An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PENYIAPAN KERJA , PENYERAHAN KERJA DAN KECACATAN

  2. PENYIAPAN KERJA - FASAL 39 SYARAT-SYARAT KONTRAK • KERJA DIANGGAP TELAH MENCAPAI PENYIAPAN PRAKTIK • APABILA IA MEMENUHI FUNGSI PEMBINAAN ATAU BOLEH • DIDUDUKI DAN DIGUNAKAN WALAUPUN TERDAPAT SEDIKIT • BAKI YANG TAK SIAP • TARIKH SIAP DIKIRA SEBAGAI TARIKH BERMULANYA • TEMPOH TANGGUNGAN KECACATAN • SEBELUM DIPERAKUKAN SIAP , ADAKAN PEMERIKSAAN BERSAMA • KONTRAKTOR , WAKIL PP DAN WAKIL PELANGGAN • KERJA YANG DIPERAKUKAN SIAP AKAN DISERAH KEPADA JKR • PENYERAHAN KEPADA PELANGGAN TIDAK SEMESTINYA PADA • TARIKH YANG SAMA

  3. PERINGATAN DALAM KES DIMANA KERJA DIPERAKUKAN SIAP WALAUPUN MASIH TERDAPAT SEDIKIT BAKI YANG BELUM SIAP , SATU SENARAI BAKI YANG TERTINGGAL PERLU DIBERI KEPADA KONTRAKTOR BERSAMA-SAMA PERAKUAN SIAP KERJA . SERTAKAN JUGA SENARAI KECACATAN YANG PERLU DIBAIKI .

  4. PENGEDARAN PERAKUAN SIAP KERJA PERAKUAN SIAP KERJA BOLEH DITANDATANGANI OLEH WAKIL PP DAN HENDAKLAH DIHANTAR KEPADA KONTRAKTOR DAN SALINAN-SALINANNYA DIEDAR KEPADA SYARIKAT PENJAMIN , JABATAN PELANGGAN DSB.

  5. PERAKUAN TAK SIAP KERJA (Fasal 40) • Tiada asas kpd. EOT dan dikenakan LAD • PP mesti yakin dengan LAD, kontraktor mampu meneruskan kerja • Perbincangan dengan kontraktor • Prolonged LAD perlu dielakkan • Surat surat amaran dikeluarkan • Jkr 203x untuk kelulusan PP • Pengawasan rapi keatas projek yang dikenakan LAD.

  6. KEMUNGKIRAN KONTRAKTOR • JIKA KONTRAKTOR GAGAL MEMPERBAIKI DALAM TEMPOH • YANG DITETAPKAN TINDAKAN SEGERA HENDAKLAH • DIAMBIL UNTUK MEMPERBAIKI DENGAN CARA LAIN • a) BOLEH DIBUAT SENDIRI OLEH JABATAN • b) LANTIK ORANG LAIN UNTUK SIAPKAN • KOS PERBELANJAAN DIPEROLEHI DENGAN MEMOTONG • DARI BAKI YANG PERLU DIBAYAR KEPADA KONTRAKTOR. • SEKIRANYA BAKI TIADA ATAU TIDAK CUKUP , GUNAKAN • BON PELAKSANAAN ATAU SEBAGAI SUATU WANG • TUNTUTAN TERTENTU

  7. PERAKUAN SIAP MEMPERBAIKI KECACATAN • SEBAIK SAHAJA DLP BERAKHIR DAN SEMUA KEROSAKAN • DIBAIKI , LAPORAN KEATAS KONTRAK YANG SUDAH SIAP • BOLEH DIKELUARKAN • PENGELUARAN SIJIL PERAKUAN MEMPERBAIKI KECACATAN • MENANDAKAN TAMATNYA OBLIGASI KONTRAKTOR DIBAWAH • KONTRAK . • 3. DENGAN ITU LIABILITI PENGGERENTI DILEPASKAN .

  8. SIAP BERBAHAGIAN-BAHAGIAN - FASAL 41 • KERAJAAN DIBENARKAN MENETAP SUPAYA KERJA DISIAPKAN • DALAM SEKSYEN ATAU BAHAGIAN • SEKSYEN ATAU BAHAGIAN BERKENAAN HENDAKLAH • DIKENALPASTI DAN DISEBUT DIDALAM KONTRAK / TENDER • JIKA SIAP BERBAHAGIAN DINYATAKAN , MAKA FASAL-FASAL • TERTENTU HENDAKLAH DIPAKAI SEOLAH-OLAH TIAP-TIAP • SATU SEKSYEN ATAU BAHAGIAN ITU ADALAH KONTRAK • BERASINGAN . FASAL YANG TERLIBAT ADALAH :- • FASAL 39 - PENYIAPAN KERJA • FASAL 40 - GANTIRUGI KERANA TAK SIAP • FASAL 43 - KELAMBATAN DAN LANJUTAN MASA • FASAL 45 - KECACATAN SELEPAS SIAP • KEDUDUKAN INSURANS KERJA , BON PELAKSANAAN DAN • BAYARAN MUKTAMAD. TIDAK BERUBAH . TEMPOH • DLP BERMULA DARI TARIKH BAHAGIAN BERKENAAN • DIPERAKU SIAP

