An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CBD Roadworks Program Management Peter Egan Main Roads Western Australia AITPM 19 June 2014

  2. Background • December 2012 – State Government decides coordinated approach required • Large Scale projects • Elizabeth Quay • Perth City Link • Perth Stadium • CBD Roadworks Steering Group • Working Group(s) • Programming Group

  3. CBD Roadworks Program Management Objectives • Coordinate major roadworks to minimise disruption to traffic • First point of contact for major roadworks info in and around the CBD • Provide advice & assist in traffic management approvals • Facilitate regular stakeholder meetings and workshops • Collate and share information • Provide traffic planning maps to assist in journey planning • Provide communications • Monitor and optimise performance at traffic signals in the CBD - TOC • Dispute resolution

  4. Communications • CBD Communications Control Group • MRWA, PTA, Transport, MRA, CoP, Water Corp • Radio – Targeted and live crosses • Australian Traffic Network channel 7 and 9 direct from TOC • Newspaper • Twitter • Right Move Perth Phone App - DoT • CBD Roadwork Maps – MRWA website (3,500 visits) • Get the Bigger Picture – Interactive Perth Roadwork Map • Perth Now – Perth traffic page, updated via twitter • Customer Information Centre (138 138 ) available 24/7 • Variable message and physical signs

  5. CBD Roadwork’s Interactive Website page

  6. CBD Roadwork’s Gantt Chart

  7. Wellington StreetPerth City Link

  8. Notice Requirements • Inadequate time to review TM proposals • TM is an important requirement – seems to be left to last minute • MRWA have notice requirements for lane closures and for advertising requirements • We need time to consider other options…..

  9. Innovative Thinking • Night work and double shifts – get in, get out • Full road closures – If required we can examine closing the road for the entire weekend or number of nights. More pain but not dragged out • Close the road completely over a long weekend or during school holidays • Close one lane at a time – keep access open • Build temporary roads on the ultimate alignment - Gateway • What's best for the travelling public? – Not always the best for the construction program

  10. Lessons Learnt • Generally Project Managers are focused on the Project e.g. Cost, Time etc. • TM is a very important part of the Project • We can assist if given enough time • Projects can be moved if agencies are given enough time • Approval for TMP’s is not a given and the process takes time. We can assist with TMP’s and considering alternative options • AWTM, RTM, PM, Traffic signal experts, Councils, sit down early and discuss issues – Establish working group to open lines of Communication • Use lessons learnt from other projects – traffic volumes may seem high but there are always options, Each situation is unique

  11. Questions?