120 likes | 198 Views
This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentation In Slide Show, click on the right mouse button Select “Meeting Minder” Select the “Action Items” tab
E N D
This presentation will probably involve audience discussion, which will create action items. Use PowerPoint to keep track of these action items during your presentation • In Slide Show, click on the right mouse button • Select “Meeting Minder” • Select the “Action Items” tab • Type in action items as they come up • Click OK to dismiss this box • This will automatically create an Action Item slide at the end of your presentation with your points entered. ENS Project Status Søren Poulsen EL-TC presentation February 29, 2000
Status Summary • New ENS • ENS hardware and software is installed in B212 • System is operational for communication testing • SEPAM and MICENE data are integrated (SE1) • Existing System • Old system is still fully operational • Some data can be seen with both system
Examples - screen-shots (1) • Synoptic diagrams (work in progress…) • CERN, Point 1 (layout, diagram) • Alarm list • Descriptions, filtering, acceptance • Real-time trends • Power, current of feeder
Examples - screen-shots (2) • Archives… • Nothing yet... • Lists • Events • Data points • Time tags • Log-in • Authentication
Progress • Basic system • Development of CERN Front End interface • Development of MICENE and SEPAM integration • Other (simpler) equipment to be integrated soon... • System configuration (database) • Development of database definitions for equipment • Development of synoptic diagrams etc.
Attention Areas • Major difficult areas • Integration of CERN non-industrial equipment with industrial supervisory system • Understanding of the CERN equipment required by the contractor • Documentation required and produced • Other areas • Integration in CERN environment • Integration with other CERN systems (CAS)
Schedule • ENS First release • Operational from April 3rd • Covers LEP Point 1 (SE1) • Covers integration with CERN systems • RTU Pilot Project • Operational from April 3rd • SEM11 MICENEs replaced by RTU system • Integration with ENS system
Training • To be provided by contractor (end of March) • General training in overall supervision system • Special training in RTU system • Provided for users involved in operation • Everybody needs to become familiar with system from now on… • Special introduction to be provided to people directly involved
Operator terminals and user interfaces • Possibilities • Modern X terminals • “dedicated” PC-based terminals • ...CERN recommendation pending (support) • Proposed new operator terminals • Dedicated X terminal for Point 1 (SE1) • Dedicated X terminal for 104 “Control room” • Any NICE office PC can be used
Operational changes (1) • General alarm supervision: CAS • Alarms from SE1 to be included in new “category tree” • No SE1 alarms in old “category tree” • Detailed supervision: ENS • Supervision via new facilities (synoptics, etc.) • No SEM11 information in OLD system
Operational changes (2) • Local control • RTU system in SEM11 • Independent of ENS • Local control in the case of disturbances • Synoptic diagrams • Local alarm lists
What to do ? • Personnel involved in operation • I will arrange for a personal demonstration and introduction to operation • Personnel NOT involved in operation • Request personal demonstration • Request setup of operator terminal (PC) • Everybody • Give feedback and comments