDOT charges a construction management fee for TxDOT let projects • TxDOT and LG must agree on final acceptance of completed project • Many federal requirements must be met for TxDOT and local let projects • Local Government Project Procedures

More Related