Traffic Incident Management at the Big Dig

Traffic Incident Management at the Big Dig. Presenter: Kevin A Duffy- CA/T Manager of Emergency Planning & Response Kaduffy@bigdig.com. Difficulty Keeping the Roadways Traversing Boston Open and Flowing at Pre Construction Levels Daily Use of Project Footprint Areas: 339,000(minimum).

ryo
Download Presentation

Traffic Incident Management at the Big Dig

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Traffic Incident Managementat the Big Dig Presenter: Kevin A Duffy- CA/T Manager of Emergency Planning & Response Kaduffy@bigdig.com

  2. DifficultyKeeping the Roadways Traversing Boston Open and Flowing at Pre Construction LevelsDaily Use of Project Footprint Areas: 339,000(minimum) Traffic Incident Managementat the Big Dig Solution: Disseminate information quickly; simplify response, and execute with perfection

  3. Critical Elements of Success • Strategic • Great emphasis on traffic planning and congestion prevention • All lane alterations are scripted, using a three phase sign off, involving Construction, Traffic Engineering, and state/local authorities • Every effort in planning yielded one less incident

  4. Strategic (continued) • Established Traffic Disruptions as part of Project- wide Emergency Response System Guarantees that a quick, efficient method is continually in place to mitigate traffic difficulties As part of the ERS, multiple resources are dedicated to a traffic disruption, minimizing the time and scope of a traffic disruption. These include a field engineer, and a traffic engineer, along with emergency services.

  5. Including Traffic in the ERS Provided a Structure of Communication and Incident Management Control Among Non- Traffic Personnel. Field Staff Receive Instruction on Clearing Self- Created Disruptions. All Staff must Submit to Annual Refresher Training Strategic (continued)

  6. Strategic (continued) Non project related disruptions were handled through the same assessment criteria and communications links to external agencies as would be used for injuries, utility disruptions etc. Critical links were found by analyzing these non related events

  7. Continually Functional Operations CenterThe CA/T Ops Center Operates 24/7 Due to Construction Demands. A Less Ambitious Construction Project Would Only Require a Center Operating Around That Specific Construction Schedule Tactical Application of measures to minimize disruption

  8. Tactical • Video Monitoring • A picture is worth a thousand words • Sharing images with decision makers via intranet link • Rapid identification and classification of a traffic disruption • Occurring when a disruption is noticed by a construction engineer, operations monitor, or external notification • Classification to ensure standard response

  9. Tactical • Primary notification is delivered to a single point of contact in the field, who will coordinate the response • One point of coordination is a traffic engineer • Immediate independent notification of a Traffic Engineer when a disruption is reported or identified • Notification is made by the operations center, ensuring the passage of information

  10. Tactical • Exercise program with training and drills • All personnel will be ready for the real disruption