  9. PENDUDUKAN SEPARA - FASAL 42 • KERAJAAN BOLEH AMBIL MILIK DAN MENDUDUKI MANA • MANA BAHAGIAN KERJA YANG TELAH SIAP SEBELUM • PENYIAPAN PRAKTIKAL SELURUH KERJA • PERLU PERSETUJUAN KONTRAKTOR • SIJIL PERAKUAN PENDUDUKAN SEPARA HENDAKLAH • DIKELUARKAN DALAM MASA 7 HARI DARI TARIKH PEMILIKAN • PENDUDUKAN SEPARA KERJA TERSEBUT • NYATAKAN NILAI ANGGARAN BAHAGIAN YANG DIAMBIL MILIK • DLP BAGI BAHAGIAN YANG DIAMBIL MILIK BERMULA DARI • TARIKH KERAJAAN MENGAMBIL MILIK DAN MENDUDUKI • BAHAGIAN BERKENAAN • LAD AKAN DIKURANGKAN MENGIKUT KADAR JUMLAH NILAI • BAHAGIAN DIAMBIL MILIK BERBANDING HARGA KONTRAK

  10. PENDUDUKAN SEPARA - FASAL 42 • 1. PERUNTUKAN KONTRAK MENGENAI INSURANS DAN • PELEPASAN BON PELAKSANAAN ADALAH TIDAK BERUBAH • WALAUPUN BERLAKU PENDUDUKAN SEPARA KONTRAKTOR • MESTI SENTIASA MENGINSURANSKAN KERJA SEPERTI • KETETAPAN FASAL 36 • BON PELAKSANAAN HANYA AKAN DILEPASKAN SETELAH • SEMUA PEMBAIKAN KECACATAN DIBUAT ATAU SELEPAS • SIJIL MEMPERBAIKI KECACATAN DIKELUARKAN

  11. PELEPASAN BON PELAKSANAAN - SPP 11 / 99 • JAMINAN BANK • PP DIBENARKAN MELEPASKAN 50 % DARIPADA NILAI JAMINAN • BANK SETELAH PERAKUAN SIAP KERJA DIKELUARKAN • PP PERLU MAKLUM PERKARA INI DAN KONTRAKTOR • BOLEH BERURUSAN DENGAN BANK BAGI MENGGANTI • JAMINAN ASAL DENGAN JAMINAN BARU YANG NILAINYA • BERSAMAAN DENGAN 50 % DARI JAMINAN ASAL • SETELAH JAMINAN BARU DITERIMA , PP BOLEH PULANGKAN • JAMINAN ASAL

  12. 2. JAMINAN INSURANS • PP JUGA BOLEH MELEPASKAN 50 % DARIPADA NILAI • JAMINAN INSURANS KEPADA KONTRAKTOR SEBAIK SAHAJA • PERAKUAN SIAP KERJA DIKELUARKAN • PP PERLU MEMAKLUMKAN PERKARA INI DAN KONTRAKTOR • BOLEHLAH BERURUSAN DENGAN SYARIKAT INSURANS • UNTUK MENGGANTIKAN JAMINAN ASAL DENGAN YANG BARU • BERSAMAAN 50 % DARI JAMINAN ASAL • SETELAH JAMINAN BARU DITERIMA , JAMINAN YANG ASAL • BOLEHLAH DIKEMBALIKAN

  13. WANG JAMINAN PELAKSANAAN • PP BOLEH MELEPASKAN 50 % DARI WANG JAMINAN • PELAKSANAAN YANG DITAHAN SETELAH PERAKUAN • SIAP KERJA DIKELUARKAN • BAKI WANG JAMINAN PELAKSANAAN SEBANYAK 50 % • LAGI BOLEH DIDILEPASKAN SEKIRANYA KONTRAKTOR • MENGEMUKAKAN JAMINAN BANK YANG SAMA NILAI • DENGAN WANG JAMINAN PELAKSANAAN

  14. WANG JAMINAN PELAKSANAAN (samb.) • BAKI BON PELAKSANAAN SEBANYAK 50 % LAGI ( SAMADA • DALAM BENTUK JAMINAN BANK / INSURANS / WANG • JAMINAN PELKSANAAN ) HENDAKLAH DILEPASKAN 12 BULAN • SELEPAS TEMPOH TANGGUNGAN KECACATAN ATAU SETELAH • PERAKUAN SIAP MEMPERBAIKI KECACATAN DIKELUARKAN