RECUPERAÇÃO DA BACIA DE DISSIPAÇÃO

RECUPERAÇÃO DA BACIA DE DISSIPAÇÃO. EROSÃO NO TALUDE EROSÃO SOB A FUNDAÇÃO DO MURO EROSÃO SOB A FUNDAÇÃO DO PILAR P-4 DA PONTE DA CPTM EROSÃO SOB A LAJE DAS COMPORTAS DE FUNDO. O APARECIMENTO DO PROBLEMA. VISTA DA EROSÃO. DETALHE DA EROSÃO. CONTROLE DE RECALQUES PINOS DE RELALQUES

sherry
Download Presentation

RECUPERAÇÃO DA BACIA DE DISSIPAÇÃO

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RECUPERAÇÃO DA BACIA DE DISSIPAÇÃO

  2. EROSÃO NO TALUDE EROSÃO SOB A FUNDAÇÃO DO MURO EROSÃO SOB A FUNDAÇÃO DO PILAR P-4 DA PONTE DA CPTM EROSÃO SOB A LAJE DAS COMPORTAS DE FUNDO O APARECIMENTO DO PROBLEMA

  3. VISTA DA EROSÃO

  4. DETALHE DA EROSÃO

  5. CONTROLE DE RECALQUES PINOS DE RELALQUES MARCOS SUPERFICIAIS CONTROLE DE DESLOCAMENTOS HORIZONTAIS ESTAÇÃO TOTAL CONTROLE DA ROTAÇÃO DO MURO E DO PILAR NAS DIREÇÕES TRANSVERSAL E LONGITUDINAL À LINHA FÉRREA ELETRONÍVEL CONTROLE DAS VIBRAÇÕES SISMÓGRAFO (24 HORAS) O MONITORAMENTO

  6. EXECUÇÃO DAS LEITURAS NOS PINOS DE RECALQUES NO PILAR

  7. PINO PARA CONTROLE DE RECALQUE DO MACIÇO

  8. ELETRONÍVEL

  9. CONSULTOR PARECER IPT DIVERSAS ALTERNATIVAS COM CUSTOS E PRAZOS DIFERENTES SOLUÇÕES TÉCNICAS

  10. O MENOR CUSTO O MENOR PRAZO DE EXECUÇÃO (PREVISÃO 40 HORAS) CONCRETAGEM SUBMERSA (PREVISÃO 3000 m³) SOLUÇÃO TÉCNICA ADOTADA

  11. SOLUÇÃO ADMINISTRATIVA A EMAE PROPÕE QUE O DAEE EXECUTE AS OBRAS O DAEE CONCORDA COM SOLUÇÃO TÉCNICA MAS NÃO CONCORDA EM EXECUTAR A OBRA 3)A EMAE, PARA DIMINUIR OS CUSTOS , PROPÕE UMA SOLUÇÃO MAIS LOCALIZADA VISANDO PRESERVAR PRINCIPALMENTE O PILAR DA CPTM 4) A EMAE RESOLVE EXECUTAR A OBRA COM RECURSOS PRÓPRIOS, CONTRATANDO APENAS A MÃO DE OBRA ESPECIALIZADA E EQUIPAMENTOS ESPECÍFICOS

  12. COM A DECISÃO DE SE FAZER GRANDE PARTE DOS SERVIÇOS COM RECURSOS PRÓPRIOS, VÁRIAS ÁREAS DA EMPRESA FORAM ACIONADAS E PROVIDENCIARAM : PARTICIPAÇÃO DE OUTRAS ÁREAS DA EMAE

  13. GUINDASTE PLATAFORMAS FLUTUANTES AMBULÂNCIA REFEIÇÕES TELEFONES CONTEINERS INSTALAÇÕES ELÉTRICAS MERGULHADORES SEGURANÇA DO TRABALHO SEGURANÇA PATRIMONIAL OPERAÇÃO DO SISTEMA HIDRÁULICO TOPOGRAFIA E BATIMETRIA RADIO COMUNICADORES

  14. AMBULÂNCIA UTI COM EQUIPE MÉDICA

  15. CONTEINERS

  16. PREPARAÇÃO DAS PLATAFORMAS PARA EXECUÇÃO DOS SERVIÇOS

  17. POSICIONAMENTO DAS PLATAFORMAS E GUINCHO

  18. O POSICIONAMENTO DAS PLATAFORMAS O Nº E POSiCIONAMENTO DAS TREMONHAS A PRODUÇÃO HORÁRIA PREVISTA O PLANEJAMENTO DO SISTEMA HIDRÁULICO O HORÁRIO DOS SERVIÇOS A LOGÍSTICA DO TRÂNSITO A DISPOSIÇÃO DOS EQUIPAMENTOS A PRODUÇÃO DAS CENTRAIS DE CONCRETO PLANEJAMENTO DO SERVIÇO

  19. PREPARAÇÃO E POSICIONAMENTO DAS PLATAFORMAS BOMBAS DE CONCRETO TELESCÓPICAS CONTROLE TECNOLÓGICO BETONEIRAS INÍCIO DA CONCRETAGEM (02:40h DO DIA 31/08/2002) TÉRMINO DA CONCRETAGEM (06:40h DO DIA 01/09/2002) EXECUÇÃO DOS SERVIÇOS

  20. FIXAÇÃO DO SUPORTE DO GUINCHO ELÉTRICO NA PLATAFORMA

  21. POSICIONAMENTO DA 1ª PLATAFORMA

  22. POSICIONAMENTO DA 2ª PLATAFORMA

  23. ESCADA DE SEGURANÇA E ACESSO ÀS PLATAFORMAS

  24. PLATAFORMAS E TREMONHAS POSICIONADAS

  25. RETIRADA DE AMOSTRA PARA EXECUÇÃO DO “SLUMP TEST”

  26. AFERIÇÃO DO CONTROLE TECNOLÓGICO DO CONCRETO “SLUMP TEST”

  27. COMPROVAÇÃO DOS VALORES DO “SLUMP TEST” ESPECIFICADOS

  28. POSICIONAMENTO DAS BETONEIRAS JUNTO ÀS BOMBAS (INÍCIO DA CONCRETAGEM)

  29. DETALHE DO BOMBEAMENTO DO CONCRETO

  30. DETALHE DO LANÇAMENTO DO CONCRETO

  31. DETALHE DA FIXAÇÃO DO MANGOTE DA BOMBA NA TREMONHA

  32. EXECUÇÃO DO LANÇAMENTO DO CONCRETO

  33. CONFIGURAÇÃO FINAL

  34. DE ACORDO COM AS INFORMAÇÕES DO BANCO DE DADOS DAS “CONCRETEIRAS”, O VOLUME DE 2240 m³ BOMBEADO EM 28 HORAS, COM PRODUÇÃO CONTÍNUA DE 80 m³/h, É O MAIOR JÁ REGISTRADO NA CIDADE DE SÃO PAULO

  35. TRABALHO ININTERRUPTO INJEÇÕES SOB O MURO, LAJE E PILAR NENHUM ACIDENTE, COM OU SEM LESÃO REGISTRADO APRIMORAMENTO DE KNOW HOW PELA EQUIPE PRÓPRIA PONTOS POSITIVOS